Introduced
Underlined text would be added to current law. Struck-through text would be removed.
| 90R1342 CS-F | ||
| By: Hall | S.B. No. 191 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to the interconnection of a facility in the ERCOT power | |
| region to certain other facilities. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Section 37.051, Utilities Code, is amended by | |
| amending Subsections (c), (c-1), (c-2), and (c-3) and adding | |
| Subsection (c-4) to read as follows: | |
| (c) Notwithstanding any other provision of this chapter | |
| except Subsection (c-1)[ |
|
| cooperative is not required to obtain a certificate of public | |
| convenience and necessity for the construction, installation, | |
| operation, or extension of any generating facilities or necessary | |
| interconnection facilities. | |
| (c-1) In this subsection, "facility" means a facility that | |
| consumes, generates, transmits, or distributes electricity. | |
| Notwithstanding any other provision of this title except Section | |
| 11.009, and except as provided by Subsection (c-3) [ |
|
| electric cooperative, [ |
|
| [ |
|
| interconnect a facility in [ |
|
| located wholly or partly outside of this state or to a facility that | |
| is connected directly or indirectly with a facility located wholly | |
| or partly outside of this state, [ |
|
| (1) the proposed interconnection will not subject the | |
| ERCOT power region to additional federal control or jurisdiction; | |
| (2) the commission first determines that the proposed | |
| interconnection is in the public interest after considering: | |
| (A) the technical attributes of the proposed | |
| interconnection; | |
| (B) the expected costs to the public to install, | |
| operate, and maintain the interconnection; | |
| (C) the results of relevant criteria adopted by | |
| the commission under Section 37.056(d); | |
| (D) the results of a reliability assessment | |
| conducted by the independent organization certified under Section | |
| 39.151 for the ERCOT power region; and | |
| (E) any other information the commission | |
| considers appropriate; | |
| (3) the cooperative, utility, or person applies for a | |
| public interest determination from the commission under | |
| Subdivision (2) [ |
|
| cooperative, utility, or person seeks any order from the Federal | |
| Energy Regulatory Commission related to the proposed | |
| interconnection; and | |
| (4) after the cooperative, utility, or person obtains | |
| any order from the Federal Energy Regulatory Commission related to | |
| the proposed interconnection, the commission grants a certificate | |
| stating that public convenience or necessity requires or will | |
| require the interconnection. | |
| (c-2) The commission shall apply Section 37.056 in | |
| considering an application under Subsection (c-1) [ |
|
| implement Subsection (c-1) [ |
|
| [ |
|
| December 31, 2014. | |
| (c-3) [ |
|
| after the date the application is filed, shall approve an | |
| application filed under Subsection (c-1) for a facility that is to | |
| be constructed under an interconnection agreement appended to an | |
| offer of settlement approved in a final order of the Federal Energy | |
| Regulatory Commission that was issued in Docket No. TX11-01-001 on | |
| or before December 31, 2014, directing physical connection between | |
| the ERCOT and SERC regions under Sections 210, 211, and 212 of the | |
| Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In | |
| approving the application, the commission may prescribe reasonable | |
| conditions to protect the public interest that are consistent with | |
| the final order of the Federal Energy Regulatory Commission. | |
| (c-4) [ |
|
| (c-3) is intended to restrict the authority of the commission or the | |
| independent organization certified under Section 39.151 for the | |
| ERCOT power region to adopt rules or protocols of general | |
| applicability. | |
| SECTION 2. The changes in law made by this Act in Section | |
| 37.051, Utilities Code, apply only to an interconnection made on or | |
| after the effective date of this Act. An interconnection made | |
| before the effective date of this Act is governed by the law in | |
| effect when the interconnection was made, and the former law is | |
| continued in effect for that purpose. | |
| SECTION 3. This Act takes effect immediately if it receives | |
| a vote of two-thirds of all the members elected to each house, as | |
| provided by Section 39, Article III, Texas Constitution. If this | |
| Act does not receive the vote necessary for immediate effect, this | |
| Act takes effect September 1, 2027. |