SENATE BILL NO. 762

A bill to amend 1939 PA 3, entitled

"An act to provide for the regulation and control of public and certain private utilities and other services affected with a public interest within this state; to provide for alternative energy suppliers and certain providers of electric vehicle charging services; to provide for licensing; to include municipally owned utilities and other providers of energy under certain provisions of this act; to create a public service commission and to prescribe and define its powers and duties; to abolish the Michigan public utilities commission and to confer the powers and duties vested by law on the public service commission; to provide for the powers and duties of certain state governmental officers and entities; to provide for the continuance, transfer, and completion of certain matters and proceedings; to abolish automatic adjustment clauses; to prohibit certain rate increases without notice and hearing; to qualify residential energy conservation programs permitted under state law for certain federal exemption; to create a fund; to encourage the utilization of resource recovery facilities; to prohibit certain acts and practices of providers of energy; to allow for the securitization of stranded costs; to reduce rates; to provide for appeals; to provide appropriations; to declare the effect and purpose of this act; to prescribe remedies and penalties; and to repeal acts and parts of acts,"

by amending section 5a (MCL 460.5a), as added by 1989 PA 33.

the people of the state of michigan enact:

Sec. 5a. (1) The Michigan public service On or before the first Monday of March each year, the commission shall make submit an annual report , summarizing that summarizes the activities of the commission , to the governor and the legislature. on or before the first Monday of March of each year. The annual report shall be must include a summary of commission activities and may include rules, opinions, and orders promulgated or entered by the commission during the calendar year covered by the annual report. The annual report shall must also contain any other information which that the commission considers to be of value.

(2) Not later than July 1, 2027, and by each July 1 thereafter, the commission shall publish a report on the commission's website that contains the following information:

(a) The total amount of water used by each data center in each public water supply's service area for the preceding calendar year. Not later than June 1, 2027, and by each June 1 thereafter, each public water supply shall submit to the commission the total water usage data described in this subdivision.

(b) The total amount of energy used by each data center, described in total gigawatts per year, for the preceding calendar year.

(3) As used in subsection (2):

(a) "Data center" means a facility that is designed and intended for housing, and does house, equipment to centralize the storage and processing of data.

(b) "Public water supply" means that term as defined in section 2 of the safe drinking water act, 1976 PA 399, MCL 325.1002.