Introduced
Underlined text would be added to current law. Struck-through text would be removed.
| By: Wilson | H.B. No. 873 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to air quality permits for aggregate production operations | |
| and concrete batch plants. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subchapter C, Chapter 382, Health and Safety | |
| Code, is amended by adding Sections 382.051991 and 382.051992 to | |
| read as follows: | |
| Sec. 382.051991. USE OF STANDARD PERMIT FOR AGGREGATE | |
| PRODUCTION OPERATIONS AND CONCRETE BATCH PLANTS: PUBLIC HEARING OR | |
| MEETING. (a) This section applies only to a public hearing or | |
| meeting regarding an authorization to use a standard permit under | |
| this chapter for: | |
| (1) the production of aggregates, as defined by | |
| Section 28A.001, Water Code; or | |
| (2) the operation of a concrete plant that performs | |
| wet batching, dry batching, or central mixing. | |
| (b) The commission shall accept written questions about the | |
| facility from the public until the 15th day before the date of the | |
| hearing or meeting. | |
| (c) Not later than the 14th day before the date of the | |
| hearing or meeting, the commission shall notify the following | |
| entities of the date, time, and place of the hearing or meeting: | |
| (1) the Texas Department of Transportation; | |
| (2) each groundwater conservation district with | |
| jurisdiction over the area in which the facility is located or | |
| proposed to be located; | |
| (3) if no groundwater conservation district has | |
| jurisdiction over the area in which the facility is located or | |
| proposed to be located, the Texas Water Development Board; | |
| (4) any state agency with jurisdiction over a topic | |
| raised in a written question submitted to the commission under | |
| Subsection (b); and | |
| (5) each municipality and county in which the facility | |
| is located or proposed to be located. | |
| (d) Each entity other than a municipality or county that | |
| receives notice of a hearing or meeting under Subsection (c) shall | |
| send a representative of the entity to attend the hearing or | |
| meeting. | |
| Sec. 382.051992. ADDITIONAL STANDARD PERMIT REQUIREMENTS | |
| FOR AGGREGATE PRODUCTION OPERATIONS AND CONCRETE BATCH PLANTS. (a) | |
| This section applies only to the use of a standard permit under this | |
| chapter for: | |
| (1) the production of aggregates, as defined by | |
| Section 28A.001, Water Code; or | |
| (2) the operation of a concrete plant that performs | |
| wet batching, dry batching, or central mixing. | |
| (b) The commission may not authorize the use of a standard | |
| permit for or renew a standard permit authorization for a facility | |
| unless the applicant indicates on the application that the | |
| applicant: | |
| (1) has complied with the requirements of Subsection | |
| (c); and | |
| (2) will comply with any Texas Department of | |
| Transportation requirements for the construction or alteration of | |
| driveways as provided by Subsection (j). | |
| (c) In addition to requirements in any other applicable | |
| provision of this chapter, a person authorized to use a standard | |
| permit must: | |
| (1) install equipment to monitor noise levels from the | |
| facility: | |
| (A) at the point on the perimeter of the property | |
| on which the facility is located that is closest to the nearest | |
| building in use as a single-family or multifamily residence, | |
| school, place of worship, or commercial enterprise; and | |
| (B) at two other points on the perimeter of the | |
| property on which the facility is located equidistant from the | |
| point described by Paragraph (A); | |
| (2) ensure that outdoor lighting installed at the | |
| facility complies with standards adopted by the Illuminating | |
| Engineering Society; | |
| (3) obtain computer-controlled blasting technology to | |
| minimize the effect of seismic forces on adjacent property caused | |
| by blasting at the facility; | |
| (4) either: | |
| (A) use water for the facility only from a | |
| metered source or under a permit from a groundwater conservation | |
| district; or | |
| (B) implement commission-approved methods of | |
| water recirculation to ensure efficient use of groundwater for the | |
| facility; | |
| (5) provide to the commission a plan to ensure that the | |
| area on which the facility operates will be safe and useful after | |
| operations cease, including a description of how the person will: | |
| (A) resolve potential safety and environmental | |
| problems; | |
| (B) minimize fugitive dust from areas the person | |
| does not plan to revegetate; and | |
| (C) control erosion by revegetating barren | |
| areas; and | |
| (6) provide to the commission a performance bond or | |
| other form of financial assurance to ensure payment of the costs of | |
| executing the plan required by Subdivision (5). | |
| (d) The commission is not required to inspect a facility | |
| solely to verify compliance with Subsection (c). The commission | |
| shall inspect a facility for compliance with Subsection (c) during | |
| regular inspections under this chapter and Chapter 28A, Water Code. | |
| (e) The commission shall publish a list of monitoring | |
| equipment that a person may use to meet the requirements of | |
| Subsection (c)(1). | |
| (f) The person shall maintain records of monitoring data | |
| from the equipment required by Subsection (c)(1) until the fifth | |
| anniversary of the date on which the data was collected. | |
| (g) The person authorized to use a standard permit shall | |
| ensure that noise created by the permitted facility does not | |
| exceed: | |
| (1) 70 decibels at the points at which monitors are | |
| installed under Subsection (c); or | |
| (2) 65 decibels at the perimeter of a property that is: | |
| (A) used as a residence; and | |
| (B) located within 880 yards of the permitted | |
| facility. | |
| (h) If the commission receives a complaint about noise | |
| created by a permitted facility, the commission shall require the | |
| person authorized to use the permit to submit to the commission all | |
| relevant available monitoring data from the monitoring equipment | |
| required by Subsection (c)(1) collected for a time period beginning | |
| 30 days before the date that is the subject of the complaint and | |
| ending 30 days after that date. The commission shall analyze the | |
| data before determining whether the complaint is valid. | |
| (i) The commission is authorized to: | |
| (1) receive funds as the beneficiary of a financial | |
| assurance mechanism required under Subsection (c); and | |
| (2) expend funds from the financial assurance | |
| mechanism to ensure that the area on which the permitted facility | |
| operated is safe and useful. | |
| (j) If the Texas Department of Transportation determines | |
| that activities at a facility necessitate the construction or | |
| modification of driveway access to or from a state highway, | |
| including to meet any applicable requirements under Chapter 133, | |
| Natural Resources Code, the person authorized to use a standard | |
| permit for the facility shall enter into a donation agreement with | |
| the department for the donation of costs or property needed by the | |
| state to facilitate the construction or alteration. | |
| SECTION 2. (a) Except as provided by Subsection (b) of this | |
| section, the changes in law made by this Act apply only to a permit | |
| or an authorization to use a permit for which an application is | |
| submitted to the Texas Commission on Environmental Quality on or | |
| after the effective date of this Act. A permit or an authorization | |
| to use a permit for which an application was submitted to the Texas | |
| Commission on Environmental Quality before the effective date of | |
| this Act is governed by the law in effect immediately before the | |
| effective date of this Act, and the former law is continued in | |
| effect for that purpose. | |
| (b) The changes in law made by this Act apply to a permit or | |
| an authorization to use a permit for which an application for | |
| renewal is submitted to the Texas Commission on Environmental | |
| Quality on or after January 1, 2027. | |
| SECTION 3. This Act takes effect January 1, 2026. |