Ratifi Español Sign in
Ratifi

Federal bills from Congress.gov. State bills from Open States.

HB 371289th Legislature (2025)

What changed between versions

59 paragraphs changed+372 words added−31 removed

Highlighted text was added in the newer version. Struck-through text was removed.

89R26827 SCR-F

By: Guillen

H.B. No. 3712

Substitute the following for H.B. No. 3712:

By: Button

C.S.H.B. No. 3712

A BILL TO BE ENTITLED

AN ACT

relating to funds reserved or retained for certain construction materials.

materials.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

SECTION 1. Section 532252.101032, PropertyGovernment Code, is amended by

amending Subsection (e) and adding Subsection (a-1e-1) to read as follows:

(a-1) An owner, contractor, or subcontractor may not

reserve funds under this section for specially fabricated material

that:

follows:

(e) A governmental entity may not withhold retainage:

(1) after completion of the work required to be

performed under the contract by the prime contractor, including

during the warranty period; [ or ]

(2) for the purpose of requiring the prime contractor,

after completion of the work required to be performed under the

contract, to perform work on manufactured goods or systems that

were:

(A) specified by the designer of record; and

(B) properly installed by the contractor ; or

(3) for specially fabricated material that:

(A) has been delivered by a subcontractor and

accepted by the governmental entity and the prime contractor at the

site or off-site; and

(B) is covered by a manufacturer's warranty:

(i) under a contract with the governmental

entity; or

(ii) assigned to the governmental entity by

the prime contractor .

(e-1) Subsection (e)(3) does not apply to funds for the

value of the installation of the specially fabricated material by a

subcontractor.

SECTION 2. Section 53.101, Property Code, is amended by

amending Subsection (a) and adding Subsections (a-1) and (a-2) to

read as follows:

(a) Except as provided by Subsection (a-1), during [ During ]

the progress of work under an original contract for which a

mechanic's lien may be claimed and for 30 days after the work under

the contract is completed, the owner shall reserve:

(1) 10 percent of the contract price of the work to the

owner; or

(2) 10 percent of the value of the work, measured by

the proportion that the work done bears to the work to be done,

using the contract price or, if there is no contract price, using

the reasonable value of the completed work.

(a-1) An owner is not required to reserve under this section

and may not retain under a contract funds for specially fabricated

material that:

(1) has been delivered by a subcontractor and accepted

by the owner, or a contractor, or subcontractor at the site or off-site;

and

off-site; and

(2) is covered by a manufacturer's warranty under a

contract with the owner, or a contractor, or subcontractor.

(a-2) Subsection (a-1) does not apply to funds for the value

of the installation of specially fabricated material by a

subcontractor.

SECTION 23. The changes in law made by this Act apply only to

an original contract that is entered into on or after the effective

3 unchanged paragraphs

date of this Act. An original contract entered into before the

effective date of this Act is governed by the law as it existed

immediately before the effective date of this Act, and the former

law is continued in effect for that purpose.

SECTION 34. This Act takes effect September 1, 2025.

Back to the full text