Introduced
Underlined text would be added to current law. Struck-through text would be removed.
| By: Hall | S.B. No. 1979 | |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to renewable energy generation facilities; authorizing | |
| fees. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subchapter C, Chapter 15, Utilities Code, is | |
| amended by adding Section 15.053 to read as follows: | |
| Sec. 15.053. COMPLAINT REGARDING RENEWABLE ENERGY | |
| GENERATION FACILITIES. (a) An affected person may complain to the | |
| commission in writing setting forth an act or omission by an owner | |
| or operator of renewable generation in violation or claimed | |
| violation of Subchapter F, Chapter 35. | |
| (b) The commission shall keep for a reasonable period an | |
| information file about each complaint filed with the commission | |
| relating to an owner or operator of battery energy storage. | |
| (c) The commission, at least quarterly and until final | |
| disposition of the written complaint, shall notify the parties to | |
| the complaint of the status of the complaint unless the notice would | |
| jeopardize an undercover investigation. | |
| SECTION 2. Chapter 35, Utilities Code, is amended by adding | |
| Subchapter F to read as follows: | |
| SUBCHAPTER F. RENEWABLE ENERGY GENERATION FACILITY PERMIT | |
| Sec. 35.201. DEFINITIONS; APPLICABILITY. (a) In this | |
| subchapter: | |
| (1) "Battery energy storage facility" includes a | |
| facility or equipment used to support the operation of battery | |
| energy storage, including an underground or aboveground electrical | |
| transmission or communications line, an electric transformer, | |
| telecommunications equipment, a road, a meteorological tower, or a | |
| maintenance yard. | |
| (2) "Battery energy storage facility agreement" means | |
| a lease agreement between a grantee and a landowner that authorizes | |
| the grantee to operate a battery energy storage facility on the | |
| leased property. | |
| (3) "Grantee" means a person who: | |
| (A) leases property from a landowner; and | |
| (B) operates a battery energy storage facility on | |
| the property. | |
| (4) "Permit holder" means a person who holds a permit | |
| issued under this subchapter. | |
| (5) "Person" includes an electric cooperative and a | |
| municipally owned utility. | |
| (6) "Renewable energy generation facility" for | |
| purposes of this chapter means: | |
| (A) a wind power facility as defined by Section | |
| 301.0001; | |
| (B) a solar power facility as defined by Section | |
| 302.0001; | |
| (C) a battery energy storage facility; or | |
| (D) a facility that generates electric energy | |
| using a renewable energy technology, as defined by Section 39.916, | |
| Utilities Code, other than a technology that relies exclusively on | |
| wind or solar energy. | |
| (b) The permit requirements of this subchapter apply to a | |
| renewable energy generation facility regardless of whether the | |
| facility is the subject of a facility agreement entered into under | |
| Chapter 301 or 302 or this subchapter. | |
| (c) This subchapter applies only to a renewable energy | |
| generation facility that is intended to be used to sell energy or | |
| ancillary services at wholesale. | |
| Sec. 35.202. PERMIT REQUIRED. (a) A person may not | |
| interconnect a renewable energy generation facility to a | |
| transmission facility unless the person holds a permit to operate a | |
| renewable energy generation facility issued by the commission under | |
| this subchapter. | |
| (b) The commission by rule shall require each permitted | |
| renewable energy generation facility to be installed only in a | |
| location that: | |
| (1) for a solar power facility, is at least: | |
| (A) 500 feet from any property line, unless the | |
| permit holder has obtained a written waiver from each owner of | |
| property located less than 500 feet from the permitted facility; | |
| and | |
| (B) 500 feet from any habitable structure, unless | |
| the permit holder has obtained a written waiver from each owner of | |
| the habitable structure; | |
| (2) for a wind power facility, is at least twice the | |
| height of the wind turbine, including the blades of the turbine, | |
| from the property line of each property that borders the property on | |
| which the permitted facility is located, unless the permit holder | |
| has obtained a written waiver from each owner of property located in | |
| the applicable area; and | |
| (3) for a battery energy storage facility, is at | |
| least: | |
| (A) 500 feet from any property line, unless the | |
| permit holder has obtained a written waiver from each owner of | |
| property located less than 500 feet from the permitted facility; | |
| and | |
| (B) 500 feet from: | |
| (i) public ways; | |
| (ii) buildings; | |
| (iii) stored combustible materials; | |
| (iv) hazardous materials; | |
| (v) high-piled stock; and | |
| (vi) other exposure hazards not associated | |
| with electrical grid infrastructure. | |
| (c) The commission by rule shall require each permitted | |
| renewable energy generation facility to be installed only in a | |
| location that, in the event of an emergency at the site of the | |
| permitted renewable energy generation facility, will not block the | |
| only access point to a residential area. If an emergency could block | |
| access to a residential area, a different access point to the | |
| facility must be constructed. | |
| (d) A person may apply for a permit under this subchapter by | |
| filing with the commission: | |
| (1) a description of the proposed location of the | |
| renewable energy generation facility; | |
| (2) a description of the type of renewable energy | |
| generation facility; | |
| (3) a statement identifying the fire department, as | |
| defined by Section 419.021, Government Code, volunteer fire | |
| department, fire marshal, or other first responder entity that may | |
| reasonably be expected to be the primary first responder to a fire | |
| at the location of the renewable energy generation facility; | |
| (4) a statement that the person has provided written | |
| notice to the entity identified in Subdivision (3) of the | |
| applicant's intent to install a renewable energy generation | |
| facility; | |
| (5) evidence of insurance coverage sufficient to | |
| insure against losses arising from the operation of the renewable | |
| energy generation facility; and | |
| (6) any other information required by commission rule. | |
| (e) When an application for a permit, or an amendment to a | |
| permit issued under this section, is filed, the commission shall | |
| give notice of the application to the county judge of the county in | |
| which all or a majority of the renewable energy generation facility | |
| is proposed to be located. The county shall publish the notice on | |
| their website in perpetuity and, in accordance with Chapter 2051, | |
| Government Code, in a newspaper for a minimum of three consecutive | |
| days. | |
| (f) The commission may hold one or more public meetings on a | |
| permit application in the county in which the renewable energy | |
| generation facility is proposed to be located. The commission | |
| shall hold a public meeting: | |
| (1) on the request of a member of the legislature who | |
| represents the area in which the renewable energy generation | |
| facility is proposed to be located; or | |
| (2) if the commission determines there is substantial | |
| public interest in the proposed permit. | |
| (g) The commission by order or rule may delegate to the | |
| executive director or another commission employee the authority to | |
| hold a public meeting under this section. | |
| (h) The commission may approve an application for a permit | |
| only if the commission finds that: | |
| (1) issuance of the permit would not violate state or | |
| federal law; and | |
| (2) the location of the proposed renewable energy | |
| generation facility complies with rules adopted under Subsections | |
| (b) and (c). | |
| (i) The commission by rule shall adopt a fee to be imposed on | |
| each permit applicant to cover costs associated with implementing | |
| this section. | |
| (j) For purposes of this subchapter: | |
| (1) a provision of Subchapter B or E, Chapter 14, that | |
| authorizes the commission to regulate a public utility also applies | |
| to a person required to obtain a permit under this section, | |
| including an electric cooperative or a municipally owned utility; | |
| and | |
| (2) a reference in Chapter 15 to a person includes a | |
| person required to obtain a permit under this section, including an | |
| electric cooperative or a municipally owned utility. | |
| Sec. 35.203. FIRE SAFETY STANDARDS FOR BATTERY ENERGY | |
| STORAGE. (a) The commission shall adopt and periodically update | |
| fire safety standards and testing requirements for battery energy | |
| storage operating under a permit issued under this subchapter. The | |
| standards and requirements must be based on: | |
| (1) model code requirements for battery energy storage | |
| established by UL Solutions, such as UL 9540 and UL 9540A | |
| performance criteria; | |
| (2) minimum standards related to the installation, | |
| design, and maintenance of stationary energy storage systems and | |
| electrical equipment established by the National Fire Protection | |
| Association, such as NFPA 70 and NFPA 855; | |
| (3) fire hazard management standards, such as the | |
| International Fire Code and NFPA 1; | |
| (4) explosion prevention and mitigation standards, | |
| such as NFPA 68 and NFPA 69; | |
| (5) fire and explosion prevention standards for | |
| battery energy storage that is integrated with a photovoltaic | |
| energy system, such as NFPA 585; | |
| (6) lithium ion battery safety standards, such as UL | |
| 1642; and | |
| (7) industry best practices for security fencing and | |
| signage near battery energy storage. | |
| (b) Each permit holder that owns or operates permitted | |
| battery energy storage shall ensure that the storage meets the fire | |
| safety standards and testing requirements adopted by the commission | |
| under Subsection (a) at the time of interconnection. | |
| (c) On request by a municipality in which the battery energy | |
| storage is located, or a county in which the battery energy storage | |
| is located if the storage is in an unincorporated area, the permit | |
| holder shall contract at the permit holder's expense with an | |
| independent, third-party engineer licensed in this state to: | |
| (1) evaluate the design, safety, and installation of | |
| the battery energy storage to ensure compliance with the | |
| requirements of this section; | |
| (2) produce a written report on the evaluation; and | |
| (3) provide the written report described by | |
| Subdivision (2) to the requesting municipality or county. | |
| Sec. 35.204. EMERGENCY OPERATIONS PLANS FOR RENEWABLE | |
| ENERGY GENERATION FACILITIES. (a) This section applies to a permit | |
| holder that owns or operates a renewable energy generation | |
| facility. | |
| (b) A permit holder to which this section applies shall file | |
| with the commission a site-specific emergency operations plan for | |
| each facility owned or operated by the permit holder, including | |
| emergency response and communications protocols for an equipment | |
| failure incident. | |
| (c) The permit holder shall offer to local fire departments | |
| training regarding responding to a fire at the facility. | |
| Sec. 35.205. EVIDENCE OF COMPLIANCE WITH STANDARDS. | |
| Evidence of compliance with state or local regulations is not | |
| sufficient to support a finding by a trier of fact that an owner or | |
| operator of renewable generation equipment or facilities was not | |
| negligent in an action arising out of a malfunction of or mitigation | |
| of a fire caused by renewable generation equipment or facilities. | |
| Sec. 35.206. WAIVER VOID; REMEDIES. (a) A provision of a | |
| renewable generation facility agreement that purports to waive a | |
| right or exempt a grantee from a liability or duty established by | |
| Section 35.207 or 35.208 is void. | |
| (b) A person who is harmed by a violation of Section 35.207 | |
| or 35.208 is entitled to appropriate injunctive relief to prevent | |
| further violation of Section 35.207 or 35.208. | |
| (c) The provisions of this section are not exclusive. The | |
| remedies provided in this section are in addition to any other | |
| procedures or remedies provided by other law. | |
| Sec. 35.207. REQUIRED AGREEMENT PROVISIONS ON FACILITY | |
| REMOVAL. (a) A renewable generation facility agreement must | |
| provide that the grantee is responsible for removing the grantee's | |
| renewable generation facilities from the landowner's property and | |
| that the grantee shall, in accordance with any other applicable | |
| laws or regulations, safely: | |
| (1) clear, clean, and remove from the property each | |
| piece of renewable generation equipment, including any | |
| transformers or substations; | |
| (2) for each foundation of renewable generation | |
| equipment, including a transformer or substation installed in the | |
| ground: | |
| (A) clear, clean, and remove the foundation from | |
| the ground to a depth of at least three feet below the surface grade | |
| of the land in which the foundation is installed; and | |
| (B) ensure that each hole or cavity created in | |
| the ground by the removal is filled with topsoil of the same type or | |
| a similar type as the predominant topsoil found on the property; | |
| (3) for each buried cable, including power, | |
| fiber-optic, and communications cables, installed in the ground: | |
| (A) clear, clean, and remove the cable from the | |
| ground to a depth of at least three feet below the surface grade of | |
| the land in which the cable is installed; and | |
| (B) ensure that each hole or cavity created in | |
| the ground by the removal is filled with topsoil of the same type or | |
| a similar type as the predominant topsoil found on the property; and | |
| (4) clear, clean, and remove from the property each | |
| overhead power or communications line installed by the grantee on | |
| the property. | |
| (b) The agreement must provide that, at the request of the | |
| landowner, the grantee shall: | |
| (1) clear, clean, and remove each road constructed by | |
| the grantee on the property; and | |
| (2) ensure that each hole or cavity created in the | |
| ground by the removal is filled with topsoil of the same type or a | |
| similar type as the predominant topsoil found on the property. | |
| (c) The agreement must provide that, at the request of the | |
| landowner, if reasonable, the grantee shall: | |
| (1) remove from the property all rocks over 12 inches | |
| in diameter excavated during the decommissioning or removal | |
| process; | |
| (2) return the property to a tillable state using | |
| scarification, V-rip, or disc methods, as appropriate; and | |
| (3) ensure that: | |
| (A) each hole or cavity created in the ground by | |
| the removal is filled with topsoil of the same type or a similar | |
| type as the predominant topsoil found on the property; and | |
| (B) the surface is returned as near as reasonably | |
| possible to the same condition as before the grantee dug holes or | |
| cavities, including by reseeding pastureland with native grasses | |
| prescribed by an appropriate governmental agency, if any. | |
| (d) The landowner shall make a request under Subsection (b) | |
| or (c) not later than the 180th day after the later of: | |
| (1) the date on which the renewable generation | |
| facility is no longer capable of generating or storing electricity | |
| in commercial quantities; or | |
| (2) the date the landowner receives written notice of | |
| intent to decommission the renewable generation facility from the | |
| grantee. | |
| Sec. 35.208. REQUIRED AGREEMENT PROVISIONS ON FINANCIAL | |
| ASSURANCE. (a) A renewable generation facility agreement must | |
| provide that the grantee shall obtain and deliver to the commission | |
| evidence of financial assurance payable to the landowner that | |
| conforms to the requirements of this section to secure the | |
| performance of the grantee's obligation to remove the grantee's | |
| renewable generation facilities located on the landowner's | |
| property as described by Section 35.207. The financial assurance | |
| may be a bond or another form of financial assurance acceptable to | |
| the landowner. | |
| (b) The amount of the financial assurance must be at least | |
| equal to the estimated amount by which the cost of removing the | |
| renewable generation facilities from the landowner's property and | |
| restoring the property to as near as reasonably possible the | |
| condition of the property as of the date the agreement begins | |
| exceeds the salvage value of the renewable generation facilities, | |
| less any portion of the value of the renewable generation | |
| facilities pledged to secure outstanding debt. | |
| (c) The agreement must provide that: | |
| (1) the estimated cost of removing the renewable | |
| generation facilities from the landowner's property and restoring | |
| the property to as near as reasonably possible the condition of the | |
| property as of the date the agreement begins, and the estimated | |
| salvage value of the renewable generation facilities must be | |
| determined by an independent, third-party professional engineer | |
| licensed in this state; | |
| (2) the grantee must deliver to the landowner and the | |
| commission an updated estimate, prepared by an independent, | |
| third-party professional engineer licensed in this state, of the | |
| cost of removal and the salvage value at least once every five years | |
| for the remainder of the term of the agreement; and | |
| (3) the grantee is responsible for ensuring that the | |
| amount of the financial assurance remains sufficient to cover the | |
| amount required by Subsection (b), consistent with the estimates | |
| required by this subsection. | |
| (d) The grantee is responsible for the costs of obtaining | |
| financial assurance described by this section and costs of | |
| determining the estimated removal costs and salvage value. | |
| (e) The agreement must provide that the grantee shall | |
| deliver the financial assurance to the commission not later than | |
| the 30th day after the date the agreement begins, or the permit may | |
| be denied or revoked. | |
| (f) The grantee may not cancel financial assurance before | |
| the date the grantee has completed the grantee's obligation to | |
| remove the grantee's renewable generation facilities located on the | |
| landowner's property as required by this chapter, unless the | |
| grantee provides the commission with replacement financial | |
| assurance at the time of or before the cancellation. In the event | |
| of a transfer of ownership of the grantee's renewable generation | |
| facilities, the financial security provided by the grantee shall | |
| remain in place until the date evidence of financial security | |
| meeting the requirements of this chapter is provided to the | |
| commission. | |
| Sec. 35.209. RELEASE OF FINANCIAL ASSURANCE TO GRANTEE. | |
| (a) At any time, a grantee may file an application with the | |
| commission for the release of all or part of a bond or other | |
| financial assurance provided to the commission by the grantee for a | |
| landowner under this subchapter. | |
| (b) The application must be on a form prescribed by the | |
| commission and, in addition to other information the commission may | |
| require, must include the type and the approximate date of removal | |
| and restoration work performed and a description of the results | |
| achieved. | |
| (c) The grantee shall provide a copy of the application to | |
| the landowner not later than the 30th day after the date the grantee | |
| files the application with the commission. | |
| (d) Not later than the 45th day after the date the grantee | |
| files the application, the commission shall conduct an inspection | |
| and evaluation of the removal and restoration work performed. | |
| (e) The commission may release all or part of the financial | |
| assurance if the commission determines that the grantee has | |
| completed all or part of the grantee's obligations under the | |
| agreement entered into under this subchapter. All of the financial | |
| assurance shall be released if all of the grantee's obligations are | |
| completed. | |
| (f) If the commission disapproves the application for | |
| release of the financial assurance, the commission shall notify the | |
| grantee in writing of the reasons for disapproval and recommend | |
| corrective actions necessary to secure the release of the financial | |
| assurance. | |
| Sec. 35.210. FORFEITURE OF FINANCIAL ASSURANCE TO | |
| LANDOWNER. (a) A landowner may file an application with the | |
| commission for the forfeiture of all or part of a bond or other | |
| financial assurance provided to the commission by a grantee for the | |
| landowner under this subchapter if: | |
| (1) the grantee has not completed the grantee's | |
| obligations under the agreement entered into under this subchapter; | |
| and | |
| (2) the facility that is the subject of the agreement | |
| is no longer being used by the grantee to provide energy or | |
| ancillary services at wholesale for a power grid in the manner | |
| provided by the agreement. | |
| (b) The application must be on a form prescribed by the | |
| commission. | |
| (c) The landowner shall provide a copy of the application to | |
| the grantee not later than the 30th day after the date the landowner | |
| files the application with the commission. | |
| (d) Not later than the 45th day after the date the landowner | |
| files the application, the commission shall conduct an inspection | |
| and evaluation of the property for which the financial assurance | |
| was provided. | |
| (e) The commission may approve the forfeiture of all or part | |
| of the financial assurance if the commission determines that: | |
| (1) the facility that is the subject of the agreement | |
| is no longer being used in the manner described by Subsection | |
| (a)(2); and | |
| (2) the forfeiture is necessary to compensate the | |
| landowner for any remaining removal and restoration work the | |
| grantee was required to but did not complete under the agreement. | |
| (f) If the commission disapproves the application for | |
| forfeiture of the financial assurance, the commission shall notify | |
| the landowner in writing of the reasons for disapproval. | |
| Sec. 35.211. COMMISSION AUTHORITY. (a) The commission may | |
| not issue to a grantee whose financial assurance was forfeited | |
| under Section 35.210 any permit, certificate, or registration under | |
| other law that authorizes the grantee to operate a generation | |
| facility to which this subchapter applies or renew any such permit, | |
| certificate, or registration. | |
| (b) In a suit for receivership, garnishment, or bankruptcy, | |
| or in any other legal action affecting the assets of a grantee that | |
| is a party to an agreement subject to this subchapter, the | |
| commission may: | |
| (1) inform the appropriate court and parties of the | |
| commission's interest in obtaining notice of the proceedings; and | |
| (2) within the time prescribed by the applicable | |
| statutes, rules, and court orders, intervene and participate in any | |
| proceedings that affect a landowner not joined in the suit who is a | |
| party to the agreement with the grantee. | |
| SECTION 3. The changes in law made by this Act apply only to | |
| a renewable generation facility agreement entered into on or after | |
| the effective date of this Act. An agreement entered into before | |
| the effective date of this Act is governed by the law applicable to | |
| the agreement on the date the agreement was entered into, and that | |
| law is continued in effect for that purpose. | |
| SECTION 4. As soon as practicable after the effective date | |
| of this Act, the Public Utility Commission of Texas shall adopt | |
| rules to effectuate the changes in law made by this Act. | |
| SECTION 5. This Act takes effect immediately if it receives | |
| a vote of two-thirds of all the members elected to each house, as | |
| provided by Section 39, Article III, Texas Constitution. If this | |
| Act does not receive the vote necessary for immediate effect, this | |
| Act takes effect September 1, 2025. |
Official text from the Texas Legislature. Formatting has been adapted for reading on Ratifi.