House Committee Report
Underlined text would be added to current law. Struck-through text would be removed.
| 89R20942 JXC-D | ||
| By: Landgraf | H.B. No. 1710 | |
| Substitute the following for H.B. No. 1710: | ||
| By: Turner | C.S.H.B. No. 1710 |
| A BILL TO BE ENTITLED | |
| AN ACT | |
| relating to the issuance of a certificate of convenience or | |
| necessity for a facility to import or export power into or out of | |
| the ERCOT power region. | |
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | |
| SECTION 1. Section 37.051, Utilities Code, is amended by | |
| amending Subsections (c-1), (c-2), and (c-3) and adding Subsection | |
| (c-4) to read as follows: | |
| (c-1) Notwithstanding any other provision of this title | |
| except Section 11.009, and except as provided by Subsection (c-3) | |
| [ |
|
| owned utility, may not interconnect a facility to the ERCOT | |
| transmission grid that enables additional power to be imported into | |
| or exported out of the ERCOT power grid unless: | |
| (1) the interconnection is approved by the Federal | |
| Energy Regulatory Commission under Section 210, 211, or 212 of the | |
| Federal Power Act (16 U.S.C. Section 824i, 824j, or 824k), and not | |
| under Section 203, 205, or 206 of the Federal Power Act (16 U.S.C. | |
| Section 824b, 824d, or 824e); and | |
| (2) the person obtains a certificate from the | |
| commission stating that public convenience and necessity requires | |
| or will require the interconnection. | |
| (c-2) A person described by Subsection (c-1) [ |
|
| must apply for the certificate not later than the 180th day before | |
| the date the person seeks any order from the Federal Energy | |
| Regulatory Commission related to the interconnection. The | |
| commission shall apply Section 37.056 in considering an application | |
| under this subsection. In addition, the commission must determine | |
| that the application is consistent with the public interest before | |
| granting the certificate. The commission may adopt rules necessary | |
| to implement this subsection. This subsection does not apply to a | |
| facility that is in service on December 31, 2014. | |
| (c-3) [ |
|
| after the date the application is filed, shall approve an | |
| application [ |
|
| to be constructed under an interconnection agreement appended to an | |
| offer of settlement approved in a final order of the Federal Energy | |
| Regulatory Commission that was issued in Docket No. TX11-01-001 on | |
| or before December 31, 2014, directing physical connection between | |
| the ERCOT and SERC regions under Sections 210, 211, and 212 of the | |
| Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In | |
| approving the application, the commission may prescribe reasonable | |
| conditions to protect the public interest that are consistent with | |
| the final order of the Federal Energy Regulatory Commission. | |
| (c-4) [ |
|
| (c-3) is intended to restrict the authority of the commission or the | |
| independent organization certified under Section 39.151 for the | |
| ERCOT power region to adopt rules or protocols of general | |
| applicability. | |
| SECTION 2. This Act takes effect September 1, 2025. |
Official text from the Texas Legislature. Formatting has been adapted for reading on Ratifi.