HB 125590th Legislature (2027)

Relating to registration and community outreach requirements for large data centers.

Introduced

Underlined text would be added to current law. Struck-through text would be removed.

  90R4632 ANG-D
 
  By: Lalani H.B. No. 1255
 
 
  A BILL TO BE ENTITLED
  AN ACT
  relating to registration and community outreach requirements for
  large data centers.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  The Utilities Code is amended by adding Title 7
  to read as follows:
  TITLE 7. DATA CENTERS
  CHAPTER 401. DATA CENTER REGISTRATION AND COMMUNITY ENGAGEMENT
  NOTICE REQUIREMENTS
  SUBCHAPTER A. GENERAL PROVISIONS
         Sec. 401.001.  DEFINITIONS. In this title:
               (1)  "Commission" means the Public Utility Commission
  of Texas.
               (2)  "Developer" means a person who owns, develops, or
  proposes to develop a large data center.
               (3)  "Electric cooperative" has the meaning assigned by
  Section 11.003.
               (4)  "Electric utility" has the meaning assigned by
  Section 31.002.
               (5)  "Large data center" means a facility or group of
  facilities on a single parcel or contiguous parcels of land under
  common ownership or control that:
                     (A)  comprises at least 250,000 square feet of
  space; and
                     (B)  is constructed or refurbished primarily to
  house servers and related equipment for the processing, storage, or
  distribution of data.
               (6)  "Municipally owned utility" has the meaning
  assigned by Section 11.003.
  SUBCHAPTER B. REGISTRATION
         Sec. 401.051.  REGISTRATION. (a) The commission by rule
  shall:
               (1)  require a developer to register the site of a large
  data center under this section before construction of the data
  center begins; and
               (2)  establish a method to ensure compliance with this
  section.
         (b)  The rules must require the developer, before beginning
  construction of the large data center, to:
               (1)  notify the community about the construction of the
  large data center as provided by Section 401.101;
               (2)  hold a community meeting as provided by Section
  401.102; and
               (3)  submit an affidavit to the commission in
  accordance with Section 401.104 stating that the developer has
  complied with the requirements of Subchapter C.
  SUBCHAPTER C. COMMUNITY OUTREACH REQUIREMENTS
         Sec. 401.101.  NOTIFICATION REQUIREMENTS. (a) Not later
  than the 60th day before holding a community meeting as required by
  Section 401.102, a developer shall:
               (1)  send written notice of the proposed construction
  of the large data center:
                     (A)  by first-class mail to each owner of real
  property located wholly or partly within three miles of the
  boundary on which the proposed data center will be located, using
  the most recent certified appraisal roll of the appraisal district
  in which the property is located; and
                     (B)  by first-class mail or direct delivery to
  each residential address located within three miles of the boundary
  of the proposed large data center;
               (2)  provide written notice of the proposed
  construction of the large data center to:
                     (A)  the county judge of the county in which the
  proposed large data center will be located;
                     (B)  the county commissioner who represents the
  county precinct in which the proposed large data center will be
  located;
                     (C)  the mayor of the municipality in which the
  proposed large data center will be located, if applicable;
                     (D)  each member of the legislature who represents
  the area in which the proposed large data center will be located;
  and
                     (E)  any other political subdivisions in which the
  proposed large data center will be located;
               (3)  publish notice of the proposed construction of the
  large data center in a newspaper or news publication of general
  circulation in the county in which the proposed large data center
  will be located;
               (4)  post a sign providing notice of the proposed
  construction of the large data center in a conspicuous location at
  the site of the proposed data center in a location that is visible
  from a regularly traveled public road; and
               (5)  post a written notice of the proposed construction
  of and information regarding the proposed large data center,
  including information regarding the community meeting, on a
  publicly available Internet website maintained by or operated on
  behalf of the developer.
         (b)  Notice provided under this section must include:
               (1)  the developer's name and contact information;
               (2)  the location of the proposed large data center;
               (3)  a description in plain language of the proposed
  large data center;
               (4)  the anticipated square footage of the proposed
  large data center;
               (5)  the date, time, and location of the planned
  community meeting required by Section 401.102;
               (6)  a description of the manner in which a person may
  submit questions or written comments to the developer regarding the
  proposed large data center; and
               (7)  the Internet website address at which information
  regarding the proposed large data center and the community meeting
  may be found.
         Sec. 401.102.  COMMUNITY MEETING REQUIRED. (a) A developer
  shall hold at least one public community meeting before beginning
  construction of a proposed large data center.
         (b)  A community meeting held under this section must be held
  in the county in which the proposed large data center will be
  located and at a location reasonably accessible to residents who
  are entitled to notice under Section 401.101. At the meeting, the
  developer shall:
               (1)  describe the proposed large data center; and
               (2)  provide members of the public:
                     (A)  a reasonable opportunity to ask questions
  regarding the proposed large data center; and
                     (B)  an opportunity to:
                           (i)  provide oral comments on the proposed
  large data center to the developer; and
                           (ii)  submit written comments on the
  proposed large data center to the developer.
         (c)  The developer shall accept written comments on the
  proposed large data center beginning on the date notice is provided
  under Section 401.101 and until at least the 10th business day after
  the date of the community meeting held under this section.
         (d)  A developer of a large data center or a representative
  of the developer must attend the community meeting held under this
  section. The developer or the developer's representative must:
               (1)  be knowledgeable regarding the proposed large data
  center; and
               (2)  make a reasonable effort to respond to questions
  relevant to the proposed large data center.
         (e)  The developer shall make an audio or video recording of
  the community meeting held under this section.
         (f)  Not later than the 40th day after the date of the
  community meeting held under this section, the developer shall
  publish on a publicly available Internet website maintained by or
  operated on behalf of the developer:
               (1)  the audio or video recording of the meeting;
               (2)  a copy or a summary of the written comments
  received by the developer; and
               (3)  a written response provided by the developer
  addressing each relevant and material issue raised by an oral or
  written comment.
         (g)  The purpose of a community meeting held under this
  section is to provide information to the public and allow the public
  to provide input to the developer. The community meeting is not a
  governmental meeting subject to the meeting or hearing requirements
  of the Government Code applicable to meetings held by governmental
  entities.
         Sec. 401.103.  COSTS. A developer is responsible for all
  costs required for compliance with this subchapter.
         Sec. 401.104.  AFFIDAVIT OF COMPLIANCE. (a) A developer
  shall submit to the commission a sworn affidavit that the developer
  has complied with the notice and community meeting requirements
  under this subchapter.
         (b)  The commission shall verify that the information in the
  sworn affidavit is correct and share the affidavit with the
  electric cooperative, electric utility, or municipally owned
  utility the developer proposes to receive electric service from at
  the proposed large data center site.
         (c)  An electric cooperative, electric utility, or
  municipally owned utility may not interconnect facilities at a site
  on which a large data center is or will be located before receiving
  a copy of the developer's affidavit from the commission.
  SUBCHAPTER D. ENFORCEMENT
         Sec. 401.152.  ENFORCEMENT. For purposes of this chapter, a
  reference in Chapter 15 to a person includes a developer required to
  register under this chapter. The commission may use any
  enforcement mechanism authorized by Chapter 15 against a developer,
  electric cooperative, electric utility, or municipally owned
  utility that fails to comply with this chapter.
         SECTION 2.  Title 7, Utilities Code, as added by this Act,
  applies only to a large data center the construction of which begins
  on or after the effective date of this Act.
         SECTION 3.  This Act takes effect September 1, 2027.