| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
| SECTION 1. Subchapter F, Chapter 13, Water Code, is amended | ||
| by adding Section 13.1831 to read as follows: | ||
| Sec. 13.1831. TEST YEAR. A regulatory authority shall fix | ||
| rates for water and sewer services for a Class A, B, C, or D utility | ||
| based on a test year the utility selects that: | ||
| (1) includes historic, future, or combined historic | ||
| and future data; | ||
| (2) begins on the first day of a calendar or fiscal | ||
| year quarter; and | ||
| (3) is a consecutive 12-month period that: | ||
| (A) begins not later than 18 months after the | ||
| date the utility files the statement of intent to change rates; and | ||
| (B) ends not earlier than 18 months before the | ||
| date the utility files the statement of intent to change rates. | ||
| SECTION 2. Section 13.183(a), Water Code, is amended to | ||
| read as follows: | ||
| (a) In fixing the rates for water and sewer services, the | ||
| regulatory authority shall fix its overall revenues at a level that | ||
| will: | ||
| (1) permit the utility a reasonable opportunity to | ||
| earn a reasonable return on its invested capital used and useful in | ||
| rendering service to the public, based on test year information, | ||
| over and above its reasonable and necessary operating expenses; and | ||
| (2) preserve the financial integrity of the utility. | ||
| SECTION 3. Section 13.184, Water Code, is amended by | ||
| amending Subsection (a) and adding Subsection (d) to read as | ||
| follows: | ||
| (a) Unless the utility commission establishes alternate | ||
| rate methodologies in accordance with Section 13.183(c), the | ||
| utility commission may not prescribe any rate that will yield more | ||
| than a fair return on the invested capital used and useful in | ||
| rendering service to the public based on test year information. The | ||
| governing body of a municipality exercising its original | ||
| jurisdiction over rates and services may use alternate ratemaking | ||
| methodologies established by ordinance or by utility commission | ||
| rule in accordance with Section 13.183(c). Unless the municipal | ||
| regulatory authority uses alternate ratemaking methodologies | ||
| established by ordinance or by utility commission rule in | ||
| accordance with Section 13.183(c), it may not prescribe any rate | ||
| that will yield more than a fair return on the invested capital used | ||
| and useful in rendering service to the public based on test year | ||
| information. | ||
| (d) For a utility that uses a future or combined historic | ||
| and future test year in a rate proceeding, if the regulatory | ||
| authority determines in the next rate proceeding for that utility | ||
| that the test year information used for the utility resulted in the | ||
| utility's rates yielding more than a fair return on the utility's | ||
| invested capital used and useful in rendering service to the | ||
| public, the regulatory authority shall require the utility to | ||
| refund to customers money collected in excess of a rate that would | ||
| have yielded a fair return during the period in which the excessive | ||
| rate was collected. | ||
| SECTION 4. Section 13.185, Water Code, is amended by | ||
| amending Subsections (b), (d), and (j) and adding Subsections (k), | ||
| (l), and (m) to read as follows: | ||
| (b) Utility rates shall be based on the original cost of | ||
| property used by and useful to the utility during the test year in | ||
| providing service, including, if necessary to the financial | ||
| integrity of the utility, construction work in progress at cost as | ||
| recorded on the books of the utility. The inclusion of construction | ||
| work in progress is an exceptional form of rate relief to be granted | ||
| only on the demonstration by the utility by clear and convincing | ||
| evidence that the inclusion is in the ratepayers' best interest and | ||
| is necessary to the financial integrity of the utility. | ||
| Construction work in progress may not be included in the rate base | ||
| for major projects under construction to the extent that those | ||
| projects have been inefficiently or imprudently planned or managed. | ||
| Original cost is the actual money cost or the actual money value of | ||
| any consideration paid, other than money, of the property at the | ||
| time it shall have been dedicated to public use, whether by the | ||
| utility that is the present owner or by a predecessor, less | ||
| depreciation. Utility property funded by explicit customer | ||
| agreements or customer contributions in aid of construction such as | ||
| surcharges may not be included in invested capital. | ||
| (d) Net income is the total revenues of the utility less all | ||
| reasonable and necessary expenses as determined by the regulatory | ||
| authority. The regulatory authority shall: | ||
| (1) base a utility's expenses on [ |
||
| information [ |
||
| determined by utility commission rules; and | ||
| (2) determine expenses and revenues in a manner | ||
| consistent with Subsections (e) through (h) of this section. | ||
| (j) Depreciation expense included in the cost of service | ||
| includes depreciation on all [ |
||
| property owned by the utility except for property provided by | ||
| explicit customer agreements or funded by customer contributions in | ||
| aid of construction. Depreciation on all [ |
||
| shall be allowed in the cost of service. | ||
| (k) Notwithstanding Subsection (b), the regulatory | ||
| authority shall allow inclusion in the rate base of facilities | ||
| projected to be in service through the end of the test year. | ||
| (l) A utility that selects a fully projected future test | ||
| year that meets the requirements of Section 13.1831(3)(A) shall: | ||
| (1) not later than the 30th day after the last day of | ||
| the last quarter of the test year, file with the regulatory | ||
| authority a statement that: | ||
| (A) describes the utility's actual results | ||
| experienced in the test year; and | ||
| (B) provides appropriate data to demonstrate the | ||
| accuracy of the estimates used for the test year; and | ||
| (2) serve a copy of the filing made under Subdivision | ||
| (1) on the parties of record in the rate proceeding in which the | ||
| final rate determination using the test year was entered. | ||
| (m) A utility that does not have the results or data | ||
| required to be filed under Subsection (l) before the required | ||
| filing date shall: | ||
| (1) file a written notice with the regulatory | ||
| authority stating the date on which the results or data will be | ||
| available; | ||
| (2) serve a copy of the filing made under Subdivision | ||
| (1) on the parties described by Subsection (l)(2); and | ||
| (3) make the filing required under Subsection (l) as | ||
| soon as possible after the results or data are available. | ||
| SECTION 5. Section 13.002(22), Water Code, is repealed. | ||
| SECTION 6. (a) Not later than September 1, 2026, the Public | ||
| Utility Commission of Texas shall adopt rules necessary to | ||
| implement the changes in law made by this Act. | ||
| (b) The changes in law made by this Act apply only to a rate | ||
| proceeding that commences on or after the effective date of the | ||
| rules described by Subsection (a) of this section. A rate | ||
| proceeding that commences before the effective date of the rules | ||
| described by Subsection (a) of this section is governed by the law | ||
| in effect on the date the proceeding commenced, and that law is | ||
| continued in effect for that purpose. | ||
| SECTION 7. This Act takes effect September 1, 2025. | ||
| ______________________________ | ______________________________ | |
| President of the Senate | Speaker of the House | |
| I certify that H.B. No. 2712 was passed by the House on May 6, | ||
| 2025, by the following vote: Yeas 135, Nays 13, 1 present, not | ||
| voting; and that the House concurred in Senate amendments to H.B. | ||
| No. 2712 on May 28, 2025, by the following vote: Yeas 101, Nays 38, | ||
| 1 present, not voting. | ||
| ______________________________ | ||
| Chief Clerk of the House | ||
| I certify that H.B. No. 2712 was passed by the Senate, with | ||
| amendments, on May 23, 2025, by the following vote: Yeas 26, Nays | ||
| 5. | ||
| ______________________________ | ||
| Secretary of the Senate | ||
| APPROVED: __________________ | ||
| Date | ||
| __________________ | ||
| Governor |
Texto oficial de la Legislatura de Texas. El formato se adaptó para leerlo en Ratifi.