| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subchapter A, Chapter 17, Utilities Code, is | |
| amended by adding Section 17.011 to read as follows: | |
| Sec. 17.011. METER SOCKET ADAPTER. The commission by rule | |
| shall require an electric utility to modify the utility's service | |
| requirements to authorize the use of a meter socket adapter owned by | |
| a residential customer of retail electric service and certified by | |
| a nationally recognized testing laboratory to support residential | |
| distributed generation and energy storage systems. | |
| SECTION 2. Section 31.002, Utilities Code, is amended by | |
| adding Subdivision (4-c) to read as follows: | |
| (4-c) "Distributed energy resource" means a resource | |
| located on the distribution system, on a subsystem of the | |
| distribution system, or on the customer's side of the meter, | |
| including: | |
| (A) a generation resource or storage resource | |
| that provides electricity onto the distribution system; and | |
| (B) a load resource capable of modifying its | |
| electricity usage in response to grid conditions. | |
| SECTION 3. Section 39.002, Utilities Code, is amended to | |
| read as follows: | |
| Sec. 39.002. APPLICABILITY. This chapter, other than | |
| Sections 39.151, 39.1516, 39.155, 39.157(e), 39.161, 39.162, | |
| 39.163, 39.203, 39.9051, 39.9052, [ |
|
| Subchapters M and N, does not apply to a municipally owned utility | |
| or an electric cooperative. Sections 39.157(e) and 39.203 apply | |
| only to a municipally owned utility or an electric cooperative that | |
| is offering customer choice. If there is a conflict between the | |
| specific provisions of this chapter and any other provisions of | |
| this title, except for Chapters 40 and 41, the provisions of this | |
| chapter control. | |
| SECTION 4. Section 39.3515, Utilities Code, is amended by | |
| amending Subsection (b) and adding Subsection (c) to read as | |
| follows: | |
| (b) The commission shall adopt [ |
|
| registration requirements for the aggregation of distributed | |
| energy resources. | |
| (c) The commission shall: | |
| (1) establish the aggregate distributed energy | |
| resource pilot project (Project 53911) as a formal program; | |
| (2) require the independent organization certified | |
| under Section 39.151 for the ERCOT power region to: | |
| (A) increase participation in the program by: | |
| (i) eliminating capacity- and load | |
| zone-based limitations; | |
| (ii) allowing for the participation of an | |
| aggregated distributed energy resource in the wholesale energy | |
| market if the resource has a capacity of 160 megawatts or less and | |
| complies with all applicable commission requirements; | |
| (iii) allowing for the participation of an | |
| aggregated distributed energy resource in the ancillary services | |
| market if the resource has a capacity of 80 megawatts or less and | |
| complies with all applicable commission requirements; and | |
| (iv) allowing for the participation in the | |
| wholesale energy and ancillary services markets, without | |
| security-constrained economic dispatch restrictions, of load | |
| resource types that respond to demand response instructions with | |
| blocks of demand; and | |
| (B) incorporate aggregated noncontrollable load | |
| resources into the program's governing documents; and | |
| (3) provide that, when the independent organization | |
| certified under Section 39.151 for the ERCOT power region issues an | |
| emergency energy alert, a distributed energy resource that | |
| participates in the program is entitled to the same legal | |
| protections and subject to the same performance standards as | |
| another comparable energy resource. | |
| SECTION 5. Subchapter Z, Chapter 39, Utilities Code, is | |
| amended by adding Sections 39.9155 and 39.9161 to read as follows: | |
| Sec. 39.9155. DISTRIBUTED ENERGY RESOURCES. (a) The | |
| commission by rule shall: | |
| (1) provide for an expedited application process for | |
| the interconnection of distributed energy resources; | |
| (2) adopt statewide technical requirements for | |
| interconnected distributed energy resources; | |
| (3) provide for an expedited approval process for the | |
| installation of distributed energy resources with a capacity of | |
| less than 50 kilowatts; and | |
| (4) authorize the management of distributed energy | |
| resource import and export limitations using power control systems | |
| that are tested and certified by a nationally recognized testing | |
| laboratory. | |
| (b) The commission shall review the requirements adopted | |
| under Subsection (a)(2) at least once every two years and update | |
| those requirements as necessary for public safety. | |
| (c) Compliance with rules adopted under Subsection (a) by a | |
| provider of electric service which is a municipally owned utility | |
| shall be administered solely by the governing body of the | |
| municipally owned utility, which shall adopt, implement, and | |
| enforce, as to the municipally owned utility, rules having the | |
| effect of accomplishing the objectives of this section. | |
| (d) The commission by rule shall: | |
| (1) ensure that owners of distributed energy resources | |
| are fairly compensated for contributions to grid resilience, | |
| including through retail tariffs or other market mechanisms, with | |
| compensation that reflects the locational and temporal value of the | |
| resources; and | |
| (2) establish standards for telemetry provided to the | |
| independent organization certified under Section 39.151 for the | |
| ERCOT power region by an owner or operator of a distributed energy | |
| resource that include real-time two-second protocols and clarified | |
| validation metrics. | |
| (e) The commission may enter into public-private | |
| partnerships and allocate grants for the purposes of this section | |
| if money is available for those purposes under other law. | |
| Sec. 39.9161. INTERCONNECTION OF ELECTRIC VEHICLES. (a) | |
| In this section: | |
| (1) "Electric vehicle" has the meaning assigned by | |
| Section 42.0102. | |
| (2) "Interconnection" means the right of an electric | |
| vehicle owner to physically connect the electric vehicle to an | |
| electricity distribution system and the technical requirements, | |
| rules, or processes for the connection. | |
| (b) The commission by rule shall establish safety, | |
| technical, and performance standards for electric vehicles that may | |
| be interconnected. In adopting the rules, the commission shall | |
| consider standards published by the Underwriters Laboratories, the | |
| National Electrical Code, the National Electrical Safety Code, and | |
| the Institute of Electrical and Electronics Engineers. | |
| (c) The commission by rule shall establish a program to | |
| allow the sale of electricity stored by an electric vehicle to the | |
| transmission grid and distribution system. The rules must | |
| authorize an electric utility or retail electric provider to | |
| contract with an electric vehicle owner so that: | |
| (1) electricity stored by the electric vehicle is made | |
| available for sale to the transmission grid and distribution | |
| system; and | |
| (2) the value of that electricity is credited to the | |
| electric vehicle owner. | |
| SECTION 6. Not later than December 31, 2025, the Public | |
| Utility Commission of Texas shall adopt the rules required by this | |
| Act. | |
| SECTION 7. This Act takes effect immediately if it receives | |
| a vote of two-thirds of all the members elected to each house, as | |
| provided by Section 39, Article III, Texas Constitution. If this | |
| Act does not receive the vote necessary for immediate effect, this | |
| Act takes effect September 1, 2025. |
Texto oficial de la Legislatura de Texas. El formato se adaptó para leerlo en Ratifi.