89R30659 JXC-F
By: King, et al.
S.B. No. 6
(King)
Substitute the following for S.B. No. 6: No.
A BILL TO BE ENTITLED
AN ACT
relating to the planning for, interconnection and operation of, and
costs related to providing service for certain electrical loads. and
to the generation of electric power by a water supply or sewer
service corporation.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
13 párrafos sin cambios
SECTION 1. Section 35.004, Utilities Code, is amended by
adding Subsections (c-1) and (c-2) to read as follows:
(c-1) The commission by rule shall ensure that a large load
customer who is subject to the standards adopted under Section
37.0561 contributes to the recovery of the interconnecting electric
utility's costs to interconnect the large load to the utility's
system.
(c-2) An electric cooperative or municipally owned utility
that has not adopted customer choice shall pass through to a large
load customer who is subject to the standards adopted under Section
37.0561 the reasonable costs to interconnect the large load in a
manner determined by the electric cooperative or municipally owned
utility.
SECTION 2. Subchapter B, Chapter 37, Utilities Code, is
amended by adding SectionsSection 37.0561 and 37.0562 to read as follows:
Sec. 37.0561. PLANNING FOR AND INTERCONNECTION OF LARGE
43 párrafos sin cambios
LOADS. (a) For the purposes of this section, a large load customer
includes an entity requesting an interconnection that exceeds the
demand threshold adopted under Subsection (c) and a successor in
interest to such an entity.
(b) The commission by rule shall establish standards for
interconnecting large load customers in the ERCOT power region in a
manner designed to support business development in this state while
minimizing the potential for stranded infrastructure costs and
maintaining system reliability.
(c) The standards must apply only to customers requesting a
new or expanded interconnection where the total load at a single
site would exceed a demand threshold established by the commission
based on the size of loads that significantly impact transmission
needs in the ERCOT power region. The commission shall establish a
demand threshold of 75 megawatts unless the commission determines
that a lower threshold is necessary to accomplish the purposes
described by Subsection (b).
(d) The standards must require each large load customer
subject to Subsection (c) to disclose to the interconnecting
electric utility or municipally owned utility whether the customer
is pursuing a substantially similar request for electric service in
this state the approval of which would result in the customer
materially changing, delaying, or withdrawing the interconnection
request. The disclosure may withhold or anonymize competitively
sensitive details. The commission by rule shall prohibit an
electric utility or municipally owned utility from selling,
sharing, or disclosing information submitted to the utility under
this subsection other than a disclosure to the commission or the
independent organization certified under Section 39.151 for the
ERCOT power region, subject to appropriate confidentiality
protections.
(e) The standards must require each interconnected large
load customer subject to Subsection (c) to disclose to the
interconnecting electric utility or municipally owned utility
information about the customer's on-site backup generating
facilities and require the interconnecting electric utility or
municipally owned utility to provide the information to the
independent organization certified under Section 39.151 for the
ERCOT power region. For the purposes of this subsection, "on-site
backup generating facilities" means generation that is not capable
of exporting energy to the ERCOT transmission grid and that, in the
aggregate, can serve at least 50 percent of on-site demand. The
independent organization shall establish a threshold before or
during an energy emergency alert at which the organization may
issue reasonable notice that large load customers maywith be directedon-site
backup generating facilities may be directed to either deploy the
to deploycustomer's on-site backup generating facilities or curtail load.
After the independent organization deploys all available market
services, except for frequency responseresponsive services, the independent
independent organization may direct the applicable electric utility or
utility or municipally owned utility to require the large load customer to
customer to either deploy the customer's on-site backup generating facilities
facilities or curtail load. The independent organization shall include a
include a deployment under this section as firm load shed when calculating
calculating any price adjustments for reliability deployments. This subsection
This subsection does not:
(1) authorize or require a violation of any emissions
19 párrafos sin cambios
limitation in state or federal law or a violation of any other
environmental regulation; or
(2) prohibit a large load customer from participating
in a service authorized by Section 39.170(b).
(f) The standards must set a flat study fee of at least
$100,000 to be paid to the interconnecting electric utility or
municipally owned utility for initial transmission screening
studies for large loads subject to Subsection (c). A large load
customer that requests additional capacity following the screening
study must pay an additional study fee based on the new request.
The interconnecting electric utility or municipally owned utility
shall apply any unused portion of the initial transmission
screening study fee as a credit toward satisfying financial
obligations for procurement or interconnection agreements at the
same geographic site.
(g) The standards must include a method for a large load
customer subject to Subsection (c) to demonstrate site control for
the proposed load location through an ownership interest, lease, or
another legal interest acceptable to the commission.
(h) The standards must include uniform financial commitment
standardsrequirements for the development of transmission infrastructure
needed to serve a large load customer subject to Subsection (c).
before an electric utility or municipally owned utility may submit
a project for review to the independent organization certified
under Section 39.151 for the ERCOT power region based on the large
load customer's demand. Unless the payment is later refunded, an
interconnecting electric utility or municipally owned utility that
receives a payment that meets the financial commitment standards
shall preserve the ability of the large load customer to
interconnect and retain the customer's contract capacity under the
interconnection or facilities extension agreement, once the
utility has approved the customer's initial or modified request for
interconnection. The standards must provide that satisfactory proof of financial
proof of financial commitment may include:
(1) security provided on a dollar per megawatt basis
40 párrafos sin cambios
as set by the commission;
(2) contribution in aid of construction;
(3) security provided under an agreement that requires
a large load customer to pay for significant equipment or services
in advance of signing an agreement to establish electric delivery
service; or
(4) a form of financial commitment acceptable to the
commission other than those provided by Subdivisions (1)-(3).
(i) Security provided under Subsection (h)(1) must be
refunded, in whole or in part, after the security is applied to any
outstanding amounts owed:
(1) as the large load customer meets the customer's
load ramp milestones and sustains operations for a prescribed
period as determined by the commission;
(2) if the large load customer withdraws the
customer's request for all or a portion of the requested capacity;
or
(3) if capacity subject to a financial commitment will
be reallocated to one or more other customers.
(j) The commission shall establish uniform requirements for
determining when capacity that is subject to an outstanding
financial commitment under this section may be reallocated.
(k) The standards must establish a procedure to allow the
independent organization certified under Section 39.151 for the
ERCOT power region to access any information collected by the
interconnecting electric utility or municipally owned utility to
ensure compliance with the standards for transmission planning
analysis. Any customer-specific or competitively sensitive
information obtained under this subsection is confidential and not
subject to disclosure under Chapter 552, Government Code.
(l) The commission may not limit the authority of a
municipally owned utility or an electric cooperative to impose
electric service requirements for large load customers on their
systems in addition to the standards adopted under this section.
(m) Notwithstanding the forecasted load growth and
additional load currently seeking interconnection required to be
considered under Section 37.056(c-1), the commission by rule shall
establish criteria by which the independent organization certified
under Section 39.151 for the ERCOT power region includes forecasted
large load of any peak demand in the organization's transmission
planning and resource adequacy models and reports.
Sec. 37.0562. EXPEDITED INTERCONNECTION FOR CERTAIN LARGE
LOADS. (a) In this section:
(1) "Behind-the-meter generation" means a generation
facility on the retail customer's side of the meter capable of
serving the full load requirement of the retail customer.
(2) "Flexible load" means a large load operated by a
retail customer who is obligated by contract or agreement in the
ERCOT market to reduce the load or power the load exclusively with
back-up generation:
(A) at the direction of the independent
organization certified under Section 39.151 for the ERCOT power
region; or
(B) as required to protect the integrity of the
ERCOT grid.
(b) The commission by rule shall establish a program to
provide an expedited process for the interconnection of large
loads. The program must require the interconnecting municipally
owned utility or electric utility and the independent organization
certified under Section 39.151 for the ERCOT power region to give
priority in the interconnection queue to a large load for which a
retail customer has received approval for expedited processing over
any other large loads that have not entered into a contractual
agreement with the municipally owned utility or electric utility
regarding the provision of electric service. If applicable, the
generation interconnection application for a generation facility
associated with the large load must be processed in parallel with
the large load.
(c) The program must require a large load to qualify for
expedited interconnection processing by bringing in-service, not
later than the 180th day after the interconnection date,
behind-the-meter generation that is:
(1) registered with the independent organization
certified under Section 39.151 for the ERCOT power region; and
(2) capable of serving the full load requirement of
the customer.
(d) As an alternative to the requirements of Subsection (c),
a large load may qualify for expedited interconnection processing,
if the load is a facility with an aggregated peak demand at a single
site of more than 75 megawatts, by:
(1) providing to the interconnecting municipally
owned utility or electric utility all data regarding, and making
satisfactory proof of financial commitment for, the load; and
(2) being subject to a binding commitment with the
independent organization certified under Section 39.151 for the
ERCOT power region to establish the load as a flexible load for a
minimum period established by the commission, which must be at
least 10 years.
(e) A large load that qualifies for expedited
interconnection processing may choose:
(1) if authorized by the independent organization
certified under Section 39.151 for the ERCOT power region and the
relevant municipally owned utility or electric utility, to contract
with a vendor approved by the relevant utility or by the independent
organization to perform all studies required by the relevant
utility before the approval of the interconnection application; and
(2) if authorized by the relevant municipally owned
utility or electric utility:
(A) to procure equipment required for the
interconnection in accordance with technical specifications
provided by the relevant utility; and
(B) to construct interconnection facilities in
accordance with technical and other requirements of the relevant
utility.
(f) The program may provide that studies required by a
municipally owned utility or electric utility before the approval
of an interconnection application for a flexible load may evaluate
the load as non-firm.
(g) Demand reductions from flexible loads that receive
expedited processing and are removed from the system through the
utilization of behind-the-meter generation during an energy
emergency alert must be counted toward any obligation of the
municipally owned utility or electric utility to shed load.
(h) The independent organization certified under Section
39.151 for the ERCOT power region shall consider action taken under
this section as a reliability deployment when calculating any price
adjustments for reliability deployments.
(i) The commission shall establish financial penalties the
commission may impose on an owner or operator of a large load that
is approved for expedited interconnection processing but fails to
reduce the load or power the load with back-up generation as
directed by the independent organization certified under Section
39.151 for the ERCOT power region.
SECTION 3. Section 39.002, Utilities Code, is amended to
28 párrafos sin cambios
read as follows:
Sec. 39.002. APPLICABILITY. This chapter, other than
Sections 39.151, 39.1516, 39.155, 39.157(e), 39.161, 39.162,
39.163, 39.169, 39.170, 39.203, 39.9051, 39.9052, and 39.914(e),
and Subchapters M and N, does not apply to a municipally owned
utility or an electric cooperative. Sections 39.157(e) and 39.203
apply only to a municipally owned utility or an electric
cooperative that is offering customer choice. If there is a
conflict between the specific provisions of this chapter and any
other provisions of this title, except for Chapters 40 and 41, the
provisions of this chapter control.
SECTION 4. Subchapter D, Chapter 39, Utilities Code, is
amended by adding Sections 39.169 and 39.170 to read as follows:
Sec. 39.169. CO-LOCATION OF LARGE LOAD CUSTOMER WITH
EXISTING GENERATION RESOURCE. (a) A power generation company,
municipally owned utility, or electric cooperative must submit a
notice to the independent organization certified under Section
39.151 for the ERCOT power region before implementing a net
metering arrangement between an operating facility registered with
the independent organization as a stand-alone generation resource
as of September 1, 2025, and a new large load customer as described
by Section 37.0561(c).
(b) This section does not apply to a generation resource:
(1) the registration for which included a co-located
large load customer at the time of energization, regardless of
whether the load was energized at a later date; or
(2) a majority interest of which is owned indirectly
or directly as of January 1, 2025, by a parent company of the
customer that participates in the new net metering arrangement.
(c) The electric cooperative, transmission and distribution
utility, or municipally owned utility that provides electric
(c)service Theat the location of the new net metering arrangement mustmay be requested orfor
consented to by the electric cooperative, electric utility, or
municipally owned utility certificated to provide electric service
at the location. The electric cooperative, electric utility, or
municipally owned utility may withhold consent to a proposal that
reasonable cause including a violation of other law, object to the
arrangement, provided however, that no reasonable cause objection
may be raised after a final decision by the commission is issued
under this section.
is(d) consistentThe withindependent theorganization determination providedcertified under Subsection (d)Section
and applicable law only for a reasonable cause.
(d) Not later than the 180th day after the date the
39.151 for the ERCOT power region shall study the system impacts of
a proposed net metering arrangement and removal of generation for
which the independent organization certifiedreceives a notice under Section 39.151 for the
ERCOT power region receives the notice under Subsection (a), the
Subsection (a) after the independent organization receives all
information regarding the arrangement required by the independent
organization to be submitted to the independent organization. The
independent organization shallmust approve,complete deny,the orstudy imposeand reasonablesubmit the
results to the commission with any associated recommendations not
later than the 120th day after the independent organization
receives all required information regarding the arrangement. Not
later than the 60th day after the date the commission receives the
study results from the independent organization, the commission
shall approve, deny, or impose reasonable conditions on the
conditions on a proposed net metering arrangement describedas bynecessary to maintain system
Subsection (a) as necessary to maintain system reliability,
reliability, including transmission security and resource adequacy impacts. The
impacts. The conditions must require a generation resource that makes capacity
makes dispatchable capacity available to the ERCOT power region
before the implementation of a net metering arrangement under this
section to make at least that amount of dispatchable capacity
available to the ERCOT power region beforeafter the implementation of athe
net metering arrangement under this section to make at leastthe thatdirection of the independent organization in
amount of capacity available to the ERCOT power region after the
implementation of the arrangement at the direction of the
independent organization in advance of an anticipated emergency condition. The conditions may
condition. The conditions may:
include:
(1) requirerequiring the retail customer who is served
behind-the-meter to reduce load during certain events;
(2) requirerequiring the generation resource to make capacity
available to the ERCOT power region during certain events; or
(3) provide that the owner of the generation resource
(3) requiring customers to be held harmless for
may be held liable for stranded or underutilized transmission assets resulting from the
assets resulting from the behind-the-meter operation.
(e) If the independent organization certified under Section
39.151(e) forIf the ERCOT power regioncommission does not approve, deny, or impose
reasonable conditions on a proposed net metering arrangement before
the expiration of the deadline established by Subsection (d), the
independent organizationcommission is considered to have approved the arrangement.
arrangement.
(f) If conditions imposed under Subsection (d) are not
limited to a specific period, the independentcommission organizationshall review the
certified under Section 39.151 for the ERCOT power region shall
review the conditions at least every five years to determine whether the
whether the conditions should be extended or rescinded.
(g) The parties to a proceeding under this section are
limited to the commission, the independent organization certified
under Section 39.151 for the ERCOT power region, the
interconnecting electric cooperative, electrictransmission utility, orand
distribution utility, or municipally owned utility, and a party in the net metering
arrangement. A final decision made by the independent organization
the net metering arrangement.
(h) The commission shall post the decision made on each
relatednotice tosubmitted under this section may be appealed toon the commissioncommission's by theInternet
owner of the generation resource or the large load customer.
(h)website. The commission shallmay not post theinformation decision made byregarding the
independent organization certified under Section 39.151 for the
ERCOT power region on each notice submitted under this section on
the commission's Internet website. The commission may not post
information regarding the decision that is competitively sensitive or otherwise considered
or otherwise considered confidential.
Sec. 39.170. LARGE LOAD DEMAND MANAGEMENT SERVICE.
3 párrafos sin cambios
(a) The commission shall require the independent organization
certified under Section 39.151 for the ERCOT power region to ensure
that each electric cooperative, transmission and distribution
utility, and municipally owned utility serving a
transmission-voltage customer develops a protocol and installs, orincluding the
requires to be installed, before the customer is interconnected,
installation of any necessary equipment or technology before the
anycustomer necessaryis equipmentinterconnected, to allow the load to be curtailed during
during firm load shed. The electric cooperative, transmission and
distribution utility, or municipally owned utility shall confer
27 párrafos sin cambios
with the customer to the extent feasible to shed load in a
coordinated manner. This subsection applies only to a load
interconnected after December 31, 2025, that is not:
(1) load operated by a critical load industrial
customer, as defined by Section 17.002; or
(2) designated as a critical natural gas facility
under Section 38.074.
(b) The commission shall require the independent
organization certified under Section 39.151 for the ERCOT power
region to develop a reliability service to competitively procure
demand reductions from large load customers with a demand of at
least 75 megawatts to be deployed in the event of an anticipated
emergency condition. The rules governing this service must:
(1) specify the periods when the service may be used to
assist with maintaining reliability during extreme weather events;
(2) ensure that the independent organization provides
at least a 24-hour notice to large load customers and requires each
large load to remain curtailed for the duration of the energy
emergency alert event or until the load can be recalled safely; and
(3) prohibit participation by any large load customer
that curtails in response to the wholesale price of electricity, as
determined by the independent organization certified under Section
39.151 for the ERCOT power region, or that otherwise participates
in a different reliability or ancillary service.
(c) The independent organization certified under Section
39.151 for the ERCOT power region shall include a deployment under
this section when calculating any price adjustments for reliability
deployments.
SECTION 5. (a) The Public Utility Commission of Texas shall
SECTION 5. Subchapter A, Chapter 67, Water Code, is amended
by adding Section 67.0115 to read as follows:
Sec. 67.0115. ELECTRIC GENERATION. (a) A corporation may
generate electric power for use in the corporation's operations,
limited to:
(1) powering water well pumps, service pumps, and
other equipment for the production, treatment, and transportation
of raw water; and
(2) powering infrastructure for the treatment and
delivery of potable drinking water.
(b) For the purposes of Subsection (a), a corporation
operating solely as a wholesale water supplier or sewer service in a
county with a population of less than 350,000 may generate excess
electric power in conjunction with the uses described in Subsection
(a) for sale in the ERCOT power region to provide revenue for the
corporation only if the corporation:
(1) primarily generates electric power solely for the
uses described in Subsection (a); and
(2) registers as a power generation company under
Section 39.351, Utilities Code.
(c) A corporation that generates electric power for sale
under Subsection (b) shall account for and use the revenue from
those sales in a manner that complies with Section 67.004. The
revenue that accrues from those sales of electric power may be used
by the corporation only for:
(1) the corporation's costs of producing and selling
electric power, including administration, employees, equipment,
fuel, and maintenance; or
(2) a purpose described by Section 67.002.
SECTION 6. (a) The Public Utility Commission of Texas shall
evaluate whether the existing methodology used to charge wholesale
28 párrafos sin cambios
transmission costs to distribution providers under Section
35.004(d), Utilities Code, continues to appropriately assign costs
for transmission investment. The commission shall also evaluate:
(1) whether the current four coincident peak
methodology used to calculate wholesale transmission rates ensures
that all loads appropriately contribute to the recovery of an
electric cooperative's, electric utility's, or municipally owned
utility's costs to provide access to the transmission system;
(2) whether alternative methods to calculate
wholesale transmission rates would more appropriately assign the
cost of providing access to and wholesale service from the
transmission system, such as consideration of multiple seasonal
peak demands, demand during different length daily intervals, or
peak energy intervals; and
(3) the portion of the costs related to access to and
wholesale service from the transmission system that should be
nonbypassable, consistent with Section 35.004(c-1), Utilities
Code, as added by this Act.
(b) The Public Utility Commission of Texas shall evaluate
whether the commission's retail ratemaking practices ensure that
transmission cost recovery appropriately charges the system costs
that are caused by each customer class.
(c) The Public Utility Commission of Texas shall begin the
evaluation required under Subsection (a) of this section not later
than the 90th day after the effective date of this Act. After
completion of the evaluation project and not later than December
31, 2026, the commission shall amend commission rules to ensure
that wholesale transmission charges appropriately assign costs for
transmission investment.
SECTION 67. Section 35.004(c-1), Utilities Code, as added by
this Act, applies only to an interconnection agreement entered into
on or after the effective date of this Act.
SECTION 78. This Act takes effect immediately if it receives
a vote of two-thirds of all the members elected to each house, as
provided by Section 39, Article III, Texas Constitution. If this
Act does not receive the vote necessary for immediate effect, this
Act takes effect September 1, 2025.
______________________________
______________________________
President of the Senate
Speaker of the House
I hereby certify that S.B. No. 6 passed the Senate on
March 19, 2025, by the following vote: Yeas 31, Nays 0; and that
the Senate concurred in House amendments on May 29, 2025, by the
following vote: Yeas 31, Nays 0.
______________________________
Secretary of the Senate
I hereby certify that S.B. No. 6 passed the House, with
amendments, on May 27, 2025, by the following vote: Yeas 103,
Nays 25, two present not voting.
______________________________
Chief Clerk of the House
Approved:
______________________________
Date
______________________________
Governor