| 90R4632 ANG-D | ||
| By: Lalani | H.B. No. 1255 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to registration and community outreach requirements for | |
| large data centers. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. The Utilities Code is amended by adding Title 7 | |
| to read as follows: | |
| TITLE 7. DATA CENTERS | |
| CHAPTER 401. DATA CENTER REGISTRATION AND COMMUNITY ENGAGEMENT | |
| NOTICE REQUIREMENTS | |
| SUBCHAPTER A. GENERAL PROVISIONS | |
| Sec. 401.001. DEFINITIONS. In this title: | |
| (1) "Commission" means the Public Utility Commission | |
| of Texas. | |
| (2) "Developer" means a person who owns, develops, or | |
| proposes to develop a large data center. | |
| (3) "Electric cooperative" has the meaning assigned by | |
| Section 11.003. | |
| (4) "Electric utility" has the meaning assigned by | |
| Section 31.002. | |
| (5) "Large data center" means a facility or group of | |
| facilities on a single parcel or contiguous parcels of land under | |
| common ownership or control that: | |
| (A) comprises at least 250,000 square feet of | |
| space; and | |
| (B) is constructed or refurbished primarily to | |
| house servers and related equipment for the processing, storage, or | |
| distribution of data. | |
| (6) "Municipally owned utility" has the meaning | |
| assigned by Section 11.003. | |
| SUBCHAPTER B. REGISTRATION | |
| Sec. 401.051. REGISTRATION. (a) The commission by rule | |
| shall: | |
| (1) require a developer to register the site of a large | |
| data center under this section before construction of the data | |
| center begins; and | |
| (2) establish a method to ensure compliance with this | |
| section. | |
| (b) The rules must require the developer, before beginning | |
| construction of the large data center, to: | |
| (1) notify the community about the construction of the | |
| large data center as provided by Section 401.101; | |
| (2) hold a community meeting as provided by Section | |
| 401.102; and | |
| (3) submit an affidavit to the commission in | |
| accordance with Section 401.104 stating that the developer has | |
| complied with the requirements of Subchapter C. | |
| SUBCHAPTER C. COMMUNITY OUTREACH REQUIREMENTS | |
| Sec. 401.101. NOTIFICATION REQUIREMENTS. (a) Not later | |
| than the 60th day before holding a community meeting as required by | |
| Section 401.102, a developer shall: | |
| (1) send written notice of the proposed construction | |
| of the large data center: | |
| (A) by first-class mail to each owner of real | |
| property located wholly or partly within three miles of the | |
| boundary on which the proposed data center will be located, using | |
| the most recent certified appraisal roll of the appraisal district | |
| in which the property is located; and | |
| (B) by first-class mail or direct delivery to | |
| each residential address located within three miles of the boundary | |
| of the proposed large data center; | |
| (2) provide written notice of the proposed | |
| construction of the large data center to: | |
| (A) the county judge of the county in which the | |
| proposed large data center will be located; | |
| (B) the county commissioner who represents the | |
| county precinct in which the proposed large data center will be | |
| located; | |
| (C) the mayor of the municipality in which the | |
| proposed large data center will be located, if applicable; | |
| (D) each member of the legislature who represents | |
| the area in which the proposed large data center will be located; | |
| and | |
| (E) any other political subdivisions in which the | |
| proposed large data center will be located; | |
| (3) publish notice of the proposed construction of the | |
| large data center in a newspaper or news publication of general | |
| circulation in the county in which the proposed large data center | |
| will be located; | |
| (4) post a sign providing notice of the proposed | |
| construction of the large data center in a conspicuous location at | |
| the site of the proposed data center in a location that is visible | |
| from a regularly traveled public road; and | |
| (5) post a written notice of the proposed construction | |
| of and information regarding the proposed large data center, | |
| including information regarding the community meeting, on a | |
| publicly available Internet website maintained by or operated on | |
| behalf of the developer. | |
| (b) Notice provided under this section must include: | |
| (1) the developer's name and contact information; | |
| (2) the location of the proposed large data center; | |
| (3) a description in plain language of the proposed | |
| large data center; | |
| (4) the anticipated square footage of the proposed | |
| large data center; | |
| (5) the date, time, and location of the planned | |
| community meeting required by Section 401.102; | |
| (6) a description of the manner in which a person may | |
| submit questions or written comments to the developer regarding the | |
| proposed large data center; and | |
| (7) the Internet website address at which information | |
| regarding the proposed large data center and the community meeting | |
| may be found. | |
| Sec. 401.102. COMMUNITY MEETING REQUIRED. (a) A developer | |
| shall hold at least one public community meeting before beginning | |
| construction of a proposed large data center. | |
| (b) A community meeting held under this section must be held | |
| in the county in which the proposed large data center will be | |
| located and at a location reasonably accessible to residents who | |
| are entitled to notice under Section 401.101. At the meeting, the | |
| developer shall: | |
| (1) describe the proposed large data center; and | |
| (2) provide members of the public: | |
| (A) a reasonable opportunity to ask questions | |
| regarding the proposed large data center; and | |
| (B) an opportunity to: | |
| (i) provide oral comments on the proposed | |
| large data center to the developer; and | |
| (ii) submit written comments on the | |
| proposed large data center to the developer. | |
| (c) The developer shall accept written comments on the | |
| proposed large data center beginning on the date notice is provided | |
| under Section 401.101 and until at least the 10th business day after | |
| the date of the community meeting held under this section. | |
| (d) A developer of a large data center or a representative | |
| of the developer must attend the community meeting held under this | |
| section. The developer or the developer's representative must: | |
| (1) be knowledgeable regarding the proposed large data | |
| center; and | |
| (2) make a reasonable effort to respond to questions | |
| relevant to the proposed large data center. | |
| (e) The developer shall make an audio or video recording of | |
| the community meeting held under this section. | |
| (f) Not later than the 40th day after the date of the | |
| community meeting held under this section, the developer shall | |
| publish on a publicly available Internet website maintained by or | |
| operated on behalf of the developer: | |
| (1) the audio or video recording of the meeting; | |
| (2) a copy or a summary of the written comments | |
| received by the developer; and | |
| (3) a written response provided by the developer | |
| addressing each relevant and material issue raised by an oral or | |
| written comment. | |
| (g) The purpose of a community meeting held under this | |
| section is to provide information to the public and allow the public | |
| to provide input to the developer. The community meeting is not a | |
| governmental meeting subject to the meeting or hearing requirements | |
| of the Government Code applicable to meetings held by governmental | |
| entities. | |
| Sec. 401.103. COSTS. A developer is responsible for all | |
| costs required for compliance with this subchapter. | |
| Sec. 401.104. AFFIDAVIT OF COMPLIANCE. (a) A developer | |
| shall submit to the commission a sworn affidavit that the developer | |
| has complied with the notice and community meeting requirements | |
| under this subchapter. | |
| (b) The commission shall verify that the information in the | |
| sworn affidavit is correct and share the affidavit with the | |
| electric cooperative, electric utility, or municipally owned | |
| utility the developer proposes to receive electric service from at | |
| the proposed large data center site. | |
| (c) An electric cooperative, electric utility, or | |
| municipally owned utility may not interconnect facilities at a site | |
| on which a large data center is or will be located before receiving | |
| a copy of the developer's affidavit from the commission. | |
| SUBCHAPTER D. ENFORCEMENT | |
| Sec. 401.152. ENFORCEMENT. For purposes of this chapter, a | |
| reference in Chapter 15 to a person includes a developer required to | |
| register under this chapter. The commission may use any | |
| enforcement mechanism authorized by Chapter 15 against a developer, | |
| electric cooperative, electric utility, or municipally owned | |
| utility that fails to comply with this chapter. | |
| SECTION 2. Title 7, Utilities Code, as added by this Act, | |
| applies only to a large data center the construction of which begins | |
| on or after the effective date of this Act. | |
| SECTION 3. This Act takes effect September 1, 2027. |