Introduced
El texto subrayado se agregaría a la ley vigente. El texto tachado se eliminaría.
| 89R580 JXC-F | ||
| By: Patterson | H.B. No. 553 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to the permitting of renewable energy generation | |
| facilities by the Public Utility Commission of Texas; authorizing | |
| fees. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Chapter 35, Utilities Code, is amended by adding | |
| Subchapter F to read as follows: | |
| SUBCHAPTER F. RENEWABLE ENERGY GENERATION FACILITY PERMIT | |
| Sec. 35.201. DEFINITIONS; APPLICABILITY. (a) In this | |
| subchapter: | |
| (1) "Permit holder" means a person who holds a permit | |
| issued under this subchapter. | |
| (2) "Person" includes an electric cooperative and a | |
| municipally owned utility. | |
| (3) "Renewable energy generation facility" means: | |
| (A) a wind power facility as defined by Section | |
| 301.0001; or | |
| (B) a solar power facility as defined by Section | |
| 302.0001. | |
| (b) This subchapter applies to a renewable energy | |
| generation facility regardless of whether the facility is the | |
| subject of a wind power facility agreement or solar power facility | |
| agreement entered into under Chapter 301 or 302. | |
| Sec. 35.202. LEGISLATIVE POLICY AND PURPOSE. The | |
| conservation and development of all the natural resources of this | |
| state are declared to be public rights and duties. It is also | |
| declared that the protection of the wildlife, water, and land of | |
| this state against the impacts of renewable energy generation | |
| facilities is in the public interest. In the exercise of the police | |
| power of this state, it is necessary and desirable to provide | |
| additional means so that the installation and removal of renewable | |
| energy generation facilities is placed under the authority and | |
| direction of the commission. | |
| Sec. 35.203. PERMIT REQUIRED; APPLICATION. (a) A person | |
| may not operate a renewable energy generation facility in this | |
| state unless the person holds a permit issued by the commission | |
| under this subchapter. A person may not construct a renewable | |
| energy generation facility in this state unless: | |
| (1) the person holds a permit to operate a renewable | |
| energy generation facility issued by the commission under this | |
| subchapter; or | |
| (2) the commission by order approves the construction. | |
| (b) A person may apply for a permit to operate a renewable | |
| energy generation facility by filing with the commission: | |
| (1) a description of the location of the facility; | |
| (2) a description of the type of facility; | |
| (3) a copy of any information filed with the Federal | |
| Energy Regulatory Commission in connection with registration with | |
| that commission; | |
| (4) any assumed business or professional name of the | |
| applicant filed under Chapter 71, Business & Commerce Code; | |
| (5) an environmental impact statement produced by the | |
| Parks and Wildlife Department under Section 11.006, Parks and | |
| Wildlife Code; | |
| (6) any wind power facility agreement or solar power | |
| facility agreement applicable to the facility entered into under | |
| Chapter 301 or 302 by the applicant; | |
| (7) the address of an Internet website that provides | |
| information about the proposed facility; | |
| (8) an affidavit that lists the names and addresses of | |
| the persons who may be affected by the application and includes the | |
| source of the list; and | |
| (9) any other information required by commission rule, | |
| provided the commission protects the competitive process in a | |
| manner that ensures the confidentiality of competitively sensitive | |
| information. | |
| Sec. 35.204. NOTICE AND HEARING ON APPLICATION. (a) When | |
| an application for a permit is filed under Section 35.203, or when | |
| an application for a permit amendment is filed, the commission | |
| shall: | |
| (1) give notice of the application to affected | |
| parties, including any owner of property located within 25 miles of | |
| the boundary of the facility; and | |
| (2) if requested: | |
| (A) set a time and place for a hearing; and | |
| (B) give notice of the hearing to affected | |
| parties, including any owner of property located within 25 miles of | |
| the boundary of the facility. | |
| (b) For any application involving a generation capacity of | |
| 15 megawatts or more, the notice must be given to the county judge | |
| of each county located within 25 miles of the boundary of the | |
| facility who has requested in writing that the commission give that | |
| notice. | |
| (c) The commission may not act on an application before the | |
| 30th day after the date the commission gives notice of the | |
| application under Subsections (a) and (b), as applicable, | |
| regardless of whether a hearing is requested. | |
| (d) Notwithstanding any other provision of this subchapter, | |
| the commission may approve an application to amend a permit without | |
| holding a hearing if: | |
| (1) the applicant is not applying to: | |
| (A) significantly increase the amount of | |
| electricity generated under the permit; or | |
| (B) materially change the placement of the | |
| renewable energy generation facility; | |
| (2) the commission determines that the applicant's | |
| compliance history raises no issues regarding the applicant's | |
| ability to comply with a material term of the permit; and | |
| (3) the commission: | |
| (A) gives notice of the application to the county | |
| judge of each county and the governing body of each municipality in | |
| which the facility is located at least 30 days before the date of | |
| the commission's approval of the application; and | |
| (B) allows the county judges and governing bodies | |
| to present information to the commission on the application. | |
| Sec. 35.205. APPROVAL OR DENIAL OF APPLICATION. (a) The | |
| commission may approve an application only if the commission finds | |
| that issuance or amendment of the permit would not violate state or | |
| federal law or rule and would not interfere with the purpose of this | |
| subchapter. | |
| (b) In considering an application for the issuance or | |
| amendment of a permit, the commission shall consider the compliance | |
| history of the applicant. | |
| (c) A permit holder does not have a vested right in a permit. | |
| Sec. 35.206. CONDITIONS OF PERMIT. (a) For each permit, | |
| the commission shall prescribe the conditions under which it is | |
| issued, including: | |
| (1) the boundary of the permitted facility location; | |
| (2) the maximum number of renewable energy generation | |
| facilities authorized by the permit; and | |
| (3) any monitoring and reporting requirements | |
| prescribed by the commission for the permit holder. | |
| (b) The commission, on its own motion after reasonable | |
| notice and hearing, may require a permit holder to conform to new or | |
| additional conditions to comply with this subchapter or rules | |
| adopted under this subchapter. | |
| (c) A permit holder shall: | |
| (1) ensure that the permitted facility is located at | |
| least: | |
| (A) 500 feet from any property line, unless the | |
| permit holder has obtained a written waiver from each owner of | |
| property located less than 500 feet from the permitted facility; | |
| and | |
| (B) 1,000 feet from any habitable structure, | |
| unless the permit holder has obtained a written waiver from each | |
| owner of the habitable structure; | |
| (2) provide a publicly accessible Internet website | |
| that displays: | |
| (A) a map of the boundaries of the permitted | |
| facility; | |
| (B) any interconnection request numbers assigned | |
| to the permitted facility; | |
| (C) the name of the owner of the permitted | |
| facility; and | |
| (D) any other information the commission | |
| requires; and | |
| (3) post at each entrance to the permitted facility a | |
| sign that: | |
| (A) includes: | |
| (i) the name of the facility; | |
| (ii) the name of the owner of the facility; | |
| (iii) the name, business address, and | |
| telephone number of the operator of the facility; | |
| (iv) a general description of the property | |
| on which the facility is located, including the boundaries of the | |
| property; and | |
| (v) emergency contact information for the | |
| facility; | |
| (B) uses contrasting colors with block letters at | |
| least one inch in height; and | |
| (C) is displayed in a conspicuous manner clearly | |
| visible to the public. | |
| Sec. 35.207. MONITORING AND REPORTING. The commission by | |
| rule may, in coordination with the Parks and Wildlife Department, | |
| require a permit holder to: | |
| (1) monitor, record, and report on environmental | |
| impacts created by the permitted facility; | |
| (2) conduct wildlife assessments around the permitted | |
| facility; and | |
| (3) provide to the commission other information about | |
| the operation of the permitted facility. | |
| Sec. 35.208. FACILITY REMOVAL BY COMMISSION. (a) The | |
| commission may determine after reasonable notice and hearing that a | |
| permit holder has not removed a renewable energy generation | |
| facility according to the requirements of an applicable wind power | |
| facility agreement or solar power facility agreement entered into | |
| under Chapter 301 or 302 and that the permit holder has not | |
| delivered financial assurance required under Chapter 301 or 302, as | |
| applicable. After making the determination, the commission may: | |
| (1) order the permit holder to comply with the wind | |
| power facility agreement or solar power facility agreement; or | |
| (2) fulfill the requirements of the wind power | |
| facility agreement or solar power facility agreement if the permit | |
| holder cannot be found or does not have assets with which to comply | |
| with the wind power facility agreement or solar power facility | |
| agreement. | |
| (b) The commission or its employees or agents, on proper | |
| identification, may enter the land of another for the purpose of | |
| implementing Subsection (a)(2). | |
| (c) The commission's removal of a renewable energy | |
| generation facility under this section does not prevent the | |
| commission from seeking penalties or other relief provided by law | |
| from the permit holder. | |
| (d) The commission and its employees and agents are not | |
| liable for any damages arising from an act or omission if the act or | |
| omission is part of a good-faith effort to carry out this section. | |
| (e) If the commission removes a renewable energy generation | |
| facility under this section, the commission may recover from the | |
| permit holder all costs the commission incurs. The commission by | |
| order may require the permit holder to reimburse the commission for | |
| those costs or may request the attorney general to file suit against | |
| the permit holder to recover those costs. At the request of the | |
| commission, the attorney general may file suit to enforce an order | |
| the commission issues under this subsection. A suit under this | |
| subsection may be filed in Travis County. Costs recovered under | |
| this subsection shall be deposited to the renewable energy | |
| generation facility cleanup fund. | |
| Sec. 35.209. RENEWABLE ENERGY GENERATION FACILITY CLEANUP | |
| FUND. (a) The renewable energy generation facility cleanup fund is | |
| a dedicated account in the general revenue fund. | |
| (b) The fund consists of: | |
| (1) environmental impact fees collected under Section | |
| 35.210; | |
| (2) private contributions; and | |
| (3) legislative appropriations. | |
| (c) Money in the fund may be used only by the commission to | |
| implement this subchapter. | |
| Sec. 35.210. ENVIRONMENTAL IMPACT FEE. (a) An annual | |
| environmental impact fee is imposed on each permit holder. | |
| (b) Except as provided by Subsection (c), environmental | |
| impact fees must be deposited in the renewable energy generation | |
| facility cleanup fund. | |
| (c) The commission shall designate 20 percent of the revenue | |
| collected from environmental impact fees to be deposited in the | |
| renewable energy generation facility cleanup fund and used only for | |
| the removal of renewable energy generation facilities under Section | |
| 35.208. If the commission determines that the renewable energy | |
| generation facility cleanup fund has a sufficient amount of money | |
| to fund removal of renewable energy generation facilities under | |
| Section 35.208, the commission may instead deposit 20 percent of | |
| the revenue from environmental impact fees in the county and road | |
| district highway fund. | |
| (d) The fee for each year is imposed on each permit in effect | |
| during any part of the year. The commission may establish reduced | |
| fees for inactive permits. | |
| (e) The commission by rule shall adopt a fee schedule for | |
| determining the amount of the fee to be charged. In determining the | |
| fee amount under this section, the commission may consider: | |
| (1) the efficiency of the renewable energy generation | |
| facility; | |
| (2) the area and size of the renewable energy | |
| generation facility; | |
| (3) the renewable energy generation facility's | |
| environmental impact score provided under Section 11.006, Parks and | |
| Wildlife Code; and | |
| (4) expenses necessary to implement this subchapter. | |
| Sec. 35.211. FEDERAL FUNDS. The commission may execute | |
| agreements with the United States Environmental Protection Agency | |
| or any other federal agency that administers programs providing | |
| federal cooperation, assistance, grants, or loans for research, | |
| development, investigation, training, planning, studies, | |
| programming, or construction related to methods, procedures, | |
| mitigation, and facilities for the removal of renewable energy | |
| generation facilities. The commission may accept federal funds for | |
| these purposes and for other purposes consistent with the | |
| objectives of this subchapter and may use the funds as prescribed by | |
| law or as provided by agreement. | |
| Sec. 35.212. POWER TO REGULATE AND SUPERVISE. (a) For | |
| purposes of this subchapter, a provision of Subchapter B or E, | |
| Chapter 14, that authorizes the commission to regulate a public | |
| utility also applies to a person required to obtain a permit under | |
| this subchapter, including an electric cooperative and a | |
| municipally owned utility. | |
| (b) The commission may adopt and enforce rules reasonably | |
| required in the exercise of its powers under this subchapter. | |
| Sec. 35.213. ENFORCEMENT AND PENALTIES. For the purposes | |
| of enforcing this subchapter, a reference in Chapter 15 to a person | |
| includes any person required to obtain a permit under this | |
| subchapter, including an electric cooperative and a municipally | |
| owned utility. | |
| SECTION 2. Subchapter A, Chapter 11, Parks and Wildlife | |
| Code, is amended by adding Section 11.006 to read as follows: | |
| Sec. 11.006. ENVIRONMENTAL IMPACT STATEMENTS FOR RENEWABLE | |
| ENERGY GENERATION FACILITIES. The commission by rule shall adopt a | |
| system for providing an environmental impact statement to an | |
| applicant for a renewable energy generation facility permit under | |
| Section 35.203, Utilities Code. The system must establish: | |
| (1) a process for a person to apply for and receive | |
| from the department an environmental impact statement; | |
| (2) criteria for the department to evaluate the | |
| environmental impact of a proposed renewable energy generation | |
| facility, including: | |
| (A) conservation of natural resources; | |
| (B) continuous use of the land on which a | |
| facility is located for agricultural and wildlife purposes; and | |
| (C) in coordination with the Texas A&M AgriLife | |
| Extension Service, agricultural best practices; | |
| (3) a method for the department to provide an | |
| environmental impact score for a renewable energy generation | |
| facility, based on the criteria described by Subdivision (2); | |
| (4) fees for providing the environmental impact | |
| statements, in an amount sufficient to cover the department's costs | |
| of implementing this section; and | |
| (5) guidelines for the department's use of any map | |
| applications necessary for the implementation of this section. | |
| SECTION 3. (a) Except as otherwise provided by rules | |
| adopted by the Public Utility Commission of Texas under Subsection | |
| (b) of this section, Subchapter F, Chapter 35, Utilities Code, as | |
| added by this Act, applies to all renewable energy generation | |
| facilities in this state, including: | |
| (1) renewable energy generation facilities that: | |
| (A) generate renewable energy before the | |
| effective date of this Act; or | |
| (B) are interconnected to a transmission | |
| facility before the effective date of this Act; and | |
| (2) renewable energy generation facilities the | |
| construction of which began before the effective date of this Act. | |
| (b) The Public Utility Commission of Texas by rule shall | |
| authorize a person who operates or constructs a facility described | |
| by Subsection (a)(1) or (2) of this section to continue to operate | |
| or construct the facility after the effective date of this Act while | |
| the person applies for a permit for the facility as required under | |
| Subchapter F, Chapter 35, Utilities Code, as added by this Act. The | |
| rules may require a person who operates or constructs a facility | |
| described by Subsection (a)(1) or (2) of this section to apply for a | |
| permit for the facility as required under Subchapter F, Chapter 35, | |
| Utilities Code, as added by this Act, by a certain date. | |
| SECTION 4. This Act takes effect September 1, 2025. |
Texto oficial de la Legislatura de Texas. El formato se adaptó para leerlo en Ratifi.