H.B. No. 3223

Capriglione, et al.

A BILL TO BE ENTITLED

85 unchanged paragraphs

AN ACT

relating to statutes of limitation and repose for certain claims

involving the construction or repair of an improvement to real

property.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

SECTION 1. Sections 16.008(a) and (c), Civil Practice and

Remedies Code, are amended to read as follows:

(a) A [ Except as provided by Subsection (a-1), a ] person

must bring suit for damages for a claim listed in Subsection (b)

against a registered or licensed architect, engineer, interior

designer, or landscape architect in this state, who designs, plans,

or inspects the construction of an improvement to real property or

equipment attached to real property, not later than eight [ 10 ]

years after the substantial completion of the improvement or the

beginning of operation of the equipment in an action arising out of

a defective or unsafe condition of the real property, the

improvement, or the equipment.

(c) If the claimant presents a written claim for damages,

contribution, or indemnity to the architect, engineer, interior

designer, or landscape architect within the applicable limitations

period, the period is extended for[ :

[ (1) two years from the date the claim is presented,

for a claim to which Subsection (a) applies; or

[ (2) ] one year from the date the claim is presented[ ,

for a claim to which Subsection (a-1) applies ].

SECTION 2. Sections 16.009(a), (c), and (d), Civil Practice

and Remedies Code, are amended to read as follows:

(a) Except as provided by Subsection [ (a-1) or ] (a-2), a

claimant must bring suit for damages for a claim listed in

Subsection (b) against a person who constructs or repairs an

improvement to real property not later than eight [ 10 ] years after

the substantial completion of the improvement in an action arising

out of a defective or unsafe condition of the real property or a

deficiency in the construction or repair of the improvement.

(c) If the claimant presents a written claim for damages,

contribution, or indemnity to the person performing or furnishing

the construction or repair work during the applicable limitations

period, the period is extended for[ :

[ (1) two years from the date the claim is presented, for

a claim to which Subsection (a) applies; or

[ (2) ] one year from the date the claim is presented[ ,

for a claim to which Subsection (a-1) or (a-2) applies ].

(d) If the damage, injury, or death occurs during the last

year of the applicable limitations period, the claimant may bring

suit not later than one year [ two years ] after the day the cause of

action accrues.

SECTION 3. Sections 16.008(a-1) and 16.009(a-1), Civil

Practice and Remedies Code, are repealed.

SECTION 4. (a) Except as provided by this section, Section

16.008, Civil Practice and Remedies Code, as amended by this Act,

applies to a cause of action arising out of a design, plan, or

inspection of the construction of an improvement to real property

or equipment attached to real property that commences on or after

the effective date of this Act. Section 16.008, Civil Practice and

Remedies Code, as amended by this Act, does not apply to a cause of

action arising out of a design, plan, or inspection that commences

on or after the effective date of this Act under a contract entered

into before that date.

(b) A cause of action arising out of a design, plan, or

inspection of the construction of an improvement to real property

or equipment attached to real property that commenced before the

effective date of this Act or arising out of a design, plan, or

inspection of the construction of an improvement to real property

or equipment attached to real property that commences on or after

the effective date of this Act under a contract entered into before

that date is governed by the law applicable to the cause of action

immediately before the effective date of this Act, and that law is

continued in effect for that purpose.

SECTION 5. (a) Except as provided by this section, Section

16.009, Civil Practice and Remedies Code, as amended by this Act,

applies to a cause of action arising out of construction or repair

of an improvement to real property that commences on or after the

effective date of this Act. Section 16.009, Civil Practice and

Remedies Code, as amended by this Act, does not apply to a cause of

action arising out of construction or repair of an improvement to

real property that commences on or after the effective date of this

Act under a contract entered into before that date.

(b) A cause of action arising out of construction or repair

of an improvement to real property that commenced before the

effective date of this Act or arising out of construction or repair

of an improvement to real property that commences on or after the

effective date of this Act under a contract entered into before that

date is governed by the law applicable to the cause of action

immediately before the effective date of this Act, and that law is

continued in effect for that purpose.

SECTION 6. This Act takes effect September 1, 2025.