Introduced
Underlined text would be added to current law. Struck-through text would be removed.
| 89R14038 SCR/CJC-D | ||
| By: McLaughlin | H.B. No. 3580 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to renewable energy generation facilities. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subtitle F, Title 10, Government Code, is | |
| amended by adding Chapter 2278 to read as follows: | |
| CHAPTER 2278. PROHIBITION ON GRANTING OF INCENTIVES FOR RENEWABLE | |
| ENERGY GENERATION FACILITIES | |
| Sec. 2278.001. DEFINITIONS. In this chapter: | |
| (1) "Economic incentive" means a rebate, refund, or | |
| other monetary incentive offered by this state or a political | |
| subdivision of this state. | |
| (2) "Renewable energy generation facility" means a | |
| renewable energy generation facility to which Subchapter F, Chapter | |
| 35, Utilities Code, applies. | |
| (3) "Tax incentive" means an abatement, credit, | |
| discount, exclusion, exemption, limitation on taxable value, | |
| refund, special valuation, special accounting treatment, special | |
| appraisal method or provision, special rate, or special method of | |
| reporting authorized by state law or the state constitution that | |
| relates to a tax imposed by this state or a political subdivision of | |
| this state. | |
| Sec. 2278.002. PROHIBITION ON INCENTIVES AND RENEWAL OF | |
| INCENTIVES. (a) Except as otherwise provided by this chapter, | |
| neither this state nor a political subdivision of this state may | |
| provide an economic incentive or a tax incentive to a person for the | |
| construction, maintenance, or operation of a renewable energy | |
| generation facility. | |
| (b) An economic incentive or a tax incentive for the | |
| construction, maintenance, or operation of a renewable energy | |
| generation facility that was granted to a person before the date the | |
| incentive became disallowed under Subsection (a) may not be renewed | |
| after that date. | |
| Sec. 2278.003. EXCEPTION: PREVIOUSLY GRANTED INCENTIVES. | |
| Subject to Section 2278.002(b), a person who is receiving an | |
| economic incentive or a tax incentive from this state or a political | |
| subdivision of this state for the construction, maintenance, or | |
| operation of a renewable energy generation facility under an | |
| agreement that was executed before the date the incentive becomes | |
| disallowed under Section 2278.002(a) may continue to receive the | |
| incentive as provided under the terms of that agreement. | |
| SECTION 2. Chapter 35, Utilities Code, is amended by adding | |
| Subchapter F to read as follows: | |
| SUBCHAPTER F. RENEWABLE ENERGY GENERATION FACILITY PERMIT | |
| Sec. 35.201. DEFINITIONS. In this subchapter: | |
| (1) "Person" includes an electric cooperative and a | |
| municipally owned utility. | |
| (2) "Renewable energy generation facility" means: | |
| (A) a wind power facility as defined by Section | |
| 301.0001; or | |
| (B) a solar power facility as defined by Section | |
| 302.0001. | |
| Sec. 35.202. APPLICABILITY. (a) This subchapter applies | |
| only to a renewable energy generation facility that is intended to | |
| be used to sell energy or ancillary services at wholesale. | |
| (b) This subchapter applies to a renewable energy | |
| generation facility regardless of whether the facility is the | |
| subject of a wind power facility agreement or solar power facility | |
| agreement entered into under Chapter 301 or 302. | |
| Sec. 35.203. PERMIT REQUIRED; APPLICATION. (a) A person | |
| may not interconnect a renewable energy generation facility to a | |
| transmission facility unless the person holds a permit to operate a | |
| renewable energy generation facility issued by the commission under | |
| this subchapter. | |
| (b) A person may apply for a permit to operate a renewable | |
| energy generation facility by filing with the commission: | |
| (1) a description of the location of the facility; | |
| (2) a description of the type of facility; | |
| (3) any assumed business or professional name of the | |
| applicant filed under Chapter 71, Business & Commerce Code; | |
| (4) an impact review described by Subsection (c); and | |
| (5) any other information required by commission rule. | |
| (c) A person who applies for a permit under this subchapter | |
| must conduct an impact review of the facility to be permitted. The | |
| impact review must evaluate the potential effects of the facility | |
| relating to the following: | |
| (1) the land in the area of the facility, including the | |
| potential for degradation, potential for soil contamination, and | |
| subsequent possibility for the land to be used for agricultural | |
| purposes; | |
| (2) local water resources, including potential | |
| groundwater depletion, harmful runoff, and chemical contamination; | |
| (3) local wildlife, including potential habitat | |
| destruction and long-term effects on biodiversity; and | |
| (4) the local community and economy, including | |
| property values and infrastructure. | |
| (d) The commission shall publish each permit application | |
| received under this section, including the impact review, on the | |
| commission's Internet website at least 60 days before the | |
| commission approves or denies the permit. | |
| Sec. 35.204. APPROVAL OR DENIAL OF APPLICATION. The | |
| commission may approve an application only if: | |
| (1) the commissioners court of the county in which the | |
| renewable energy generation facility is located consents; and | |
| (2) the commission finds that issuance of the permit | |
| would not violate state law. | |
| Sec. 35.205. POWER TO REGULATE AND SUPERVISE. (a) For | |
| purposes of this subchapter, a provision of Subchapter B or E, | |
| Chapter 14, that authorizes the commission to regulate a public | |
| utility also applies to a person required to obtain a permit under | |
| this subchapter, including an electric cooperative and a | |
| municipally owned utility. | |
| (b) The commission may adopt and enforce rules reasonably | |
| required in the exercise of its powers under this subchapter. | |
| Sec. 35.206. ENFORCEMENT AND PENALTIES. For the purposes | |
| of enforcing this subchapter, a reference in Chapter 15 to a person | |
| includes any person required to obtain a permit under this | |
| subchapter, including an electric cooperative and a municipally | |
| owned utility. | |
| SECTION 3. Chapter 2278, Government Code, as added by this | |
| Act, applies to an economic incentive or a tax incentive received by | |
| a person regardless of the date the person first began receiving the | |
| incentive and irrespective of whether the incentive is the subject | |
| of an agreement between the person and this state or a political | |
| subdivision of this state. | |
| SECTION 4. This Act takes effect immediately if it receives | |
| a vote of two-thirds of all the members elected to each house, as | |
| provided by Section 39, Article III, Texas Constitution. If this | |
| Act does not receive the vote necessary for immediate effect, this | |
| Act takes effect September 1, 2025. |
Official text from the Texas Legislature. Formatting has been adapted for reading on Ratifi.