Florida Senate
-
2026
CS for SB 548
By
Senator McClain
the Committee on Community Affairs; and Senator McClain
9-00714-26 2026548__578-02033-26 2026548c1
1 A bill to be entitled
2 An act relating to growth management; amending s.
3 163.3164, F.S.; defining the term “plan-based
4 methodology”; amending s. 163.31803177, F.S.; deleting anproviding
5 requirements for coordination mechanisms that are
6 required for certain agreements required as part of
7 the intergovernmental coordination element of a
8 comprehensive plan; amending s. 163.3180, F.S.;
9 requiring that certain interlocal agreements use a
10 plan-based methodology for a certain purpose;
11 prohibiting certain interlocal agreements from
512 exceptionextending tobeyond a specified date; deleting an applicability provision relating to
13 exception to an applicability provision relating to
614 concurrency; amending s. 163.31801, F.S.; defining the
715 term “extraordinary circumstances”; requiring that a
816 demonstrated-need study use a plan-based methodology for
917 for a certain purpose; requiring that certain conditionscapacity
18 standards be specified in a certain impact fee study;
1019 requiring that a demonstrated-need study be shown to exist in order to demonstrate
11 extraordinary circumstances; revising the voting
20 accompanied by a certain declaration; requiring local
21 governments, school districts, and special districts
1222 thresholdto requireduse localized data for approvala ofcertain an ordinancepurpose;
23 prohibiting local governments, school districts, and
24 special districts from using certain data for a
25 specified purpose; prohibiting local governments,
26 school districts, and special districts from including
27 certain deductions in certain impact fee increases and
1328 from increasing an impact fee rates beyond certain phase-inphase
29 in limitations by more than a specified percentage
30 within a certain timeframe; providing that a
31 prevailing petitioner is entitled to an impact fee
32 overpayment refund, with interest, under certain
1433 limitationscircumstances; prohibitingrequiring local governments, from usingschool
34 districts, and special districts to issue such refunds
1535 certain data forwithin a specified purposetimeframe; prohibitingproviding that certain
16 local governments from including certain deductions in
17 certain impact fee increases; prohibiting local
36 prevailing petitioners are entitled to reasonable
1837 governmentsattorney fees and schoolcosts; districtsamending froms. increasing212.055, F.S.;
19 impact fee rates beyond certain phase-in limitations
20 by more than a specified percentage within a certain
2138 timeframeconforming a cross-reference; providing thatan certain prevailing partieseffective
22 in actions challenging certain impact fees are
23 entitled to reasonable attorney fees and costs;
24 amending s. 212.055, F.S.; conforming a cross
25 reference; providing an effective date.
39 date.
40
41 Be It Enacted by the Legislature of the State of Florida:
2642
27 Be It Enacted by the Legislature of the State of Florida:
28
2943 Section 1. Present subsections (39) through (54) of section
3044 163.3164, Florida Statutes, are redesignated as subsections (40)
3145 through (55), respectively, and a new subsection (39) is added
3246 to that section, to read:
3347 163.3164 Community Planning Act; definitions.—As used in
3448 this act:
35
49
(39) “Plan-based methodology
3 unchanged paragraphs
”
means a
study
methodology
36
50
that uses
the most recent and localized data to project growth
37
51
within a jurisdiction over a
5
10
-year period,
anticipate
capacity
38
52
impacts on
5 unchanged paragraphs
relevant
system
s
which will be
created by th
e
3953
projected growth, and
establish
a list of capital projects to be
4054
constructed
or purchased
constructed in a defined time period to mitigate th
55
th
e anticipated
41
capacity impact
s
as part of a new or updated impact fee study.
42
The
56
impact fee study. The
capital projects
identified in the study
57
and any necessary interlocal agreement
must
comport with the
43
58
the requirements of
s.
163.3177(6)(h)
.
4459 Section 2. Paragraph (jh) of subsection (56) of section
4560 163.31803177, Florida Statutes, is amended to read:
4661 163.31803177 Concurrency.—Required and optional elements of comprehensive
47 (5)
48 (j)1. If a county and municipality charge the developer of
49 a new development or redevelopment a fee for transportation
50 capacity impacts, the county and municipality must create and
62 plan; studies and surveys.—
63 (6) In addition to the requirements of subsections (1)-(5),
64 the comprehensive plan shall include the following elements:
51 execute65 (h)1. An anintergovernmental interlocalcoordination agreementelement to coordinate the mitigation ofshowing
52 their respective transportation capacity impacts.
53 2. The interlocal agreement must, at a minimum:
54 a. Ensure that any new development or redevelopment is not
55 charged twice for the same transportation capacity impacts.
56 b. Establish a plan-based methodology for determining the
57 legally permissible fee to be charged to a new development or
58 redevelopment.
66 relationships and stating principles and guidelines to be used
67 in coordinating the adopted comprehensive plan with the plans of
68 school boards, regional water supply authorities, and other
69 units of local government providing services but not having
70 regulatory authority over the use of land, with the
59 c. Require71 comprehensive plans of adjacent municipalities, the county or municipality issuing the building,
60 permit to collect the fee, unless agreed to otherwise.
61 d. Provide a method for the proportionate distribution of
62 the revenue collected by the county or municipality to address
72 adjacent counties, or the region, with the state comprehensive
73 plan and with the applicable regional water supply plan approved
74 pursuant to s. 373.709, as the case may require and as such
6375 theadopted transportationplans capacityor impactsplans in preparation may exist. This element of a new development or
64 redevelopment, or provide a method of assigning responsibility
76 the local comprehensive plan must demonstrate consideration of
77 the particular effects of the local plan, when adopted, upon the
78 development of adjacent municipalities, the county, adjacent
6579 forcounties, or the mitigationregion, ofor upon the transportationstate capacitycomprehensive impactsplan,
80 as the case may require.
81 a. The intergovernmental coordination element must provide
82 procedures for identifying and implementing joint planning
6683 belongingareas, toespecially for the countypurpose andof theannexation, municipality.municipal
84 incorporation, and joint infrastructure service areas.
85 b. The intergovernmental coordination element shall provide
86 for a dispute resolution process, as established pursuant to s.
87 186.509, for bringing intergovernmental disputes to closure in a
88 timely manner.
89 c. The intergovernmental coordination element shall provide
67 3. By October 1, 2025, if an90 for interlocal agreementagreements isas notestablished pursuant to s.
68 executed pursuant to this paragraph:
69 a. The fee charged to a new development or redevelopment
70 shall be based on the transportation capacity impacts
71 apportioned to the county and municipality as identified in the
72 developer’s traffic impact study or the mobility plan adopted by
73 the county or municipality.
74 b. The developer shall receive a 10 percent reduction in
75 the total fee calculated pursuant to sub-subparagraph a.
76 c. The county or municipality issuing the building permit
77 must collect the fee charged pursuant to sub-subparagraphs a.
91 333.03(1)(b).
92 2. The intergovernmental coordination element shall also
93 state principles and guidelines to be used in coordinating the
7894 andadopted b.comprehensive andplan distributewith the proceedsplans of suchschool fee to the countyboards and
79 municipality within 60 days after the developer’s payment.
80 4. This paragraph does not apply to:
81 a. A county as defined in s. 125.011(1).
82 b. A county or municipality that has entered into, or
83 otherwise updated, an existing interlocal agreement, as of
84 October 1, 2024, to coordinate the mitigation of transportation
85 impacts. However, if such existing interlocal agreement is
86 terminated, the affected county and municipality that have
87 entered into the agreement
95 other units of local government providing facilities and
96 services but not having regulatory authority over the use of
97 land. In addition, the intergovernmental coordination element
98 must describe joint processes for collaborative planning and
99 decisionmaking on population projections and public school
100 siting, the location and extension of public facilities subject
101 to concurrency, and siting facilities with countywide
102 significance, including locally unwanted land uses whose nature
103 and identity are established in an agreement.
104 3. Within 1 year after adopting their intergovernmental
105 coordination elements, each county, all the municipalities
106 within that county, the district school board, and any unit of
107 local government service providers in that county shall
108 establish by interlocal or other formal agreement executed by
109 all affected entities, the joint processes described in this
110 subparagraph consistent with their adopted intergovernmental
111 coordination elements. The agreement must:
112 a. Ensure that the local government addresses through
113 coordination mechanisms the impacts of development proposed in
114 the local comprehensive plan upon development in adjacent
115 municipalities, the county, adjacent counties, the region, and
116 the state. The area of concern for municipalities shall include
117 adjacent municipalities, the county, and counties adjacent to
118 the municipality. The area of concern for counties shall include
119 all municipalities within the county, adjacent counties, and
120 adjacent municipalities.
Such coordination mechanisms must
121
include plans to provide mitigation funding to address any
122
extrajurisdictional impacts of development, consistent with the
123
requirements of s. 163.3180(5)(j).
124 b. Ensure coordination in establishing level of service
125 standards for public facilities with any state, regional, or
126 local entity having operational and maintenance responsibility
127 for such facilities.
128 Section 3. Paragraph (j) of subsection (5) of section
129 163.3180, Florida Statutes, is amended to read:
130 163.3180 Concurrency.—
131 (5)
132 (j)1. If a county and municipality charge the developer of
133 a new development or redevelopment a fee for transportation
134 capacity impacts, the county and municipality must create and
135 execute an interlocal agreement to coordinate the mitigation of
136 their respective transportation capacity impacts.
137 2. The interlocal agreement must, at a minimum:
138 a. Ensure that any new development or redevelopment is not
139 charged twice for the same transportation capacity impacts.
140 b. Establish a plan-based methodology for determining the
141 legally permissible fee to be charged to a new development or
142 redevelopment.
143 c. Require the county or municipality issuing the building
144 permit to collect the fee, unless agreed to otherwise.
145 d. Provide a method for the proportionate distribution of
146 the revenue collected by the county or municipality to address
147 the transportation capacity impacts of a new development or
148 redevelopment, or provide a method of assigning responsibility
149 for the mitigation of the transportation capacity impacts
150 belonging to the county and the municipality.
151
e. Use a plan-based methodology in complying with the
152
requirements of s. 163.3177(6)(h).
153 3. By October 1, 2025, if an interlocal agreement is not
154 executed pursuant to this paragraph:
155 a. The fee charged to a new development or redevelopment
156 shall be based on the transportation capacity impacts
157 apportioned to the county and municipality as identified in the
158 developer’s traffic impact study or the mobility plan adopted by
159 the county or municipality.
160 b. The developer shall receive a 10 percent reduction in
161 the total fee calculated pursuant to sub-subparagraph a.
162 c. The county or municipality issuing the building permit
163 must collect the fee charged pursuant to sub-subparagraphs a.
164 and b. and distribute the proceeds of such fee to the county and
165 municipality within 60 days after the developer’s payment.
166 4. This paragraph does not apply to:
167 a. A county as defined in s. 125.011(1).
168 b. A county or municipality that has entered into, or
169 otherwise updated, an existing interlocal agreement, as of
170 October 1, 2024, to coordinate the mitigation of transportation
171 impacts. However, if such existing interlocal agreement is
172 terminated, the affected county and municipality that have
173 entered into the agreement
are
shall be
subject to the
88174 requirements of this paragraph
unless the county and
89
municipality mutually agree to extend the existing interlocal
90
agreement before the expiration of the agreement
.
91 Section 3. Present paragraphs (a) and (b) of subsection (3)
92 of section 163.31801, Florida Statutes, are redesignated as
93 paragraphs (b) and (c), respectively, a new paragraph (a) is
94 added to that subsection, and paragraph (g) of subsection (6)
95 and subsection (9) of that section are amended, to read:
96 163.31801 Impact fees; short title; intent; minimum
97 requirements; audits; challenges.—
98 (3) For purposes of this section, the term:
99
An interlocal agreement entered
175
into before October 1, 2024, may not extend beyond October 1,
176
2031
unless the county and municipality mutually agree to extend
177
the existing interlocal agreement before the expiration of the
178
agreement
.
179 Section 4. Present paragraphs (a) and (b) of subsection (3)
180 of section 163.31801, Florida Statutes, are redesignated as
181 paragraphs (b) and (c), respectively, a new paragraph (a) is
182 added to that subsection, and paragraph (g) of subsection (6)
183 and subsection (9) of that section are amended, to read:
184 163.31801 Impact fees; short title; intent; minimum
185 requirements; audits; challenges.—
186 (3) For purposes of this section, the term:
187
(a)
“Extraordinary circumstances” means m
easurable effects
100
188
of development
which
will require mitigation by the affected
101
189
local government
, school district, or special district
and which
190
exceed the total of the current adopted impact fee amount
102
adopted impact fee amount
and
191
any increase as provided in paragraphs (6)(c), (d),
103
paragraphs (6)(c), (d),
and
(e) in
192
(e) in less than
4
years.
104193 (6) A local government, school district, or special
105194 district may increase an impact fee only as provided in this
106195 subsection.
107196 (g)1. A local government, school district, or special
108197 district may increase an impact fee rate beyond the phase-in
109198 limitations established under paragraph (b), paragraph (c),
110199 paragraph (d), or paragraph (e) by establishing the need for
111200 such increase in full compliance with the requirements of
112201 subsection (4), provided the following criteria are met:
113202 a. A demonstrated-need study
using a plan-based methodology
114
203
which justifies
justifying
any increase in excess of those
115204 authorized in paragraph (b), paragraph (c), paragraph (d), or
116205 paragraph (e) has been completed within the 12 months before the
117206 adoption of the impact fee increase and expressly demonstrates
118207 the extraordinary circumstances necessitating the need to exceed
119208 the phase-in limitations.
The capacity standards used to support
209
the existence of such extraordinary circumstances must be
210
specified in the impact fee study adopted under paragraph
211
(4)(a). The
Todemonstrated-need demonstrate such extraordinarystudy
must be accompanied by a
120212
circumstances, at least four of the following conditions must be
declaration stating how and the timeframe during which the
121213
shown to exist, using
localized data
that reflects
differences
122
in area costs and modalit
proposed impact fee
iesincrease
of projects between
any
urban,
123
emerging urban
will be used to construct or
214
purchase the
improvements necessary to increase capacity
.
The
215
local government, school district, or special district
must
use
216
localized data reflecting differences in costs and modality of
217
projects between urban, emerging urban
,
or
and rural area
s
,
as
218
applicable
within the study area
,
to project the
anticipated
219
growth or capacity
impacts
which underlie the extraordinary
220
circumstances necessitating the impact fee increase
.
221 b. The local government jurisdiction has held at least two
222 publicly noticed workshops dedicated to the extraordinary
223 circumstances necessitating the need to exceed the phase-in
224 limitations set forth in paragraph (b), paragraph (c), paragraph
225 (d), or paragraph (e).
226 c. The impact fee increase ordinance is approved by a
227 unanimous vote of the governing body.
228 2. An impact fee increase approved under this paragraph
229 must be implemented in at least two but not more than four equal
230 annual increments beginning with the date on which the impact
231 fee increase ordinance is adopted.
232 3. A local government
, school district, or special district
233 may not
:
124234
(I)
Population growth
with
in the
local government
’s
, school
125
district
’s
, or special district
’s
jurisdiction
in
the
previous
126
5
-
year
period
exceeds the high
population
projections
provided
127
by the
University of Florida’s Bureau of Economic and Business
128
Research
.
129
(II)
The average
number of
building permits issued by the
130
local government
in
the
previous 3-year period
is
less than 10
131
percent of the average number of building permits issued in the
132
previous 10-year period.
133
(III) There is a documented failure to meet transportation
134
level
-
of
-
service
standards or
quality
-
of
-
service
standards
135
within the jurisdiction
which were necessary
to meet
demand in
136
the previous
5
-year
period.
137
(IV)
The local capital construction cost exceeds the
138
previous 5-year average construction cost specified in the
139
National Highway Construction Cost
I
ndex
provided by the United
140
States Department of Transportation’s Federal Highway
141
Administration.
142
(V)
The employment base within the jurisdiction has
143
exceeded the average
labor market employment gains
reported
by
144
the
Department of Commerce
in
the pre
vious
5
-year period
.
145
(VI)
The
average daily
vehicle miles traveled
in the
146
jurisdiction
in the past
5
years has exceeded the Florida
147
Vehicle Miles Traveled index average
.
148
(VII)
The
cost per mile
estimates for construction
projects
149
are at least 10 percent greater than the average cost per mile
150
provided by the Department of Transportation as a model for
151
similar construction projects in the previous 5-year period.
152 b. The local government jurisdiction has held at least two
153 publicly noticed workshops dedicated to the extraordinary
154 circumstances necessitating the need to exceed the phase-in
155 limitations set forth in paragraph (b), paragraph (c), paragraph
156 (d), or paragraph (e).
157 c. The impact fee increase ordinance is approved by a
two
158
thirds
unanimous
vote of the governing body.
159 2. An impact fee increase approved under this paragraph
160 must be implemented in at least two but not more than four equal
161 annual increments beginning with the date on which the impact
162 fee increase ordinance is adopted.
163 3. A local government may not
:
164
a.
Increase an impact fee rate beyond the phase-in
165235 limitations under this paragraph if the local government has not
, school
236
district, or special district
has not increased the impact fee
166237 increased the impact fee within the past 5 years. Any year in which the local government
167 which the local government is prohibited from increasing an
,
238
school district, or special district
is prohibited from
168239 increasing an impact fee because the jurisdiction is in a hurricane disaster
169240 hurricane disaster area is not included in the 5-year period.
170
241
b.
3 unchanged paragraphs
Use data
that is
older than 4 years to
demonstrate
171
242
extraordinary circumstances except as specifically provided in.
172
sub-subparagraph 1.a.
173
243
c. Include in the impact fee increase any deduction
174
244
authorized by a previous or existing impact fee.
175
245
4d. AI
local government or school district
may not i
ncrease
176
ncrease an impact fee rate beyond the phase-in limitations under this
177
246
limitations under this paragraph by more than 100 percent in a 4-year period.
247
divided equally over
a 4-year period.
178248 (9) In any action challenging an impact fee or the
249 government’s failure to provide required dollar-for-dollar
250 credits for the payment of impact fees as provided in s.
251 163.3180(6)(h)2.b.
:
179
,
252
(a)
AnThe impactgovernment fee orhas the government’sburden failureof toproving provideby a
180 required dollar-for-dollar credits for the payment of impact
181 fees as provided in s. 163.3180(6)(h)2.b., the government has
182253 the burden of proving by a preponderance of the evidence that the imposition or amount of
183254 the imposition or amount of the fee or credit meets the requirements of state legal
184255 requirements of state legal precedent and this section. The court may not use a deferential
185256 court may not use a deferential standard for the benefit of the government.
186 government.
187
If the court
257
determines that the petitioner made an overpayment due to an
258
improperly assessed impact fee, the petitioner is entitled to a
259
refund in the amount of the overpayment with interest, with such
260
interest amount determined by the court.
The local government,
261
school district, or special district
that assessed the impact
262
fee
must issue the refund within 90 days after the judgment
263
becomes final.
264
(b)
A prevailing petitioner who is a resident of or an
265
owner of a business located within the jurisdiction of the local
266
Agovernment, localschool governmentdistrict, or special district impact fee
188
that imposed
267
imposedthe impact fee in violation of this section, a prevailing petitioner
189
who is a resident of or an owner of a business located within
190
the jurisdiction of the local government or special district, as
191
is entitled to
268
reasonable attorney fees and costs
. Such petitioner is further
269
applicable, is entitled to reasonable attorney fees and costs. in any subsequent
270
action necessary to collect a refund ordered by the court for
271
any impact fee overpayment.
192272 Section 45. Paragraph (d) of subsection (2) of section
193273 212.055, Florida Statutes, is amended to read:
194274 212.055 Discretionary sales surtaxes; legislative intent;
195275 authorization and use of proceeds.—It is the legislative intent
196276 that any authorization for imposition of a discretionary sales
197277 surtax shall be published in the Florida Statutes as a
198278 subsection of this section, irrespective of the duration of the
199279 levy. Each enactment shall specify the types of counties
200280 authorized to levy; the rate or rates which may be imposed; the
201281 maximum length of time the surtax may be imposed, if any; the
202282 procedure which must be followed to secure voter approval, if
203283 required; the purpose for which the proceeds may be expended;
204284 and such other requirements as the Legislature may provide.
205285 Taxable transactions and administrative procedures shall be as
206286 provided in s. 212.054.
207287 (2) LOCAL GOVERNMENT INFRASTRUCTURE SURTAX.—
208288 (d) The proceeds of the surtax authorized by this
209289 subsection and any accrued interest shall be expended by the
210290 school district, within the county and municipalities within the
211291 county, or, in the case of a negotiated joint county agreement,
212292 within another county, to finance, plan, and construct
213293 infrastructure; to acquire any interest in land for public
214294 recreation, conservation, or protection of natural resources or
215295 to prevent or satisfy private property rights claims resulting
216296 from limitations imposed by the designation of an area of
217297 critical state concern; to provide loans, grants, or rebates to
218298 residential or commercial property owners who make energy
219299 efficiency improvements to their residential or commercial
220300 property, if a local government ordinance authorizing such use
221301 is approved by referendum; or to finance the closure of county
222302 owned or municipally owned solid waste landfills that have been
223303 closed or are required to be closed by order of the Department
224304 of Environmental Protection. Any use of the proceeds or interest
225305 for purposes of landfill closure before July 1, 1993, is
226306 ratified. The proceeds and any interest may not be used for the
227307 operational expenses of infrastructure, except that a county
228308 that has a population of fewer than 75,000 and that is required
229309 to close a landfill may use the proceeds or interest for long
230310 term maintenance costs associated with landfill closure.
231311 Counties, as defined in s. 125.011, and charter counties may, in
232312 addition, use the proceeds or interest to retire or service
233313 indebtedness incurred for bonds issued before July 1, 1987, for
234314 infrastructure purposes, and for bonds subsequently issued to
235315 refund such bonds. Any use of the proceeds or interest for
236316 purposes of retiring or servicing indebtedness incurred for
237317 refunding bonds before July 1, 1999, is ratified.
238318 1. For the purposes of this paragraph, the term
239319 “infrastructure” means:
240320 a. Any fixed capital expenditure or fixed capital outlay
241321 associated with the construction, reconstruction, or improvement
242322 of public facilities that have a life expectancy of 5 or more
243323 years, any related land acquisition, land improvement, design,
244324 and engineering costs, and all other professional and related
245325 costs required to bring the public facilities into service. For
246326 purposes of this sub-subparagraph, the term “public facilities”
247327 means facilities as defined in
s. 163.3164(42)
s. 163.3164(41)
,
248328 s. 163.3221(13), or s. 189.012(5), and includes facilities that
249329 are necessary to carry out governmental purposes, including, but
250330 not limited to, fire stations, general governmental office
251331 buildings, and animal shelters, regardless of whether the
252332 facilities are owned by the local taxing authority or another
253333 governmental entity.
254334 b. A fire department vehicle, an emergency medical service
255335 vehicle, a sheriff’s office vehicle, a police department
256336 vehicle, or any other vehicle, and the equipment necessary to
257337 outfit the vehicle for its official use or equipment that has a
258338 life expectancy of at least 5 years.
259339 c. Any expenditure for the construction, lease, or
260340 maintenance of, or provision of utilities or security for,
261341 facilities, as defined in s. 29.008.
262342 d. Any fixed capital expenditure or fixed capital outlay
263343 associated with the improvement of private facilities that have
264344 a life expectancy of 5 or more years and that the owner agrees
265345 to make available for use on a temporary basis as needed by a
266346 local government as a public emergency shelter or a staging area
267347 for emergency response equipment during an emergency officially
268348 declared by the state or by the local government under s.
269349 252.38. Such improvements are limited to those necessary to
270350 comply with current standards for public emergency evacuation
271351 shelters. The owner must enter into a written contract with the
272352 local government providing the improvement funding to make the
273353 private facility available to the public for purposes of
274354 emergency shelter at no cost to the local government for a
275355 minimum of 10 years after completion of the improvement, with
276356 the provision that the obligation will transfer to any
277357 subsequent owner until the end of the minimum period.
278358 e. Any land acquisition expenditure for a residential
279359 housing project in which at least 30 percent of the units are
280360 affordable to individuals or families whose total annual
281361 household income does not exceed 120 percent of the area median
282362 income adjusted for household size, if the land is owned by a
283363 local government or by a special district that enters into a
284364 written agreement with the local government to provide such
285365 housing. The local government or special district may enter into
286366 a ground lease with a public or private person or entity for
287367 nominal or other consideration for the construction of the
288368 residential housing project on land acquired pursuant to this
289369 sub-subparagraph.
290370 f. Instructional technology used solely in a school
291371 district’s classrooms. As used in this sub-subparagraph, the
292372 term “instructional technology” means an interactive device that
293373 assists a teacher in instructing a class or a group of students
294374 and includes the necessary hardware and software to operate the
295375 interactive device. The term also includes support systems in
296376 which an interactive device may mount and is not required to be
297377 affixed to the facilities.
298378 2. For the purposes of this paragraph, the term “energy
299379 efficiency improvement” means any energy conservation and
300380 efficiency improvement that reduces consumption through
301381 conservation or a more efficient use of electricity, natural
302382 gas, propane, or other forms of energy on the property,
303383 including, but not limited to, air sealing; installation of
304384 insulation; installation of energy-efficient heating, cooling,
305385 or ventilation systems; installation of solar panels; building
306386 modifications to increase the use of daylight or shade;
307387 replacement of windows; installation of energy controls or
308388 energy recovery systems; installation of electric vehicle
309389 charging equipment; installation of systems for natural gas fuel
310390 as defined in s. 206.9951; and installation of efficient
311391 lighting equipment.
312392 3. Notwithstanding any other provision of this subsection,
313393 a local government infrastructure surtax imposed or extended
314394 after July 1, 1998, may allocate up to 15 percent of the surtax
315395 proceeds for deposit into a trust fund within the county’s
316396 accounts created for the purpose of funding economic development
317397 projects having a general public purpose of improving local
318398 economies, including the funding of operational costs and
319399 incentives related to economic development. The ballot statement
320400 must indicate the intention to make an allocation under the
321401 authority of this subparagraph.
322402 4. Surtax revenues that are shared with eligible charter
323403 schools pursuant to paragraph (c) shall be allocated among such
324404 schools based on each school’s proportionate share of total
325405 school district capital outlay full-time equivalent enrollment
326406 as adopted by the education estimating conference established in
327407 s. 216.136. Surtax revenues must be expended by the charter
328408 school in a manner consistent with the allowable uses provided
329409 in s. 1013.62(4). All revenues and expenditures shall be
330410 accounted for in a charter school’s monthly or quarterly
331411 financial statement pursuant to s. 1002.33(9). If a school’s
332412 charter is not renewed or is terminated and the school is
333413 dissolved under the provisions of law under which the school was
334414 organized, any unencumbered funds received under this paragraph
335415 shall revert to the sponsor.
336416 Section 56. This act shall take effect July 1, 2026.