2026 SESSION

HOUSE SUBSTITUTE

INTRODUCED

26107310D26105396D

HOUSE BILL NO. 1065

AMENDMENT IN THE NATURE OF A SUBSTITUTE

Offered January 14, 2026

Prefiled January 14, 2026

A BILL to amend the Code of Virginia by adding in Chapter 23 of Title 56 a section numbered 56-596.7, relating to electric utilities; surplus interconnection service sites.

—————

Patrons—Hernandez, Anthony, Clark, LeVere Bolling, Carr, Cousins and Tran

—————

(ProposedReferred by the Houseto Committee on Labor and Commerce

on ________________)

(Patron Prior to Substitute—Delegate Hernandez)

A BILL to direct certain electric utilities to undertake comprehensive assessments and establish pilot programs related to surplus interconnection service; report.

—————

Be it enacted by the General Assembly of Virginia:

1. § 1. That each Phase I and Phase II Utilit y shall undertake a comprehensive assessment of available interconnection capacity at each such utility's existing and planned intermittent electric generation facilities locate d in the Commonwealth. Such assessment shall (i) identify all of each such utility's solar generation facilities located in the certificated service territory of the Phase I or Phase II Utility that are interconnected pursuant to an interconnection agreem ent or that have executed an interconnection agreement; (ii) determine the capacity interconnection rights of each such solar generation facility pursuant to the filed or executed interconnection agreement; and (iii) determine how much, if any, surplus interconnection service may be available at each such solar ge neration facility's point of interconnection. In conducting such assessment, a Phase I Utility shall identify at least two points of interconnection and a Phase II Utility shall identify at least five points of interconnection at which utilizing surplus interconnection service may be feasible. In conducting such assessment and identifying such points of interconnection , the Phase I and Phase II Utility shall consider relevant factors, including the relative resource value expected from utilizing surplus interconnection service at each such point of interconnection and the potential for deferring other investments in electric gen eration or transmission infrastructure, the proximity to areas of highly concentrated electric load, environmental impacts, impacts to the existing generation facility, and the receptivity o f local permitting. Additionally, the Phase I and Phase II Utility shall identify planned intermittent electric generation facilities operating pursuant to a power purchase agreement with the Phase I or Phase II Utility and shall, to the extent such information is reasonably available, list for each such facility the capacity interconnection rights and potential surplus interconnection service that may be available at the point of interconnection for such facility. The Phase I and Phase II Utility shall submit a report to the State Corporation Commission (the Commission) no later than January 1, 2027, describing the results of the as sessments conducted pursuant to this section , including the preliminary identification of specific points of interconnection as required under this section .

§ 2. That a Phase I Utility shall establish a pilot program with a capacity of 100 megawatts and a Phase II Utility shall establish a pilot prog ram with a capacity of 500 megawatts for energy storage resources and solar generation facilities , to the extent the Commission finds solar generation facilities to be practicable, that utilize surplus interconnection service and, as part of such pilot program s , evaluate the feasibility, effectiveness, and reliability benefits of such resources and facilities utilizing surplus interconnection service. As part of such pilot programs, the Commission shall approve an independent auditor to participate in the formulation of a request for proposals, including by formulating criteria for the request for proposals and reviewing results for energy storage resources and solar generation facilities to utilize surplus interconnection service, no later than March 1, 2027. Such request for proposals shall include proposals for (i) power purchase agreement projects that seek to utilize an existing point of interconnection of a Phase I or Phase II Utility for surplus interconnection service under an additional energy storage resource system tolling agreement and (ii) projects located adjacent to a utility-owned solar generation facility that seeks to utilize surplus interconnection service at an existing point of interconnection of a Phase I or Phase II Utility for acquisition. The results of such request for proposals shall b e submitted to the Commission in each such utility's 2027 application required under subdivision D 4 of § 56-585.5 of the Code of Virginia to request the necessary approvals to construct or acquire capacity from the selected resources and facilities. Nothing in this section shall prohibit a Phase I or Phase II Utility from constructing, acquiring, or procuring more than 100 megawatts or 500 megawatts, respectively, of surplus interconnection service project capacity , provided that the utility receives approval from the Commission for such additional capacity pursuant to §§ 56-580 and 56-585.1 of the Code of Virginia.

1. That the Code of Virginia is amended by adding in Chapter 23 of Title 56 a section numbered 56-596.7 as follows:

§ 56-596.7. Surplus interconnection service sites .

§ 3A. As used in this actsection:

"Capacity interconnection rights" means the permissions granted to entities to connect their energy generation facilities to the electric grid system, allowing such facilities to transmit a specified amount of generation capacity to the electric grid system.

"Eligible site" means any point of interconnection identified by the Commission as having surplus interconnection service.

"Interconnection agreement" means an interconn ectioninterconnection service agreement or generator interconnection agreement to interconnect to the transmission system operated by thePJM regional transmission entity Interconnection.

"Interconnection service" means the same as that term is defined in 1 6 U.S.C. § 2621(d)(15).

"Phase I Utility" and "Phase II Utility" havemean the same meanings as providedsuch terms are defined in subdivision A 1 of § 56-585.1 of the Code of Virginia.

"Planned intermittent generation facility" means any project for which a Phase I or Phase II Utility has signed an interconnection agreement with the regional transmission entity or a small generator interconnection agreement.

"Surplus interconnection service" means any unused or unnecessary portion of interconnection service capacity at a point of interconnection establishe destablished in ana n interconnection agreement , such that if such surplus interconnection service is utilized, the total amount of interconnection service capacit ycapacity at such point of interconnection remains the same.

"Zero-carbon electricity" means the same as that term is defined in § 56-585.5.

B. E ach Phase I and Phase II Utility shall conduct a request for proposals for the development of zero-carbon electricity or energy storage resources on eligible sites. Such request shall quantify the amount of surplus interconnection service at each eligible site and shall be publicly announced and made available for public review on such utility's website at least 45 days before the closing of such request. Such reques t shall contain , at a minimum, the following information:

1. T he size, type, and timing of any resource with which the utility seeks to use surplus interconnection service at each eligible site ;

2. A ny minimum threshold s that must be met by applicants;

3. Any assumptions or standards to be used by the utility in the proposal evaluation process, including environmental emission standards ;

4. Detailed i nstructions for preparing proposals to ensure consistent evaluation ;

5 . T he preferred location of additional capacity; a nd

6. I nformation concerning the factors involved in determining the price and non-price criteria used for selecting winning proposals . The utility may evaluate responses to such request based on any criteria that it deems reasonable but shall at a minimum consider in its selection process (i) the age of the applicant's existing generation facilities; ( ii ) the demonstrated financial viability of the proposal and the applicant ; ( iii ) the applicant's prior experience in the field; ( iv ) the proposal's location and impact on the transmission grid; ( v ) any benefits to the Commonwealth that are associated with the proposal , including regional economic development and the use of goods and services from businesses in the Commonwealth ; ( vi ) the environmental impacts of proposed resources, including impacts on air quality within the Commonwealth and the carbon intensity of the utility's generation portfolio; and ( vii ) any potential cost savings for ratepayers due to the utilization of surplus interconnection service compared to the development of new generation facilities or the construction of new transmission or distribution infrastructure.

C. Each Phase I and Phase II Utility shall select (i) at least 65 percent of proposals received in response to such request or (ii) a combination of such proposals that includes a total of at least 1,000 megawatts of generation capacity , whichever represents a greater total generation capacity, including proposals for power purchase agreements and utility acquisitions , to submit to the Commission for approval within s ix months after the deadline for proposal submission . Any proposal selected by a Phase I or Phase II Utility pursuant to this subsection shall be considered a critical reliability resou rce.

D. No Phase I or Phase II Utility shall petition to construct a new electric generating facility that emits carbon dioxide pursuant to subdivision A 5 c of § 56-585.1 or to upgrade or extend the operational life of such facility pursuant to subdivision A 6 of § 56-585.1 until all proposals selected pursuant to subsection C have been awarded. No such petition shall b e approved unless the Commission determines that (i) the petition seeks to operate such facility to use surplus interconnection service at an eligible site or (ii) no surplus interco nnection service exists that would provide a more cost-effective alternative to c onstructing such facility.

E. An e nergy storage resource may charge directly from the electric distribution grid without additional interconnection or permitting requirements beyond those applicable to the incumbent utility or eligible site , except that no energy storage resource shall charge directly from any electric generating facility that emits carbon dioxide.

F. A critical reliability resource that is located entirely behind the point of interconnection requiring a conditional use permit or special use per mit shall receive a decision on such permit within six months after its submission.

2. That the provisions of the first enactment of this act shall become effective on January 1, 2027.

3. That by January 1, 2027, the State Corporation Commission (the Commission) shall, in consultation with each Phase I and Phase II Utility, as such terms are defined in subdivision A 1 of § 56-585.1 of the Code of Virginia, PJM Interconnection, and other relevant stakeholders including clean energy developers, environmental organizations, and clean energy industry experts, conduct and publish a comprehensive assessment of available interconnection capacity across the electric distribution and transmission systems in the Commonwealth. Such assessment shall (i) identify all generating facilities located in a Phase I or Phase II Utility's service territory that are interconnected pursuant to, have executed, or have requested to file an interconnection agreement, as defined in § 56-596.7 of the Code of Virginia, as created by this act; (ii) determine the total amount of electricity, in megawatts, each generating facility is permitted to contribute to the electric grid pursuant to an interconnection agreement; and (iii) identify each generating facility's point of interconnection and determine how much, if any, surplus interconnection service, as defined in § 56-596.7 of the Code of Virginia, as created by this act, is available at such point of interconnection. The Commission shall designate any point of interconnection where surplus interconnection service exists as an eligible site.