H 3560Session 2025-2026

What changed between versions

27 paragraphs changed+115 words added−21 removed

Highlighted text was added in the newer version. Struck-through text was removed.

South Carolina General Assembly 126th Session, 2025-2026

Bill 3560

Download This Bill in Microsoft Word Format

Indicates Matter Stricken Indicates New Matter

(Text matches printed bills. Document has been reformatted to meet World Wide Web specifications.)

H. 3560

STATUS INFORMATION

General Bill Sponsors: Reps. Brewer, Murphy, Robbins and Mitchell Document Path: LC-0047CM25.docx

Introduced in the House on January 14, 2025 Education and Public Works

HISTORY OF LEGISLATIVE ACTIONS

Date

Body

Action Description with journal page number

12/5/2024

House

Prefiled

12/5/2024

House

Referred to Committee on Education and Public Works

1/14/2025

House

Introduced and read first time (House Journal-page 245)

1/14/2025

House

Referred to Committee on Education and Public Works (House Journal-page 245)

View the latest legislative information at the website

VERSIONS OF THIS BILL

12/05/2024

A bill

10 unchanged paragraphs

TO AMEND THE SOUTH CAROLINA CODE OF LAWS BY ADDING SECTION 57-5-1710 SO AS TO PROVIDE THE DEPARTMENT OF TRANSPORTATION MAY ESTABLISH AND IMPLEMENT A PROJECT TO AWARD CONTRACTS USING THE "PHASE DESIGN-BUILD" PROJECT DELIVERY METHOD.

Be it enacted by the General Assembly of the State of South Carolina:

SECTION 1. Article 11, Chapter 5, Title 57 of the S.C. Code is amended by adding:

Section 57-5-1710. (A) As contained in this section, "Phase Design-Build" means a project delivery method that uses a stepped, or progressive qualifications-based selection process, followed by a progression to a contract price. The Department of Transportation must select the Phase Design-Build team exclusively on qualifications, without consideration of schedule or costs, which must deliver the project in two distinct phases with two separate contracts. The Phase Design-Build team is initially under contract for preconstruction activities including, but not limited to, developing preliminary designs, performing constructability reviews, and developing construction schedules and pricing. If the department and the Phase Design-Build team reach agreement on a guaranteed maximum construction cost, the department and the Phase Design-Build team will execute a second contract for completion of the preliminary designs and construction of the project.

(B) The department may only award a contract under this section if the department:

(1) determines the project cost is less than five hundred million dollars ($500,000,000);

(2) determines that it is in the public's interest to use the Phase Design-Build project delivery method; and

(3) prequalifies the prime contractor and lead designer firm that will be awarded the contract.

(C) The department shall develop and implement Phase Design-Build guidelines prior to awarding contracts pursuant to this section.

SECTION 2. This act takes effect upon approval by the Governor.

----XX----

This web page was last updated on DecemberJanuary 0614, 20242025 at 121:4248 PM