OFFERED FOR CONSIDERATION
2/11/2026
2026 SESSION
INTRODUCED
26101357D
HBHOUSE BILL NO. 154
SUBCOMMITTEE
1. Line 14, introduced, after 58.1-3506.
insert
"Data center" shall not include facilities owned and operated by a telecommunications provider or Title VI cable operator, or facilities that primarily support telecommunications or Title VI cable network operations.
SUBCOMMITTEE
2. Line 15, introduced
strike
all of lines 15 through 21
SUBCOMMITTEE
3. Line 22, introduced, after that
strike
operates an emergency generation unit
insert
has been issued an air permit by the Department
SUBCOMMITTEE
4. Line 23, introduced, after website
strike
the remainder of line 23 and through operation on line 24
insert
(i) for operations known at least 24 hours in advance, the start and stop time when any permitted engine will be in operation 24 hours in advance of such event and (ii) for operations known in fewer than 24 hours, the start and stop times when any permitted engine has been in operation within 24 hours of such event
Offered January 14, 2026
Prefiled January 6, 2026
A BILL to amend the Code of Virginia by adding a section numbered 10.1-1308.2, relating to Department of Environmental Quality; data centers; use of emergency generation unit; disclosure requirements.
—————
Patron—Thomas
—————
Referred to Committee on Agriculture, Chesapeake and Natural Resources
—————
Be it enacted by the General Assembly of Virginia:
1. That the Code of Virginia is amended by adding a section numbered 10.1-1308.2 as follows:
§ 10.1-1308.2. Data centers; use of emergency generation unit ; disclosure requirements .
A. As used in this section:
"Data center" means the same as that term is defined in § 58.1-3506.
" Emergency" means a condition that arises from sudden and reasonably unforeseeable events where the primary energy or power source is disrupted or disconnected due to conditions beyond the control of an owner of such energy or power source , including a failure of the electrical grid , an onsite disaster or equipment failure, and public service emergencies such as flood, fire, natural disaster, or severe weather conditions.
"Emergency generation unit " means a stationary internal combustion engine that operates only during an emergency, required maintenance, or operability and emissions testing .
B. The Department shall require each data center that operates an emergency generation unit to report on a publicly accessible website within 24 hours the time s when such emergency generation u nit has been or will be in operation.