Enrolled
El texto subrayado se agregaría a la ley vigente. El texto tachado se eliminaría.
| H.B. No. 3809 |
| AN ACT | ||
| relating to the removal of battery energy storage facilities. | ||
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
| SECTION 1. Title 6, Utilities Code, is amended by adding | ||
| Chapter 303 to read as follows: | ||
| CHAPTER 303. BATTERY ENERGY STORAGE FACILITY AGREEMENTS | ||
| Sec. 303.0001. DEFINITIONS. In this chapter: | ||
| (1) "Battery energy storage facility" includes: | ||
| (A) a battery energy storage resource; and | ||
| (B) any facility or equipment necessary to | ||
| support the operation of a battery energy storage resource, other | ||
| than a facility or equipment owned by an electric utility, as | ||
| defined by Section 31.002. | ||
| (2) "Battery energy storage facility agreement" means | ||
| a lease agreement between a grantee and a landowner that authorizes | ||
| the grantee to operate a battery energy storage facility on the | ||
| leased property. | ||
| (3) "Battery energy storage resource" means an | ||
| electrochemical device, whether connected at the transmission or | ||
| distribution level, with a capacity of one megawatt hour or greater | ||
| that charges from the grid or a colocated generation resource and | ||
| discharges that energy at a later time. | ||
| (4) "Battery operation date" means the date on which a | ||
| battery energy storage resource is first used for its intended | ||
| purpose. | ||
| (5) "Grantee" means a person, other than an electric | ||
| utility as defined by Section 31.002, who: | ||
| (A) leases property from a landowner; and | ||
| (B) operates a battery energy storage facility on | ||
| the property. | ||
| (6) "Recycle" means the processing, including | ||
| disassembling, dismantling, and shredding of battery energy | ||
| storage cells, modules or other equipment, or their components, to | ||
| recover a usable product. | ||
| Sec. 303.0002. APPLICABILITY. Except as provided by | ||
| Section 303.0004(c), this chapter applies only to an agreement that | ||
| authorizes a grantee to operate a battery energy storage facility | ||
| that is not subject to Chapter 301 or 302. | ||
| Sec. 303.0003. WAIVER VOID; REMEDIES. (a) A provision of a | ||
| battery energy storage facility agreement that purports to waive a | ||
| right or exempt a grantee from a liability or duty established by | ||
| this chapter is void. | ||
| (b) A person who is harmed by a violation of this chapter is | ||
| entitled to appropriate injunctive relief to prevent further | ||
| violation of this chapter. | ||
| (c) The provisions of this section are not exclusive. The | ||
| remedies provided in this section are in addition to any other | ||
| procedures or remedies provided by other law. | ||
| Sec. 303.0004. REQUIRED AGREEMENT PROVISIONS ON FACILITY | ||
| REMOVAL. (a) A battery energy storage facility agreement must | ||
| provide that the grantee is responsible for removing the battery | ||
| energy storage facility from the landowner's property and that the | ||
| grantee shall, in accordance with any other applicable laws or | ||
| regulations, safely: | ||
| (1) clear, clean, and remove from the property each | ||
| battery energy storage resource, transformer, and substation | ||
| installed and owned by the grantee; | ||
| (2) for each foundation installed in the ground for a | ||
| battery energy storage resource, transformer, or substation | ||
| installed and owned by the grantee: | ||
| (A) clear, clean, and remove the foundation from | ||
| the ground to a depth of at least three feet below the surface grade | ||
| of the land in which the foundation is installed; and | ||
| (B) ensure that each hole or cavity created in | ||
| the ground by the removal is filled with soil of the same type or a | ||
| similar type as the predominant soil found on the property; | ||
| (3) for each buried cable, including power, | ||
| fiber-optic, and communications cables, installed and owned by the | ||
| grantee: | ||
| (A) clear, clean, and remove the cable from the | ||
| ground to a depth of at least three feet below the surface grade of | ||
| the land in which the cable is installed; and | ||
| (B) ensure that each hole or cavity created in | ||
| the ground by the removal is filled with soil of the same type or a | ||
| similar type as the predominant soil found on the property; and | ||
| (4) clear, clean, and remove from the property each | ||
| overhead power or communications line installed and owned by the | ||
| grantee on the property. | ||
| (b) The agreement must provide that the grantee is | ||
| responsible for: | ||
| (1) collecting and reusing or recycling, or shipping | ||
| for reuse or recycling, all components of the battery energy | ||
| storage facility practicably capable of being reused or recycled, | ||
| in accordance with any other applicable laws or regulations; and | ||
| (2) properly disposing of components of the battery | ||
| energy storage facility not practicably capable of being reused or | ||
| recycled: | ||
| (A) at a facility authorized under state and | ||
| federal law to dispose of hazardous substances for a component | ||
| considered hazardous under those laws; or | ||
| (B) for nonhazardous components, at a municipal | ||
| solid waste landfill or other appropriate waste disposal facility | ||
| authorized under state and federal law to dispose of that type of | ||
| component. | ||
| (c) A wind power facility agreement entered into under | ||
| Chapter 301 or solar power facility agreement entered into under | ||
| Chapter 302 that authorizes the operation of a battery energy | ||
| storage facility must include the provisions described by | ||
| Subsection (b) and the financial assurance required by those | ||
| chapters must be sufficient to secure the performance of the | ||
| grantee's obligations under that subsection, in the manner provided | ||
| by Section 303.0005. | ||
| (d) The agreement must provide that, at the request of the | ||
| landowner, the grantee shall: | ||
| (1) clear, clean, and remove each road constructed by | ||
| the grantee on the property; and | ||
| (2) ensure that each hole or cavity created in the | ||
| ground by the removal is filled with soil of the same type or a | ||
| similar type as the predominant soil found on the property. | ||
| (e) The agreement must provide that, at the request of the | ||
| landowner, if reasonable, the grantee shall: | ||
| (1) remove from the property all rocks over 12 inches | ||
| in diameter excavated during the decommissioning or removal | ||
| process; | ||
| (2) return the property to a tillable state using | ||
| scarification, V-rip, or disc methods, as appropriate; and | ||
| (3) ensure that: | ||
| (A) each hole or cavity created in the ground by | ||
| the removal is filled with soil of the same type or a similar type as | ||
| the predominant soil found on the property; and | ||
| (B) the surface is returned as near as reasonably | ||
| possible to the same condition as before the grantee dug holes or | ||
| cavities, including by reseeding pastureland with native grasses | ||
| prescribed by an appropriate governmental agency, if any. | ||
| (f) The landowner shall make a request under Subsection (d) | ||
| or (e) not later than the 180th day after the later of: | ||
| (1) the date on which the landowner receives from the | ||
| grantee via certified mail a copy of a notification of intent to | ||
| suspend operations filed with a grid operator indicating an intent | ||
| to permanently cease operations; or | ||
| (2) the date the landowner receives written notice of | ||
| intent to decommission the battery energy storage facility from the | ||
| grantee. | ||
| Sec. 303.0005. REQUIRED AGREEMENT PROVISIONS ON FINANCIAL | ||
| ASSURANCE. (a) A battery energy storage facility agreement must | ||
| provide that the grantee shall obtain and deliver to the landowner | ||
| evidence of financial assurance that conforms to the requirements | ||
| of this section to secure the performance of the grantee's | ||
| obligations under Section 303.0004. Acceptable forms of financial | ||
| assurance include a parent company guaranty with a minimum | ||
| investment grade credit rating for the parent company issued by a | ||
| major domestic credit rating agency, a letter of credit, a bond, or | ||
| another form of financial assurance reasonably acceptable to the | ||
| landowner. | ||
| (b) The amount of financial assurance must be at least equal | ||
| to the estimated amount by which the cost of removing the battery | ||
| energy storage facilities from the landowner's property, recycling | ||
| or disposing of all the components of the battery energy storage | ||
| facilities, and restoring the property to as near as reasonably | ||
| possible the condition of the property as of the date the agreement | ||
| begins, as described by Section 303.0004, exceeds the salvage value | ||
| of the battery energy storage facilities, less any portion of the | ||
| value of the battery energy storage facilities pledged to secure | ||
| outstanding debt. | ||
| (c) The agreement must provide that: | ||
| (1) the estimated cost of removing the battery energy | ||
| storage facilities from the landowner's property, recycling or | ||
| disposing of all the components of the battery energy storage | ||
| facilities, and restoring the property to as near as reasonably | ||
| possible the condition of the property as of the date the agreement | ||
| begins, as described by Section 303.0004, and the estimated salvage | ||
| value of the battery energy storage facilities must be determined | ||
| by an independent, third-party professional engineer licensed in | ||
| this state; | ||
| (2) the grantee must deliver to the landowner the | ||
| estimated cost of removal and recycling or disposal of the battery | ||
| energy storage facilities and the salvage value on or before the | ||
| 10th anniversary of the battery operation date of the grantee's | ||
| battery energy storage resources located on the landowner's | ||
| property; and | ||
| (3) the grantee must deliver an updated estimate of | ||
| the cost and salvage value described by Subdivision (2) at least | ||
| once every five years after the initial estimate for the remainder | ||
| of the term of the agreement. | ||
| (d) The grantee is responsible for the costs of obtaining | ||
| financial assurance described by this section and determining the | ||
| estimated removal, recycling, and disposal costs and salvage value. | ||
| (e) The agreement must provide that the grantee shall | ||
| deliver financial assurance not later than the earlier of: | ||
| (1) the date the battery energy storage facility | ||
| agreement is terminated; or | ||
| (2) the 15th anniversary of the battery operation date | ||
| of the grantee's battery energy storage resources located on the | ||
| landowner's property. | ||
| (f) The grantee is responsible for ensuring that the amount | ||
| of financial assurance remains sufficient to cover the amount | ||
| required by Subsection (b), consistent with the estimates required | ||
| by this section. | ||
| (g) The grantee may not cancel financial assurance before | ||
| the date the grantee has completed the grantee's obligation to | ||
| remove the grantee's battery energy storage facilities located on | ||
| the landowner's property in the manner provided by this chapter, | ||
| unless the grantee provides the landowner with replacement | ||
| financial assurance at the time of or before the cancellation. In | ||
| the event of a transfer of ownership of the grantee's battery energy | ||
| storage facilities, financial assurance provided by the grantee | ||
| shall remain in place until the date evidence of financial | ||
| assurance meeting the requirements of this chapter is provided to | ||
| the landowner. | ||
| SECTION 2. The changes in law made by this Act apply only to | ||
| an agreement entered into on or after the effective date of this | ||
| Act. An agreement entered into before the effective date of this | ||
| Act is governed by the law in effect on the date the agreement was | ||
| entered into, and the former law is continued in effect for that | ||
| purpose. | ||
| SECTION 3. This Act takes effect September 1, 2025. | ||
| ______________________________ | ______________________________ | |
| President of the Senate | Speaker of the House | |
| I certify that H.B. No. 3809 was passed by the House on April | ||
| 29, 2025, by the following vote: Yeas 145, Nays 0, 1 present, not | ||
| voting; and that the House concurred in Senate amendments to H.B. | ||
| No. 3809 on May 19, 2025, by the following vote: Yeas 128, Nays 0, | ||
| 1 present, not voting. | ||
| ______________________________ | ||
| Chief Clerk of the House | ||
| I certify that H.B. No. 3809 was passed by the Senate, with | ||
| amendments, on May 13, 2025, by the following vote: Yeas 31, Nays | ||
| 0. | ||
| ______________________________ | ||
| Secretary of the Senate | ||
| APPROVED: __________________ | ||
| Date | ||
| __________________ | ||
| Governor |
Texto oficial de la Legislatura de Texas. El formato se adaptó para leerlo en Ratifi.