Ratifi English Iniciar sesión
Ratifi

Proyectos federales de Congress.gov. Proyectos estatales de Open States.

SB 231589.ª Legislatura (2025)

Relating to a cost overage exemption for interconnection of advanced nuclear reactors to the ERCOT transmission system.

Introduced

El texto subrayado se agregaría a la ley vigente. El texto tachado se eliminaría.

  89R9644 SCR-D
 
  By: Parker S.B. No. 2315
 
 
  A BILL TO BE ENTITLED
  AN ACT
  relating to a cost overage exemption for interconnection of
  advanced nuclear reactors to the ERCOT transmission system.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 35.004(d-2), Utilities Code, is amended
  to read as follows:
         (d-2)  Costs in excess of the transmission-owning utility
  allowance provided by Subsection (d-1) incurred to interconnect
  generation resources with the ERCOT transmission system must be
  directly assigned to and collected from the generation resource
  interconnecting through the facilities.  This subsection does not
  apply to excess costs incurred to interconnect a generation
  resource that is an advanced nuclear reactor.  For purposes of this
  subsection, an advanced nuclear reactor is a fission-based reactor
  belonging to one of the following categories:
               (1)  a large reactor, with a generation capacity
  between 400 and 1400 megawatts of electricity;
               (2)  a small modular reactor, with a generation
  capacity between 50 and 400 megawatts of electricity; or
               (3)  a microreactor, with a generation capacity of less
  than 50 megawatts of electricity.
         SECTION 2.  This Act takes effect September 1, 2025.

Texto oficial de la Legislatura de Texas. El formato se adaptó para leerlo en Ratifi.