SENATE ECONOMIC GROWTH COMMITTEE

STATEMENT TO

LEGISLATIVE FISCAL ESTIMATE

SENATE, No. 2189

STATE OF NEW JERSEY

222nd LEGISLATURE

DATED: FEBRUARYOCTOBER 1215, 2026

The Senate Economic Growth Committee reports favorably Senate Bill No. 2189.

As reported, this bill requires the Board of Public Utilities (board) to study the potential deployment of advanced transmission technologies (ATT) by electric public utilities in the State. In conducting the study, the board is to: (1) evaluate the attributes, functions, costs, and benefits of ATT, considering certain factors outlined in the bill; (2) evaluate the potential of each ATT to enable an electric public utility to provide safe, reliable, and affordable electricity to its customers, considering existing and planned transmission infrastructure and projected demand growth; (3) evaluate the potential of each of the ATT studied for deployment by a utility to identify and mitigate grid congestion in order to maximize the cost-effectiveness of delivery of energy resources in the near term; (4) identify potential reductions in an electric public utility’s transmission project costs and transmission project completion timelines by deploying ATT, as compared to traditional transmission infrastructure; (5) identify potential ways to streamline the deployment of ATT; (6) evaluate policies and laws in other states that have deregulated energy sectors, which polices and laws concern ATT, and provide recommendations, taking into consideration such policies and laws, to enable and encourage the adoption of ATT in this State; (7) identify processes or ways that an end-use customer can invest in and deploy ATT in partnership with their respective electric public utility to allow for the more rapid deployment of ATT; (8) identify how the board can support and encourage the implementation of ATT in New Jersey; and (9) evaluate any other aspect of ATT that the board determines will assist policymakers, electric public utilities, electric public utility customers, and other stakeholders in understanding the potential role of ATT in the transmission system serving this State and the region.

While conducting the study, the board is required to give notice of a public stakeholder meeting and invite interested parties and members of the public to discuss the study. The board is to hold at least two public stakeholder meetings to review comments from stakeholders.

In addition, the bill requires the board, within one year after the bill’s date of enactment, to submit a written report to the Governor and the Legislature with the findings of its study. The board is to publish the report on its Internet website.

Under the bill, “advanced transmission technology” means any software or hardware technology that increases the capacity, efficiency, reliability, or safety of an existing or new electric transmission facility, including: (1) grid enhancing technology; (2) advanced or high-performance conductors; and (3) other technology designed to reduce transmission congestion or increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission facility.

This bill was prefiled for introduction in the 2026-2027 session pending technical review. As reported, the bill includes the changes required by technical review, which has been performed.

SUMMARY

Synopsis:

Requires BPU to study potential deployment of advanced transmission technologies in NJ.

Type of Impact:

One-time State expenditure increase.

Agencies Affected:

New Jersey Board of Public Utilities.

Office of Legislative Services Estimate

Fiscal Impact

One-Time

State Expenditure Increase

Indeterminate

· The Office of Legislative Services (OLS) concludes that this bill will result in a one-time State expenditure increase of indeterminate magnitude attributable to the Board of Public Utilities conducting the required study, holding at least two public stakeholder meetings, preparing the required report, and publishing the report on the board’s website.

· The board may incur administrative expenses associated with research, stakeholder outreach, public meetings, report preparation, and publication. The OLS anticipates that the board may be able to absorb a large portion of the administrative expenses using existing staff and resources.

· The bill does not require electric public utilities to deploy advanced transmission technologies or undertake capital projects, and as such is not expected to increase ratepayer costs, or State and local utility costs. Any future fiscal impact would depend on subsequent board action or rulemaking based upon the findings of the study.

BILL DESCRIPTION

This bill requires the board to study the potential deployment of advanced transmission technologies by electric public utilities in the State. The study is required to evaluate, in part, the costs, benefits, feasibility, and potential ratepayer impacts of grid enhancing technology, advanced or high-performance conductors, and other technology designed to reduce transmission congestion or increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission facility.

This bill requires the board to give notice of a public stakeholder meeting and invite interested parties and members of the public to discuss the study. The board is to hold at least two public stakeholder meetings to review comments from stakeholders.

In addition, the bill requires the board, within one year after the bill’s date of enactment, to submit a written report to the Governor and the Legislature with the findings of the board’s study. The board is to publish the report on its Internet website.

FISCAL ANALYSIS

EXECUTIVE BRANCH

None received.

OFFICE OF LEGISLATIVE SERVICES

The OLS concludes that this bill will result in a one-time State expenditure increase of indeterminate magnitude attributable to conducting the required study, holding at least two public stakeholder meetings, preparing the required report, and publishing the report on the board’s website.

The board may incur administrative expenses associated with research, stakeholder outreach, public meetings, report preparation, and publication. The OLS anticipates that the board may be able to absorb a large portion of the administrative expenses using existing staff and resources. Additionally, due to the technical analysis in the study that is required by the bill, the board may incur additional costs if the board contracts with outside consultants or technical experts.

Notably, the bill does not require electric public utilities to deploy advanced transmission technologies or undertake capital projects. As a result, the bill is not expected to increase ratepayer costs, or State and local utility costs. Any future fiscal impact would depend on subsequent board action or rulemaking based upon the findings of the study.

Section:

Authorities, Utilities, Transportation and Communications

Analyst:

Michael D. Walker Jr.

Associate Fiscal Analyst

Approved:

Thomas Koenig

Legislative Budget and Finance Officer

This legislative fiscal estimate has been produced by the Office of Legislative Services due to the failure of the Executive Branch to respond to our request for a fiscal note.

This fiscal estimate has been prepared pursuant to P.L.1980, c.67 (C.52:13B-6 et seq.).