Introduced
Underlined text would be added to current law. Struck-through text would be removed.
| 89R3447 CXP-F | ||
| By: Troxclair | H.B. No. 5582 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to the design-build method for certain government | |
| construction projects. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subchapter G, Chapter 2269, Government Code, is | |
| amended by adding Section 2269.3035 to read as follows: | |
| Sec. 2269.3035. ALTERNATIVE DESIGN-BUILD METHODS FOR WATER | |
| AND WASTEWATER INFRASTRUCTURE. (a) A governmental entity may use | |
| the following methods for the construction, rehabilitation, | |
| alteration, or repair of water or wastewater infrastructure: | |
| (1) a method in which a single fixed price for both | |
| design and construction is established at the time the contract | |
| with the design-build firm is signed by the parties, commonly known | |
| as "fixed price design-build"; or | |
| (2) a method in which the design-build firm is | |
| involved early in the process of developing the design and the | |
| contract includes a stepped payment scheme for design and | |
| construction services, commonly known as "progressive | |
| design-build." | |
| (b) The requirements of this subchapter apply to a method | |
| described by Subsection (a) to the extent practicable. | |
| SECTION 2. Section 2269.352, Government Code, is amended to | |
| read as follows: | |
| Sec. 2269.352. APPLICABILITY. This subchapter applies to a | |
| governmental entity, including [ |
|
| [ |
|
| [ |
|
| Transportation Code. | |
| SECTION 3. Section 2269.353(b), Government Code, is amended | |
| to read as follows: | |
| (b) A contract for a project under this subchapter may cover | |
| only a single integrated project. A governmental entity may not | |
| enter into a contract for aggregated projects at multiple | |
| locations. For purposes of this subsection: | |
| (1) if a metropolitan transit authority created under | |
| Chapter 451, Transportation Code, enters into a contract for a | |
| project involving a linear transit project with multiple stops | |
| along the project route for boarding passengers, created under | |
| Chapter 451, Transportation Code, the linear transit project is a | |
| single integrated project; and | |
| (2) a water or wastewater infrastructure project | |
| [ |
|
| treatment facilities, well fields, pump stations, water storage, | |
| and pipelines, is a single integrated project. | |
| SECTION 4. Subchapter H, Chapter 2269, Government Code, is | |
| amended by adding Section 2269.3535 to read as follows: | |
| Sec. 2269.3535. ALTERNATIVE DESIGN-BUILD PROCEDURES FOR | |
| WATER AND WASTEWATER INFRASTRUCTURE. (a) A governmental entity | |
| may use a design-build method described by Section 2269.3035(a) for | |
| the construction, rehabilitation, alteration, or repair of water or | |
| wastewater infrastructure. | |
| (b) The requirements of this subchapter apply to a method | |
| described by Subsection (a) to the extent practicable. | |
| SECTION 5. This Act takes effect September 1, 2025. |