| By: Perez of El Paso | H.B. No. 730 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to the interconnection of large load customers and the | |
| recovery of costs of generation facilities serving large load | |
| customers by electric utilities operating outside of the ERCOT | |
| power region. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Section 36.053, Utilities Code, is amended by | |
| adding Subsections (e), (f), and (g) to read as follows: | |
| (e) In this subsection and Subsections (f) and (g): | |
| (1) "Dedicated large load generation facility" means a | |
| generation facility, or a portion of a generation facility, that an | |
| electric utility operating solely outside of the ERCOT power region | |
| constructs, acquires, or contracts for primarily to serve one large | |
| load customer. | |
| (2) "Large load customer" means a retail customer | |
| whose total load at a single site exceeds, or is projected to | |
| exceed, 75 megawatts. The term includes an affiliate or successor | |
| in interest of the customer. | |
| (f) Notwithstanding Section 39.410 or any other law, the | |
| commission may not find that a dedicated large load generation | |
| facility is used by and useful to the electric utility in providing | |
| service, and the utility may not include the original cost of the | |
| facility in invested capital or otherwise recover the cost of the | |
| facility from customers other than the large load customer, unless | |
| the commission, in a proceeding for which notice is provided to each | |
| affected customer class and that is concluded before the cost is | |
| included in rates, finds that: | |
| (1) the facility provides a net benefit to the | |
| utility's customers other than the large load customer; and | |
| (2) the costs of the facility are allocated among | |
| customer classes in accordance with cost-causation principles and | |
| in a manner that does not cause the rates of the residential or | |
| small commercial customer classes to exceed the rates those classes | |
| would pay if the facility had not been constructed, acquired, or | |
| contracted for. | |
| (g) The commission may make the findings described by | |
| Subsection (f) in a proceeding under Chapter 37 for a certificate of | |
| convenience and necessity for the facility or in a separate | |
| proceeding. Subsection (f) applies regardless of whether the large | |
| load customer has agreed to pay all or part of the costs of the | |
| facility for a limited period. | |
| SECTION 2. Section 37.056, Utilities Code, is amended by | |
| adding Subsection (j) to read as follows: | |
| (j) The commission may not grant a certificate for a | |
| dedicated large load generation facility, as defined by Section | |
| 36.053(e), unless the commission: | |
| (1) makes the findings described by Section 36.053(f); | |
| or | |
| (2) conditions the certificate on the electric | |
| utility's agreement that the costs of the facility will not be | |
| recovered from customers other than the large load customer unless | |
| the commission later makes those findings in a proceeding described | |
| by Section 36.053(f). | |
| SECTION 3. Subchapter I, Chapter 39, Utilities Code, is | |
| amended by adding Section 39.411 to read as follows: | |
| Sec. 39.411. INTERCONNECTION OF LARGE LOADS. (a) In this | |
| section, "large load customer" includes an entity requesting an | |
| interconnection that exceeds the demand threshold established | |
| under Subsection (c) and a successor in interest to such an entity. | |
| (b) The commission by rule shall establish standards for | |
| interconnecting large load customers to an electric utility subject | |
| to this subchapter in a manner designed to support business | |
| development in this state while minimizing the potential for | |
| stranded infrastructure costs, protecting the utility's other | |
| customers from costs caused by large load customers, and | |
| maintaining system reliability. | |
| (c) The standards apply only to a customer requesting a new | |
| or expanded interconnection where the total load at a single site | |
| would exceed 75 megawatts, unless the commission determines that a | |
| lower threshold is necessary to accomplish the purposes described | |
| by Subsection (b). | |
| (d) The standards must: | |
| (1) require each large load customer to disclose to | |
| the electric utility whether the customer is pursuing a | |
| substantially similar request for electric service in this state or | |
| another state the approval of which would result in the customer | |
| materially changing, delaying, or withdrawing the interconnection | |
| request; | |
| (2) set a flat study fee of at least $100,000 to be | |
| paid to the electric utility for initial transmission and | |
| generation screening studies, with any unused portion credited | |
| toward the customer's financial obligations for interconnection at | |
| the same site; | |
| (3) include a method for a large load customer to | |
| demonstrate site control for the proposed load location through an | |
| ownership interest, lease, or another legal interest acceptable to | |
| the commission; | |
| (4) include uniform financial commitment requirements | |
| for the development of transmission and generation infrastructure | |
| needed to serve a large load customer, which may be satisfied by | |
| security provided on a dollar per megawatt basis as set by the | |
| commission, contribution in aid of construction, advance payment | |
| for significant equipment or services, or another form of financial | |
| commitment acceptable to the commission; and | |
| (5) provide that security posted under Subdivision (4) | |
| is refunded, in whole or in part, after application to any | |
| outstanding amounts owed, as the customer meets load ramp | |
| milestones and sustains operations for a period prescribed by the | |
| commission, if the customer withdraws all or part of its request, or | |
| if capacity subject to the commitment is reallocated to other | |
| customers. | |
| (e) Information a large load customer submits under | |
| Subsection (d)(1) that is competitively sensitive is confidential | |
| and not subject to disclosure under Chapter 552, Government Code, | |
| except to the commission. | |
| (f) Section 39.410 does not limit the application of the | |
| standards adopted under this section to a request for | |
| interconnection made on or after the effective date of the rules | |
| adopted under this section. | |
| SECTION 4. (a) Section 36.053, Utilities Code, as amended | |
| by this Act, applies to a proceeding to change rates that is | |
| initiated on or after the effective date of this Act. | |
| (b) Section 37.056(j), Utilities Code, as added by this Act, | |
| applies only to an application for a certificate of convenience and | |
| necessity filed on or after the effective date of this Act. | |
| (c) The Public Utility Commission of Texas shall adopt rules | |
| under Section 39.411, Utilities Code, as added by this Act, not | |
| later than June 1, 2028. | |
| SECTION 5. This Act takes effect September 1, 2027. |