Engrossed
Underlined text would be added to current law. Struck-through text would be removed.
| By: Darby | H.B. No. 3970 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to the interconnection and operation of large loads. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subchapter D, Chapter 39, Utilities Code, is | |
| amended by adding Section 39.169 to read as follows: | |
| Sec. 39.169. LARGE LOAD INTERCONNECTION. (a) In this | |
| section: | |
| (1) "Behind-the-meter generation" means a generation | |
| facility on the retail customer's side of the meter capable of | |
| serving the full load requirement of the retail customer. | |
| (2) "Flexible load" means a large load operated by a | |
| retail customer who is obligated by contract or agreement in the | |
| ERCOT market to reduce the load or power the load exclusively with | |
| back-up generation: | |
| (A) at the direction of the independent | |
| organization certified under Section 39.151 for the ERCOT power | |
| region; or | |
| (B) as required to protect the integrity of the | |
| ERCOT grid. | |
| (b) The commission by rule shall establish a program to | |
| provide an expedited process for the interconnection of large | |
| loads. The program must require the interconnecting electric | |
| cooperative, municipally owned utility, or transmission and | |
| distribution utility and the independent organization certified | |
| under Section 39.151 for the ERCOT power region to give priority in | |
| the interconnection queue to a large load for which a retail | |
| customer has received approval for expedited processing over any | |
| other large loads that have not entered into a contractual | |
| agreement with the electric utility, electric cooperative, or | |
| municipally owned utility regarding the provision of electric | |
| service. If applicable, the generation interconnection | |
| application for a generation facility associated with the large | |
| load must be processed in parallel with the large load. | |
| (c) The program must require a large load to qualify for | |
| expedited interconnection processing by bringing in-service, not | |
| later than the 180th day after the interconnection date, | |
| behind-the-meter generation that is: | |
| (1) registered with the independent organization | |
| certified under Section 39.151 for the ERCOT power region; and | |
| (2) capable of serving the full load requirement of | |
| the customer. | |
| (d) As an alternative to the requirements of Subsection (c), | |
| a large load may qualify for expedited interconnection processing, | |
| if the load is a facility with an aggregated peak demand at a single | |
| site of more than 75 megawatts, by: | |
| (1) providing to the interconnecting electric | |
| cooperative, municipally owned utility, or transmission and | |
| distribution utility all data regarding, and posting all required | |
| financial security for, the load; and | |
| (2) being subject to a binding commitment with the | |
| independent organization certified under Section 39.151 for the | |
| ERCOT power region to establish the load as a flexible load for a | |
| minimum period established by the commission, which must be at | |
| least 10 years. | |
| (e) A large load that qualifies for expedited | |
| interconnection processing may choose: | |
| (1) if authorized by the independent organization | |
| certified under Section 39.151 for the ERCOT power region and the | |
| relevant electric cooperative, municipally owned utility, or | |
| transmission and distribution utility, to contract with a vendor | |
| approved by the relevant electric cooperative, municipally owned | |
| utility, or transmission and distribution utility or by the | |
| independent organization to perform all studies required by the | |
| relevant electric cooperative, municipally owned utility, or | |
| transmission and distribution utility before the approval of the | |
| interconnection application; and | |
| (2) if authorized by the relevant electric | |
| cooperative, municipally owned utility, or transmission and | |
| distribution utility: | |
| (A) to procure equipment required for the | |
| interconnection in accordance with technical specifications | |
| provided by the relevant electric cooperative, municipally owned | |
| utility, or transmission and distribution utility; and | |
| (B) to construct interconnection facilities in | |
| accordance with technical and other requirements of the relevant | |
| electric cooperative, municipally owned utility, or transmission | |
| and distribution utility. | |
| (f) The program may provide that studies required by an | |
| electric cooperative, municipally owned utility, or transmission | |
| and distribution utility before the approval of an interconnection | |
| application for a flexible load may evaluate the load as non-firm. | |
| (g) Demand reductions from flexible loads that receive | |
| expedited processing and are removed from the system through the | |
| utilization of behind-the-meter generation during an energy | |
| emergency alert must be counted toward any obligation of the | |
| electric cooperative, municipally owned utility, or transmission | |
| and distribution utility to shed load. | |
| (h) The independent organization certified under Section | |
| 39.151 for the ERCOT power region shall consider action taken under | |
| this section as a reliability deployment when calculating any price | |
| adjustments for reliability deployments. | |
| (i) The commission shall establish financial penalties the | |
| commission may impose on an owner or operator of a large load that | |
| is approved for expedited interconnection processing but fails to | |
| reduce the load or power the load with back-up generation as | |
| directed by the independent organization certified under Section | |
| 39.151 for the ERCOT power region. | |
| SECTION 2. This Act takes effect September 1, 2025. |