Introduced
Underlined text would be added to current law. Struck-through text would be removed.
| 89R10526 ANG-D | ||
| By: Hall, Sparks | S.B. No. 1692 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to a limitation on wind and solar installed generation | |
| capacity in the ERCOT power region. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Section 39.1592(a), Utilities Code, is amended | |
| to read as follows: | |
| (a) This section applies only to an electric generation | |
| facility in the ERCOT power region for which a standard generator | |
| interconnection agreement is signed on or after September 1, 2025 | |
| [ |
|
| and that is not a self-generator. | |
| SECTION 2. Subchapter D, Chapter 39, Utilities Code, is | |
| amended by adding Section 39.1596 to read as follows: | |
| Sec. 39.1596. LIMITATION ON WIND AND SOLAR GENERATION | |
| CAPACITY. (a) This section applies only to an electric generation | |
| facility that: | |
| (1) exclusively relies on an energy source derived | |
| from wind or the sun; and | |
| (2) is subject to a standard generator interconnection | |
| agreement. | |
| (b) Not later than January 1, 2029, the commission shall | |
| determine whether the installed generation capacity from the | |
| electric generation facilities described by Subsection (a) is | |
| contributing more than 35 percent of the available generation | |
| capacity for the ERCOT power region at any time. | |
| (c) If the commission determines the installed generation | |
| capacity described by Subsection (b) contributes more than 35 | |
| percent of the available generation capacity for the ERCOT power | |
| region at any time, the commission shall by rule establish a program | |
| to require disconnection from the power grid of electric generation | |
| facilities as provided by this subsection. The program must: | |
| (1) require the disconnection from the power grid of | |
| only facilities for which a standard generator interconnection | |
| agreement was signed before September 1, 2025; and | |
| (2) establish a goal of reducing the installed | |
| generation capacity from facilities for which a standard generator | |
| interconnection agreement was signed before September 1, 2025, so | |
| that the installed capacity from all electric generation facilities | |
| exclusively relying on an energy source derived from wind or the sun | |
| contributes 35 percent or less of the available generation capacity | |
| for the ERCOT power region at any time. | |
| (d) After completion of the program required under | |
| Subsection (c), the commission may allow the installation of new | |
| generation capacity from an electric generation facility described | |
| by Subsection (a), regardless of the goal described by Subsection | |
| (c)(2), if the facility complies with Section 39.1592. | |
| SECTION 3. This Act takes effect immediately if it receives | |
| a vote of two-thirds of all the members elected to each house, as | |
| provided by Section 39, Article III, Texas Constitution. If this | |
| Act does not receive the vote necessary for immediate effect, this | |
| Act takes effect September 1, 2025. |
Official text from the Texas Legislature. Formatting has been adapted for reading on Ratifi.