SB 1304Sesión 2025

Qué cambió entre versiones

22 párrafos cambiaron+56 palabras agregadas−36 eliminadas

El texto resaltado se agregó en la versión más reciente. El texto tachado se eliminó.

Florida Senate

-

2025

CS for SB 1304

By

Senator Bradley

the Committee on Regulated Industries; and Senator Bradley

6-01411B-25 20251304__580-02615-25 20251304c1

1 A bill to be entitled

15 párrafos sin cambios

2 An act relating to solar facilities; amending s.

3 163.3205, F.S.; revising legislative intent; defining

4 the terms “agricultural land” and “decommissioned”;

5 authorizing a county to adopt an ordinance requiring

6 that certain solar facilities be properly

7 decommissioned under certain circumstances;

8 authorizing a county to presume that a solar facility

9 has reached the end of its useful life under certain

10 circumstances; authorizing a solar facility owner to

11 rebut the presumption in a certain manner; authorizing

12 a county to require certain financial assurance and

13 certain updates from a solar facility owner;

14 authorizing a county to take action to complete the

15 decommissioning of a solar facility under certain

16 circumstances; deleting a provision providing that a

17 solar facility is a permitted use in certain land use

18 categories and zoning districts and is subject to compliance

19 compliance with certain requirements; deleting a provision authorizing

20 provision authorizing a county to adopt an ordinance specifying certain

21 specifying certain requirements for solar facilities; revising

22 revising applicability; amending s. 163.3208, F.S.; deleting a

23 deleting a provision exempting solar facility substations from

24 substations from the electric substations for which local governments

25 local governments may adopt and enforce certain land development

26 development regulations; providing an effective date.

27

93 párrafos sin cambios

28 Be It Enacted by the Legislature of the State of Florida:

29

30 Section 1. Section 163.3205, Florida Statutes, is amended

31 to read:

32 163.3205 Solar facility approval process

and

33

decommissioning requirements

.—

34 (1) It is the intent of the Legislature

t

hat agricultural

35

land used for a solar facility be returned to its original state

36

and be viable for agricultural use at the end of the life of the

37

solar facility

to encourage renewable solar electrical

38

generation throughout this state. It is essential that solar

39

facilities and associated electric infrastructure be constructed

40

and maintained in various locations throughout this state in

41

order to ensure the availability of renewable energy production,

42

which is critical to this state’s energy and economic future

.

43 (2) As used in this section, the term

:

44

(a)

“Agricultural land” means land within:

45

1.

A

n a

rea categorized as agricultural land in a local

46

government comprehensive plan

. Such categorization includes

any

47

agricultural land use category; or

48

2.

An agricultural zoning district within an unincorporated

49

area.

50

(b) “Decommissioned” means the removal of a solar facility

51

and return of agricultural

land

that

was

used for

such

solar

52

facility

to an agriculturally useful condition similar to that

53

which existed before construction of the solar facility,

54

including the removal of above-surface facilities and

55

infrastructure that do not serve a continuing purpose.

56

(c)

“Solar facility” means a production facility for

57 electric power which:

58

1.

(a)

Uses photovoltaic modules to convert solar energy to

59 electricity that may be stored on site, delivered to a

60 transmission system, and consumed primarily offsite.

61

2.

(b)

Consists principally of photovoltaic modules, a

62 mounting or racking system, power inverters, transformers,

63 collection systems, battery systems, fire suppression equipment,

64 and associated components.

65

3.

(c)

May include accessory administration or maintenance

66 buildings, electric transmission lines, substations, energy

67 storage equipment, and related accessory uses and structures.

68 (3)

For a solar facility over 2 megawatts which is

in gross capacity

69

as defined in s. 403.503

which is constructed on agricultural land, a county may adopt an

70

land, a county may adopt an ordinance requiring that the

solar

facility be properly

71

facility be properly decommissioned upon the facility reaching the end of its useful

72

life.

the end of its useful life.

73

136 párrafos sin cambios

(a) A county may presume that a solar facility has reached

74

the end of its useful life if:

75

1. The solar facility fails to produce power for a period

76

of 12 months after construction of the solar facility has been

77

completed. This 12-month period does not include a period in

78

which the solar facility does not produce power due to a

79

disaster or other event beyond the control of the facility

80

owner; or

81

2. The solar facility has been abandoned. A solar facility

82

is considered abandoned if:

83

a. After commencement of the solar facility’s construction

84

but before completion, no significant construction of the

85

facility occurs for a period of 24 months; or

86

b. After becoming nonoperational due to a disaster or other

87

event beyond the control of the facility owner, no significant

88

reconstruction of the solar facility occurs for a period of 12

89

months.

90

(b) The presumptions provided under paragraph (a) may be

91

rebutted by the solar facility owner providing the county with a

92

plan, schedule, and adequate assurances for the continuing

93

construction or operation of the solar facility.

94

(c) Counties may require financial assurance from a solar

95

facility owner in the form of a bond, an irrevocable letter of

96

credit established pursuant to chapter 675, a guarantee by the

97

solar facility owner’s parent company, or another financial

98

device deemed adequate by the county to cover the estimated cost

99

of decommissioning the solar facility. The solar facility owner

100

must provide the information necessary for the county to

101

establish the estimated cost of such decommissioning.

102

(d) Counties may require a solar facility owner to provide

103

updates no less than every 5 years on the estimated cost of

104

decommissioning and financial assurance provided under paragraph

105

(c). Any financial assurance provided under paragraph (c) may be

106

adjusted in accordance with the updates to such estimated cost.

107

(e) If a facility owner does not complete decommissioning

108

as required by county ordinance, the county may take action to

109

complete the decommissioning, including action to require

110

forfeiture of the financial assurance provided under paragraph

111

(c). A county

shall

allow a solar facility owner at least 12

112

months to commence decommissioning and 24 months to complete

113

decommissioning before taking such action

A solar facility shall

114

be a permitted use in all agricultural land use categories in a

115

local government comprehensive plan and all agricultural zoning

116

districts within an unincorporated area and must comply with the

117

setback and landscaped buffer area criteria for other similar

118

uses in the agricultural district

.

119

(4) A county may adopt an ordinance specifying buffer and

120

landscaping requirements for solar facilities. Such requirements

121

may not exceed the requirements for similar uses involving the

122

construction of other facilities that are permitted uses in

123

agricultural land use categories and zoning districts.

124

(4)

(5)

This section does not apply to any site that was the

125 subject of an application to construct a solar facility

126 submitted to a local governmental entity before July 1,

2025

127

2021

.

128 Section 2. Subsection (3) of section 163.3208, Florida

129 Statutes, is amended to read:

130 163.3208 Substation approval process.—

131 (3) Electric substations are a critical component of

132 electric transmission and distribution.

Except for substations

133

in

s. 163.3205(2)(c)

,

Local governments may adopt and enforce

134 reasonable land development regulations for new and existing

135 electric substations, addressing only setback, landscaping,

136 buffering, screening, lighting, and other aesthetic

137 compatibility-based standards. Vegetated buffers or screening

138 beneath aerial access points to the substation equipment

may

139

shall

not be required to have a mature height in excess of 14

140 feet.

141 Section 3. This act shall take effect July 1, 2025.