SB 2565Tennessee
Utilities, Utility Districts - As introduced, requires each public and private electric utility and electric project developer, owner, or operator to conduct a technical assessment of certain electrical transformers to determine vulnerability to geomagnetically induced current; requires such entities to file a report on the assessment with the general assembly, governor, board of utility regulation, and the public utilities commission. - Amends TCA Title 4; Title 7 and Title 65.
In committee
Mar 10, 2026: Deferred to Summer Study