Ratifi English Iniciar sesión
Ratifi

Proyectos federales de Congress.gov. Proyectos estatales de Open States.

HB 2087Sesión 2025

Qué cambió entre versiones

47 párrafos cambiaron+645 palabras agregadas−552 eliminadas

El texto resaltado se agregó en la versión más reciente. El texto tachado se eliminó.

2025 SESSION

HOUSE SUBSTITUTE

INTRODUCED

25105883D25104457D

HOUSE BILL NO. 2087

AMENDMENT IN THE NATURE OF A SUBSTITUTE

Offered January 13, 2025

Prefiled January 7, 2025

A BILL to amend the Code of Virginia by adding sections numbered 56-1.2:2 and 56-581.2 and to repeal § 56-585.1:13 of the Code of Virginia, relating to electric utilities; electric vehicle charging stations; transportation electrification.

—————

Patrons—Shin, Bennett-Parker, Clark, Convirs-Fowler, Cousins, Glass, Maldonado, Sullivan and Tran; Senator: Salim

—————

(ProposedReferred by the Houseto Committee on Labor and Commerce

on January 28, 2025)

(Patron Prior to Substitute—Delegate Shin)

A BILL to amend the Code of Virginia by adding sections numbered 56-581.2 and 56-581.3 and to repeal § 56-585.1:13 of the Code of Virginia, relating to electric utilities; electric vehicle charging stations; transportation electrification.

—————

Be it enacted by the General Assembly of Virginia:

1. That the Code of Virginia is amended by adding sections numbered 56-58156-1.2:2 and 56-581.32 as follows:

§ 56-1.2:2. Electric vehicle fast-charging stations.

A. As used in this section, unless the context requires a different meaning:

"Fast-charging station" means a charging system capable of delivering at least 50 kilowatts of direct current electrical power to an electric vehicle's rechargeable battery at a voltage of 200 volts or greater.

"Phase I Utility" and "Phase II Utility" have the same meanings as provided in subdivision A 1 of § 56-585.1.

B. Effective January 1, 2028, a Phase I or Phase II Utility may develop, own, maintain, or operate public - facing fast-charging stations only at or beyond a radial distance, as determined by the Commission, relative to the location of any privately owned fast-charging station that is already in commercial operation or has a pending building permit or interconnection request as of July 1, 2027. Such radial distance shall be determined by the Commission pursuant to a rulemaking proceeding initiated by June 1, 2027 , with a final order entered no later than December 1, 2027.

§ 56-58 1 .2. Transportation electrification .

A. As used in this section, unless the context requires a different meaning:

"Electrical distribution infrastructure" means equipment, structures, and associated engineering and civil construction work designed to support electric vehicle charging stations, including poles, vaults, service drops, transformers, mounting pads, trenching, conduit, wire, cable, meters, and other necessary equipment.

"Fast-charging station" means a charging system capable of delivering at least 50 kilowatts of direct current electrical power to an electric vehicle's rechargeable battery at a voltage of 200 vol ts or greater.

"Fast-charging station" has the same meaning as provided in § 56-1.2:2.

"Historically economically disadvantaged community" has the same meaning as provided in § 56-576.

3 párrafos sin cambios

"Phase I Utility" and "Phase II Utility" have the same meanings as provided in subdivision A 1 of § 56-585.1.

"Rural community" means a city with a population density of less than 1,470 people per square mile or a county with a population density of less than 160 people per square mile.

"Transportation electrification" means the use of electricity from external sources to power all or part of passenger vehicles, trucks, buses, trains, boats, or other equipment that transport materials, goods, or people.

B. The Commission shall require each Phase I and Phase II Utility to maintain an accurate and full accounting of all expenses related to electrical distribution infrastructure as it relates to this section.

C. A Phase I or Phase II Utility may file a proposed tariff or rule with the Commission to provide utility-owned and utility-operated electrical distribution infrastructure between the main overhead or underground lines and the customer electrical revenue meter available to customers installing separately metered infrastructure to support electric vehicle charging stations, other than those in single-family residences. The Commission shall issueapprove anand orderauthorize onor modify and approve such filingtariff or rule within six months after filing. Such proposal and such tariff or rule shall provide that related costs incurred by such utility shall be tracked and reported separately and shall be eligible for cost recovery, onlyat the utility's election, pursuant to the utility's rates for generation and distribution services or through a rate adjustment clause approved pursuant to subdivision A 6 of § 56-585.1. In any proceeding in which the Commission reviews such costs, such costs shall be evaluated by the same standards as costs incurred for other necessary and essential distribution infrastructure. Customers may elect to take service under such a tariff or rule as an alternative to taking service under existing line extension rules. The provisions of this section shall not modify any arrangements for contribution in aid of construction or other agreements in effect prior to the effective date of the rule or tariff.

D. EachBy Phase I Utility shall file b y MayNovember 15, 2026 2025, and every threetwo years thereafter, each Phase I and each Phase II Utility shall file in each integrated resource plan filing required by § 56-599, transportation electrification plan sapplications to accelerate widespread transportation electrification across the Commonwealth in a manner designed to achievemaximize theratepayer mostbenefits. reasonableThe Commission shall, after notice and prudentopportunity utilityfor investmentshearing, indetermine whether to approve and authorize, modify and approve, or reject such transportation electrification throughoutplan application within eight months of the utility'sapplication's servicefiling territory,date. whichAt least 35 percent of such proposed costs of utility programs to accelerate widespread transportation electrification shall includebe allocated to programs designed to benefit rural communities and historically economically disadvantaged areascommunities. Such transportation electrification plan sapplications shall consider potential rate designs, incentives, investments, and programs designed to accelerate transportation electrification in a reasonable and prudent manner. The initial plan shallmay include:

1. Programs to incentivize and facilitate the deployment of electric vehicle charging infrastructure for light- duty , medium- duty , and heavy-duty vehicles , including a program to provide incentives and technical assistance to petroleum distributors and convenience stores to expand such fueling services to include fast-charging stations ;

2. Rate designs and programs that encourage transportation electrification and electric vehicle charging; benefit rural communities and historically economically disadvantaged areas;, support the off-peakefficient utilizationoperation of the electric grid;, facilitate fuel cost savings;, and support various categories of vehicles and charging use cases, including public level 2 and direct-current fast-charging, workplace charging, residential charging for single-family and multifamily dwellings, fleet and depot charging , vehicle-to-grid battery discharge designed to improve grid conditions including by alleviating peak demand , non-road industrial areas including ports, and charging for light-duty, medium- duty , and heavy-duty vehicles; and

3. Targeted and broad customer education and outreach programs that increase the awareness of related customer incentives and the ratepayer benefits of transportation electrification ; and.

4. Responses to Commission prompts in previous transportation electrification plans.

E. In considering transportation electrification plansapplications filed pursuant to subsection D, the Commission shall consider whether suchthe plansproposed investments, incentives, programs, rate designs, and expenditures are reasonably expected to :

1. IncreaseReasonably expected to increase access to transportation electrification, including for rural communities and historically economically disadvantaged communities;

2. ProvideReasonably expected to provide lower costs to customers and fleet operators who charge electric vehicles duringtaking off-peakinto hoursaccount grid demand conditions;

3. ImproveReasonably expected to improve the utility's electrical system efficiency, integration of variable resources, operational flexibility, and system utilization during off-peak hours while also mitigating increased peak demand;

4. ExpandReasonably expected to expand access to public charging in a manner that does not result inwith unreasonable competition with companies as defined in § 56-265.1;

5. Reasonably expected to improve air quality; and

56. ImproveTransparen airt quality and transparency, including the incorporation of public reporting requirements to inform program design and Commission policy ; and.

6. Identify and address aggregate distribution grid capacity upgrade needs to support transportation electrification or other expenditures necessary to serve projected transportation electrification growth .

F. In any biennial rate case following the submission of any transportation electrification plan required by subsection D, a Phase I or II Utility shall, pursuant to the utility's rates for generation and distribution services, seek recovery of necessary and appropriate expenditures, distribution grid capacity upgrades, and rate designs to serve aggregate transportation electrification needs as identified in the transportation electrification plan.

§ 56-581.3. Fast-charging station proposals; requirements.

Beginning January 1, 2028, a Phase I or Phase II Utility may petition for approval of expenditures to develop, own, maintain, or operate public-facing fast-charging stations only at or beyond a radial distance as determined by the Commission relative to the location of any privately owned fast-charging station that is already in commercial operation or has a pending building permit or interconnection request as of July 1, 2027. Such radial distance shall be determined by the Commission pursuant to a rulemaking proceeding initiated by June 1, 2027 with a final order entered no later than December 1, 2027.

F. By May 15, 2026, each Phase I and Phase II Utility shall submit to the Commission estimates and plans to serve load capacity needs to support transportation electrification and to comply with applicable air quality standards and regulations, and a proposal for a specific rate or set of rates for:

1. Electricity used to charge light- duty , medium- duty , and heavy-duty electric vehicles that (i) encourage electric vehicle charging and (ii) support the efficient off-peak utilization of the electric grid; and

2. Various categories of vehicles and charging use cases, including as appropriate, public level 2 and direct-current fast-charging, workplace charging, residential charging in single-family and multifamily dwellings, fleet and depot charging, and vehicle-to-grid battery discharge designed to support efficient utilization of the grid including by decreasing peak demand .

G. Each Phase I and Phase II Utility shall update the plans and rates established pursuant to subsection F annually, as determined by the utility in its sole discretion to be necessary.

H. Consistent with the estimates and plans required by subsection F, a Phase I or Phase II Utility shall propose electrical distribution system investments designed to support electric vehicle charging stations in one or more plans for electric distribution grid transformation filed pursuant to subdivision A 6 of § 56-585.1.

2. That § 56-585.1:13 of the Code of Virginia is repealed effective December 1, 2027.

3. That no later than June 1, 2027, the State Corporation Commission (the Commission) shall initiate a rulemaking proceeding pursuant to § 56-58156-1.32:2 of the Code of Virginia, as created by this act, to determine the appropriate radial distance between privately owned fast-charging stations that are already in commercial operation or have a pending building permit or interconnection request as of July 1, 2027, and fast-charging stations owned, maintained, or operated by athe Phase I or Phase II Utility, as those terms are defined in subdivision A 1 of § 56-585.1 of the Code of Virginia. In determining such radial distance, the Commission shall consider the policy of the Commonwealth, pursuant to Chapter 268 of the Acts of Assembly of 2021, Special Session I, to promote, to the greatest extent possible, private competition and investment in transportation electrification and to enable public utilities and the public sector to complement such private investment where most effective. In conducting such proceeding, the Commission's review shall include (i) an analysis of the adequacy of electric vehicle charging infrastructure throughout the Commonwealth and how equitably such infrastructure is distributed; (ii) a consideration of the impact of any federal grants or loans made to provide electric vehicle charging infrastructure in the Commonwealth; (iii) minimum requirements for direct current fast-charging equipment, including adherence to universal design guidelines and the minimum number of privately-ownedprivately direct current fast-charging stations at a single location that may prevent the development of direct currentowned fast-charging stations by a Phase I or Phase II Utility within the radial distance determined by the Commission; (iv) a consideration of similar radial distance arrangements or determinations made in other states with vertically integrated utilities; and (v) any other issues deemed relevant by the Commission. The Commission shall enter its final order no later than December 1, 2027.

3. That no later than December 1, 2029, the State Corporation Commission shall review the final rule promulgated pursuant to the second enactment of this act to assess its effectiveness in promoting the adequacy of publicly available electric vehicle fast-charging infrastructure throughout the Commonwealth and to promote small business investment and competition in transportation electrification, including by petroleum distributors and convenience stores.

Volver al texto completo