89R29102 ANG-D
By: King
S.B. No. 2321
(Bell of Kaufman)
Substitute the following for S.B. No. 2321: No.
A BILL TO BE ENTITLED
AN ACT
62 párrafos sin cambios
relating to the regulation of emissions by the Texas Commission on
Environmental Quality during an event affecting electric demand or
grid reliability.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Subchapter D, Chapter 382, Health and Safety
Code, is amended by adding Section 382.086 to read as follows:
Sec. 382.086. ENFORCEMENT DURING ELECTRIC DEMAND AND
RELIABILITY EVENT. (a) The commission may exercise the
commission's enforcement discretion to waive enforcement for
emissions from electric generation facilities and on-site backup
generation facilities in this state during a period requested by an
independent system operator if the independent system operator
notifies the commission that additional electric generation is
necessary to mitigate an emergency condition or a significant risk
of an emergency condition.
(b) After an independent system operator submits a
notification to the commission under Subsection (a):
(1) the independent system operator shall notify
market participants in this state of the period in the notification
during which limits or standards described by Subdivision (2) may
not apply to the operation of an electric generation facility or
on-site backup generation facility in this state; and
(2) notwithstanding any other state law and subject to
Subsection (d), the commission has the discretion to enforce a rule
or standard, including an emissions limit or standard, hours of
operation limit, or any similar operational limit, against the
owner or operator of an electric generation facility or on-site
backup generation facility for the period in the notification.
(c) The owner or operator of an electric generation facility
or on-site backup generation facility eligible for waived
enforcement during the period in a notification submitted under
Subsection (a) shall:
(1) take commercially reasonable steps to operate
environmental controls and minimize excess emissions during the
period;
(2) maintain operational records during the period;
and
(3) submit proper documentation of the facility's
operational records to the commission, including:
(A) the facility's name;
(B) a contact name and phone number;
(C) the county in which the facility is located;
(D) the customer reference number issued to the
facility by the commission;
(E) the name of any units in the facility that
exceeded an emissions limit or standard during the period; and
(F) a description of the emissions event,
including the date, time, pollutant, quantity, and duration.
(d) The commission has the discretion to consider whether an
exceedance of an emissions limit or standard during a period for
which a notification is submitted under Subsection (a) is
appropriate as the basis for an enforcement action against the
owner or operator of an electric generation facility or on-site
backup generation facility based on information available to the
commission, including information contained in the documentation
required by Subsection (c)(3).
(e) The owner or operator of an electric generation facility
or an on-site backup generation facility eligible for waived
enforcement during the period in a notification submitted under
Subsection (a) shall report any exceedance of an emissions limit or
standard in accordance with commission regulations and permit
requirements.
SECTION 2. This Act takes effect September 1, 2025.
______________________________
______________________________
President of the Senate
Speaker of the House
I hereby certify that S.B. No. 2321 passed the Senate on
April 16, 2025, by the following vote: Yeas 31, Nays 0; and that
the Senate concurred in House amendment on May 30, 2025, by the
following vote: Yeas 31, Nays 0.
______________________________
Secretary of the Senate
I hereby certify that S.B. No. 2321 passed the House, with
amendment, on May 28, 2025, by the following vote: Yeas 140,
Nays 2, one present not voting.
______________________________
Chief Clerk of the House
Approved:
______________________________
Date
______________________________
Governor