South Carolina General Assembly 126th Session, 2025-2026
Bill 3560
Download This Bill in Microsoft Word Format
Indicates Matter Stricken Indicates New Matter
(Text matches printed bills. Document has been reformatted to meet World Wide Web specifications.)
H. 3560
STATUS INFORMATION
General Bill Sponsors: Reps. Brewer, Murphy, Robbins and Mitchell Document Path: LC-0047CM25.docx
Introduced in the House on January 14, 2025 Education and Public Works
HISTORY OF LEGISLATIVE ACTIONS
Date
Body
Action Description with journal page number
12/5/2024
House
Prefiled
12/5/2024
House
Referred to Committee on Education and Public Works
1/14/2025
House
Introduced and read first time (House Journal-page 245)
1/14/2025
House
Referred to Committee on Education and Public Works (House Journal-page 245)
View the latest legislative information at the website
VERSIONS OF THIS BILL
12/05/2024
A bill
10 párrafos sin cambios
TO AMEND THE SOUTH CAROLINA CODE OF LAWS BY ADDING SECTION 57-5-1710 SO AS TO PROVIDE THE DEPARTMENT OF TRANSPORTATION MAY ESTABLISH AND IMPLEMENT A PROJECT TO AWARD CONTRACTS USING THE "PHASE DESIGN-BUILD" PROJECT DELIVERY METHOD.
Be it enacted by the General Assembly of the State of South Carolina:
SECTION 1. Article 11, Chapter 5, Title 57 of the S.C. Code is amended by adding:
Section 57-5-1710. (A) As contained in this section, "Phase Design-Build" means a project delivery method that uses a stepped, or progressive qualifications-based selection process, followed by a progression to a contract price. The Department of Transportation must select the Phase Design-Build team exclusively on qualifications, without consideration of schedule or costs, which must deliver the project in two distinct phases with two separate contracts. The Phase Design-Build team is initially under contract for preconstruction activities including, but not limited to, developing preliminary designs, performing constructability reviews, and developing construction schedules and pricing. If the department and the Phase Design-Build team reach agreement on a guaranteed maximum construction cost, the department and the Phase Design-Build team will execute a second contract for completion of the preliminary designs and construction of the project.
(B) The department may only award a contract under this section if the department:
(1) determines the project cost is less than five hundred million dollars ($500,000,000);
(2) determines that it is in the public's interest to use the Phase Design-Build project delivery method; and
(3) prequalifies the prime contractor and lead designer firm that will be awarded the contract.
(C) The department shall develop and implement Phase Design-Build guidelines prior to awarding contracts pursuant to this section.
SECTION 2. This act takes effect upon approval by the Governor.