Relating to certain proceedings by the Public Utility Commission of Texas and regulatory authorities regarding water and sewer utilities.

Introduced

Underlined text would be added to current law. Struck-through text would be removed.

  90R4275 EMS-D
 
  By: Perry S.B. No. 354
 
 
  A BILL TO BE ENTITLED
  AN ACT
  relating to certain proceedings by the Public Utility Commission of
  Texas and regulatory authorities regarding water and sewer
  utilities.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 13.183, Water Code, is amended by adding
  Subsections (c-5) and (c-6) to read as follows:
         (c-5)  If the utility commission determines that an
  application for a system improvement charge under Subsection (c) is
  incomplete after the 30th day after the date the application is
  filed with the utility commission, the utility commission shall
  return the application to the applicant for revision.  A revised
  application submitted to the utility commission after a finding
  that the original application is administratively incomplete is
  considered a new application.
         (c-6)  If the utility commission does not enter a final order
  on a request for a system improvement charge under Subsection (c)
  during the period required by that subsection, the request is
  considered approved.
         SECTION 2.  Section 13.185(d), Water Code, is amended to
  read as follows:
         (d)  Net income is the total revenues of the utility less all
  reasonable and necessary expenses as determined by the regulatory
  authority.  The regulatory authority shall:
               (1)  base a utility's expenses on test year
  information, as determined by utility commission rules; [and]
               (2)  determine expenses and revenues in a manner
  consistent with Subsections (e) through (h); and
               (3)  presume that expenses related to the compensation
  and benefits provided by a utility to the utility's employees,
  including base salaries, wages, incentive compensation, and
  non-salary benefits, are reasonable and necessary if the
  compensation and benefits are consistent with market studies issued
  not earlier than three years before the initiation of the rate
  proceeding during which the regulatory authority is determining
  those expenses [of this section].
         SECTION 3.  Sections 13.187(d), (d-1), (e), (f), and (i),
  Water Code, are amended to read as follows:
         (d)  Not later than the 30th day after the date the
  application or statement of intent is filed, the regulatory
  authority shall determine whether [Except as provided by
  Subsections (d-1) and (e), if] the application or the statement of
  intent is [not] substantially complete and complies [or does not
  comply] with the regulatory authority's rules.  If the regulatory
  authority determines that the application or statement of intent is
  deficient, the regulatory authority may reject the application or,
  in addition to the suspension periods under Subsections (d-1) and
  (e), suspend [, it may be rejected and] the effective date of the
  rate change for not more than 30 days to allow [may be suspended
  until] a properly completed application [is accepted by the
  regulatory authority] and a proper statement of intent to be
  provided [is provided].  The utility commission may also suspend
  the effective date of any rate change if the utility does not have a
  certificate of public convenience and necessity or a completed
  application for a certificate or to transfer a certificate pending
  before the utility commission or if the utility is delinquent in
  paying the assessment and any applicable penalties or interest
  required by Section 5.701(n).
         (d-1)  After written notice to the utility, a local
  regulatory authority may suspend the effective date of a rate
  change for not more than 90 days from the proposed effective date.  
  If the local regulatory authority does not make a final
  determination on the proposed rate before the expiration of the
  suspension period, the proposed rate shall be considered approved
  and is not subject to further processing or revision by the local
  regulatory authority.  This approval is subject to the authority of
  the local regulatory authority thereafter to continue a hearing in
  progress.
         (e)  After written notice to the utility, the utility
  commission may suspend the effective date of a rate change for not
  more than 150 days from the proposed effective date.  If the utility
  commission does not make a final determination on the proposed rate
  before the expiration of the suspension period, the proposed rate
  shall be considered approved and is not subject to further
  processing or revision by the utility commission.  This approval is
  subject to the authority of the utility commission thereafter to
  continue a hearing in progress.
         (f)  The regulatory authority shall, not later than the 60th 
  [30th] day after the effective date of the change, begin a hearing
  to determine the propriety of the change.  If the regulatory
  authority is the utility commission, the utility commission may
  refer the matter to the State Office of Administrative Hearings as
  provided by utility commission rules.  If the utility commission
  refers the matter to the State Office of Administrative Hearings,
  the State Office of Administrative Hearings shall begin a hearing
  to determine the propriety of the change not later than the 60th day
  after the effective date of the change.
         (i)  A utility may put a changed rate into effect throughout
  the area in which the utility sought to change its rates, including
  an area over which the utility commission is exercising appellate
  or original jurisdiction, during a suspension period that has been
  extended under Subsection (e-1) by filing a bond with the utility
  commission [if the suspension period has been extended under
  Subsection (e-1) and the utility commission fails to make a final
  determination before the 151st day after the date the rate change
  would otherwise be effective].
         SECTION 4.  Section 13.301, Water Code, is amended by
  amending Subsections (e) and (g) and adding Subsection (g-1) to
  read as follows:
         (e)  Before the expiration of the 120-day notification
  period, the utility commission shall notify all known parties to
  the transaction and the Office of Public Utility Counsel whether
  the utility commission will hold a public hearing to determine if
  the transaction will serve the public interest.  The utility
  commission may hold a hearing only if:
               (1)  the application filed with the utility commission
  or the public notice was improper;
               (2)  the person purchasing or acquiring the water or
  sewer system has not demonstrated adequate financial, managerial,
  and technical capability for providing continuous and adequate
  service to the service area being acquired and to any areas
  currently certificated to the person;
               (3)  the person or an affiliated interest of the person
  purchasing or acquiring the water or sewer system has a history of:
                     (A)  noncompliance with the requirements of the
  utility commission, the commission, or the Department of State
  Health Services; or
                     (B)  continuing mismanagement or misuse of
  revenues as a utility service provider;
               (4)  the person purchasing or acquiring the water or
  sewer system cannot demonstrate the financial ability to provide
  the necessary capital investment to ensure the provision of
  continuous and adequate service to the customers of the water or
  sewer system; or
               (5)  there are concerns that the transaction may not
  serve the public interest, after the application of the
  considerations provided by Section 13.246(c) for determining
  whether to grant a certificate of convenience and necessity.
         (g)  Subject to Subsection (g-1), if [If] the utility
  commission decides to hold a hearing under Subsection (e) or if the
  utility or water supply or sewer service corporation fails to make
  the application as required or to provide public notice, the sale,
  acquisition, lease, or rental may not be completed unless the
  utility commission determines that the proposed transaction serves
  the public interest.
         (g-1)  If the utility commission decides to hold a public
  hearing under Subsection (e), the utility commission shall issue a
  final order not later than the 150th day after the date the utility
  or water supply or sewer service corporation files the written
  application with the utility commission under Subsection (a).  If a
  final determination is not issued by the 150th day after the date a
  utility or a water supply or sewer service corporation files the
  written application, the transaction is considered approved and may
  be completed.
         SECTION 5.  Section 13.3011, Water Code, is amended by
  adding Subsection (c) to read as follows:
         (c)  In establishing initial rates, the regulatory authority
  shall presume that rates meeting the requirements of Subsection (a)
  are just, reasonable, and in the public interest.
         SECTION 6.  The changes in law made by this Act apply only to
  a rate proceeding under Chapter 13, Water Code, that begins on or
  after the effective date of this Act. A rate proceeding that begins
  before the effective date of this Act is governed by the law in
  effect on the date the rate proceeding began, and the former law is
  continued in effect for that purpose.
         SECTION 7.  This Act takes effect September 1, 2027.