| relating to a capacity cost recovery rider for certain electric | |
| utilities. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Subchapter E, Chapter 36, Utilities Code, is | |
| amended by adding Section 36.216 to read as follows: | |
| Sec. 36.216. RECOVERY OF ANNUAL CAPACITY-RELATED COSTS. | |
| (a) This section applies only to an electric utility that operates | |
| solely outside of ERCOT in areas of this state included in the | |
| Southeastern Electric Reliability Council. | |
| (b) It is the intent of the legislature that: | |
| (1) an electric utility's recovery of capacity-related | |
| costs and return of capacity-related revenues, which may fluctuate, | |
| should be accomplished as contemporaneously as possible with the | |
| incurrence of those costs and the receipt of those revenues; and | |
| (2) a regulatory authority should presume to be just | |
| and reasonable capacity-related costs incurred or capacity-related | |
| revenues received through an electric utility's participation in a | |
| multi-state auction operated by a regional transmission | |
| organization or independent system organization authorized by the | |
| Federal Energy Regulatory Commission, as well as those costs and | |
| revenues incurred or received under a power purchase agreement | |
| under the jurisdiction of the Federal Energy Regulatory Commission, | |
| and any associated refund or surcharge. | |
| (c) On application by an electric utility, the commission | |
| shall establish a capacity cost recovery rider that can be updated | |
| at least annually and that ensures timely: | |
| (1) recovery of the utility's costs that are eligible | |
| as provided by Subsection (d); and | |
| (2) return of the utility's revenues that are eligible | |
| as provided by Subsection (d). | |
| (d) In this section, eligible costs and revenues include: | |
| (1) costs and revenues associated with the electric | |
| utility's participation in a multi-state capacity auction operated | |
| by a regional transmission organization or independent system | |
| organization authorized by the Federal Energy Regulatory | |
| Commission; and | |
| (2) capacity-related costs and revenues associated | |
| with the utility's participation in power purchase agreements under | |
| the jurisdiction of the Federal Energy Regulatory Commission, | |
| including associated refunds and surcharges ordered by the Federal | |
| Energy Regulatory Commission, to the extent the costs and revenues | |
| are not included in the utility's base rates. | |
| (e) In each base rate proceeding following the | |
| establishment of a capacity cost recovery rider, the regulatory | |
| authority shall adjust the revenue requirement and rates of the | |
| electric utility's capacity cost recovery rider to include all | |
| eligible costs and revenues. The electric utility may not continue | |
| to include eligible costs or revenues in the utility's base rates | |
| unless the utility seeks and the commission approves termination of | |
| the utility's capacity cost recovery rider in a subsequent base | |
| rate proceeding. | |
| (f) The annual revenue requirement and rates for a proposed | |
| capacity cost recovery rider must include: | |
| (1) the electric utility's calculated costs or | |
| revenues for the upcoming year beginning on the June 1 associated | |
| with the utility's participation in a multi-state capacity auction; | |
| (2) the utility's costs or revenues for the upcoming | |
| year beginning on the June 1 associated with any power purchase | |
| agreements under the jurisdiction of the Federal Energy Regulatory | |
| Commission, including any associated refunds or surcharges | |
| required by a Federal Energy Regulatory Commission order issued in | |
| the previous 12-month period; and | |
| (3) a true-up amount that accounts for any difference | |
| between the utility's actual eligible costs and revenues and the | |
| utility's actual collections under any capacity cost recovery rider | |
| put into effect two years before the proposed effective date of the | |
| proposed rider, plus: | |
| (A) an amount to account for any mathematical | |
| error identified in the utility's most recent capacity cost | |
| recovery rider application proceeding; and | |
| (B) an amount to account for any refunds or | |
| surcharges ordered by the Federal Energy Regulatory Commission or | |
| by a regional transmission organization or independent system | |
| organization related to a previous year's capacity auction that: | |
| (i) are identified on a regional | |
| transmission organization or independent system operator | |
| settlement statement; or | |
| (ii) were directed by a Federal Energy | |
| Regulatory Commission order issued in the previous 12-month period. | |
| (g) The commission shall process an application to | |
| establish or update a capacity cost recovery rider in accordance | |
| with Subsections (h)-(k). | |
| (h) For a capacity cost recovery rider that will include an | |
| electric utility's costs to be incurred beginning on June 1 of a | |
| given year, the utility must submit the rider application not later | |
| than: | |
| (1) May 15 of that year; or | |
| (2) if the regional transmission organization or | |
| independent system operator publishes its capacity auction cost | |
| results after the 20th business day of April of that year, a date | |
| that is the same number of days after May 15 of that year as the | |
| number of days after the 20th business day of April the results were | |
| published. | |
| (i) A response to the electric utility's filing that is made | |
| by commission staff or an intervenor: | |
| (1) must be filed not later than the seventh day after | |
| the date of the utility's filing; and | |
| (2) may address only the mathematical accuracy of the | |
| utility's proposed capacity cost recovery rider revenue | |
| requirement and rates. | |
| (j) An inaccuracy identified under Subsection (i)(2) may be | |
| addressed only in the electric utility's next capacity cost | |
| recovery rider application. | |
| (k) The regulatory authority shall issue an order approving | |
| an electric utility's proposed capacity cost recovery rider not | |
| later than the 10th day after receipt of the utility's application. | |
| The electric utility may begin billing the rates proposed in the | |
| approved application for service rendered after the May 31 after | |
| the application is filed. | |
| SECTION 2. An electric utility to which Section 36.216, | |
| Utilities Code, as added by this Act, applies may file an | |
| application with a regulatory authority to recover eligible costs | |
| described by Section 36.216(d), Utilities Code, as added by this | |
| Act, to be incurred before September 1, 2026, regardless of whether | |
| the Public Utility Commission of Texas has adopted any rules | |
| regarding capacity cost recovery riders. Not later than the 10th | |
| date after the date the application is filed, the regulatory | |
| authority shall issue an order authorizing the electric utility to | |
| begin imposing the rates proposed in the application for service | |
| rendered during or after the first billing cycle of the month | |
| following the issuance of the order. | |
| SECTION 3. This Act takes effect immediately if it receives | |
| a vote of two-thirds of all the members elected to each house, as | |
| provided by Section 39, Article III, Texas Constitution. If this | |
| Act does not receive the vote necessary for immediate effect, this | |
| Act takes effect September 1, 2025. |
Official text from the Texas Legislature. Formatting has been adapted for reading on Ratifi.