Engrossed
Underlined text would be added to current law. Struck-through text would be removed.
| 89R2163 MZM-F | ||
| By: Leach, Martinez, Metcalf, Gervin-Hawkins, | H.B. No. 3223 | |
| Capriglione, et al. |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to statutes of limitation and repose for certain claims | |
| involving the construction or repair of an improvement to real | |
| property. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Sections 16.008(a) and (c), Civil Practice and | |
| Remedies Code, are amended to read as follows: | |
| (a) A [ |
|
| must bring suit for damages for a claim listed in Subsection (b) | |
| against a registered or licensed architect, engineer, interior | |
| designer, or landscape architect in this state, who designs, plans, | |
| or inspects the construction of an improvement to real property or | |
| equipment attached to real property, not later than eight [ |
|
| years after the substantial completion of the improvement or the | |
| beginning of operation of the equipment in an action arising out of | |
| a defective or unsafe condition of the real property, the | |
| improvement, or the equipment. | |
| (c) If the claimant presents a written claim for damages, | |
| contribution, or indemnity to the architect, engineer, interior | |
| designer, or landscape architect within the applicable limitations | |
| period, the period is extended for[ |
|
| [ |
|
| [ |
|
| SECTION 2. Sections 16.009(a), (c), and (d), Civil Practice | |
| and Remedies Code, are amended to read as follows: | |
| (a) Except as provided by Subsection [ |
|
| claimant must bring suit for damages for a claim listed in | |
| Subsection (b) against a person who constructs or repairs an | |
| improvement to real property not later than eight [ |
|
| the substantial completion of the improvement in an action arising | |
| out of a defective or unsafe condition of the real property or a | |
| deficiency in the construction or repair of the improvement. | |
| (c) If the claimant presents a written claim for damages, | |
| contribution, or indemnity to the person performing or furnishing | |
| the construction or repair work during the applicable limitations | |
| period, the period is extended for[ |
|
| [ |
|
| [ |
|
| (d) If the damage, injury, or death occurs during the last | |
| year of the applicable limitations period, the claimant may bring | |
| suit not later than one year [ |
|
| action accrues. | |
| SECTION 3. Sections 16.008(a-1) and 16.009(a-1), Civil | |
| Practice and Remedies Code, are repealed. | |
| SECTION 4. (a) Except as provided by this section, Section | |
| 16.008, Civil Practice and Remedies Code, as amended by this Act, | |
| applies to a cause of action arising out of a design, plan, or | |
| inspection of the construction of an improvement to real property | |
| or equipment attached to real property that commences on or after | |
| the effective date of this Act. Section 16.008, Civil Practice and | |
| Remedies Code, as amended by this Act, does not apply to a cause of | |
| action arising out of a design, plan, or inspection that commences | |
| on or after the effective date of this Act under a contract entered | |
| into before that date. | |
| (b) A cause of action arising out of a design, plan, or | |
| inspection of the construction of an improvement to real property | |
| or equipment attached to real property that commenced before the | |
| effective date of this Act or arising out of a design, plan, or | |
| inspection of the construction of an improvement to real property | |
| or equipment attached to real property that commences on or after | |
| the effective date of this Act under a contract entered into before | |
| that date is governed by the law applicable to the cause of action | |
| immediately before the effective date of this Act, and that law is | |
| continued in effect for that purpose. | |
| SECTION 5. (a) Except as provided by this section, Section | |
| 16.009, Civil Practice and Remedies Code, as amended by this Act, | |
| applies to a cause of action arising out of construction or repair | |
| of an improvement to real property that commences on or after the | |
| effective date of this Act. Section 16.009, Civil Practice and | |
| Remedies Code, as amended by this Act, does not apply to a cause of | |
| action arising out of construction or repair of an improvement to | |
| real property that commences on or after the effective date of this | |
| Act under a contract entered into before that date. | |
| (b) A cause of action arising out of construction or repair | |
| of an improvement to real property that commenced before the | |
| effective date of this Act or arising out of construction or repair | |
| of an improvement to real property that commences on or after the | |
| effective date of this Act under a contract entered into before that | |
| date is governed by the law applicable to the cause of action | |
| immediately before the effective date of this Act, and that law is | |
| continued in effect for that purpose. | |
| SECTION 6. This Act takes effect September 1, 2025. |
Official text from the Texas Legislature. Formatting has been adapted for reading on Ratifi.