SB 293089th Legislature (2025)

Relating to a certificate of public convenience and necessity to construct an electric transmission line.

Introduced

Underlined text would be added to current law. Struck-through text would be removed.

  89R9042 SCR-D
 
  By: Sparks S.B. No. 2930
 
 
  A BILL TO BE ENTITLED
  AN ACT
  relating to a certificate of public convenience and necessity to
  construct an electric transmission line.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 37.052(c), Utilities Code, is amended to
  read as follows:
         (c)  An electric utility is not required to amend the
  utility's certificate of public convenience and necessity to
  construct a transmission line that connects the utility's existing
  transmission facilities to a substation or metering point if:
               (1)  the transmission line does not exceed:
                     (A)  five [three] miles in length, if the line
  connects to a load-serving substation or metering point; or
                     (B)  two miles in length, if the line connects to a
  generation substation or metering point;
               (2)  each landowner whose property would be directly
  affected by the transmission line, as provided by commission rules,
  provides written consent for the transmission line; and
               (3)  all rights-of-way necessary for construction of
  the transmission line have been purchased.
         SECTION 2.  This Act takes effect September 1, 2025.