1 A bill to be entitled
1
2 An act relating to mitigation banks; amending s.
533 unchanged paragraphs
3 373.4136, F.S.; beginning on a specified date,
4 revising the schedule for credit release upon issuance
5 of a mitigation bank credit permit; providing
6 specifications for such schedule; authorizing a
7 mitigation bank applicant to propose an alternative
8 credit release schedule; requiring the Department of
9 Environmental Protection or water management district
10 to modify an existing permitted credit release
11 schedule upon request under certain circumstances;
12 prohibiting mitigation credits from being released for
13 freshwater wetland creation until certain conditions
14 are met; authorizing one-time use of mitigation
15 credits outside the mitigation bank service area in
16 certain circumstances; requiring the department and
17 water management districts to apply proximity factor
18 multipliers in a specified manner; specifying that the
19 use of certain multipliers meets certain requirements;
20 requiring the department or water management district
21 to request an accounting of credit availability from
22 mitigation banks within a specified timeframe;
23 specifying the timeframe to reply to such request;
24 requiring the permit applicant to be notified of
25 credits available; providing a presumption if a
26 mitigation bank does not respond within a certain
27 timeframe; limiting the timeframe for the permit
28 applicant to rely on a credit availability
29 determination for specified purposes; requiring each
30 mitigation bank to submit an accounting of credits;
31 requiring the department or water management district
32 to compile such accountings for a specified purpose
33 and to submit a report including certain information
34 to the Legislature on a specified date and annually
35 thereafter; providing an effective date.
36
37 Be It Enacted by the Legislature of the State of Florida:
38
39 Section 1. Subsections (5) and (6) of section 373.4136,
40 Florida Statutes, are amended to read:
41 373.4136 Establishment and operation of mitigation banks.—
42 (5) SCHEDULE FOR CREDIT RELEASE.—After
July 1, 2025, when
43
issuing
awarding mitigation credits to
a mitigation bank
permit
,
44 the department or the water management district shall
adhere to
45
the credit release
schedule
set forth
in paragraph (a)
a
46
schedule
for the release of
those
credits
awarded by
in
the
47 mitigation bank permit. A mitigation credit that has been
48 released may be sold or used to offset adverse impacts from an
49 activity regulated under this part.
50 (a)
1. T
hirty percent of awarded credits shall be released
51
upon the recordation of the conservation easement and
52
establishment of financial assurances required by the mitigation
53
bank permit. If a preservation-only assessment area is used, 100
54
percent of awarded credits shall be released for the recordation
55
of the conservation easement and establishment of financial
56
assurances required by the mitigation bank permit.
57
2.
Thirty percent of awarded credits shall be released
58
following completion of initial construction activities as
59
established by the mitigation bank permit.
60
3. Twenty percent of awarded credits shall be released in
61
increments as monitoring indicates interim performance criteria
62
established by the mitigation bank permit are being met.
63
4. Twenty percent of awarded credits shall be released upon
64
meeting final success criteria established by the mitigation
65
bank permit.
66
(b)
The mitigation bank applicant may propose an
67
alternative credit release schedule and the department or water
68
management district shall consider the proposed alternative
69
credit release schedule.
70
(c)
Upon request by a mitigation bank permittee for
71
modification of the credit release schedule of a permitted
72
mitigation bank, the department or relevant water management
73
district shall modify the credit release schedule to conform it
74
to paragraph (a) if such permitted mitigation bank has not yet
75
had mitigation credits released for the completion of
76
construction activities. The department or water management
77
district may not alter, change, or modify any other provision of
78
the mitigation bank permit unrelated to the credit release
79
schedule
The department or the water management district shall
80
allow a portion of the mitigation credits awarded to a
81
mitigation bank to be released for sale or use prior to meeting
82
all of the performance criteria specified in the mitigation bank
83
permit. The department or the water management district shall
84
allow release of all of a mitigation bank’s awarded mitigation
85
credits only after the bank meets the mitigation success
86
criteria specified in the permit
.
87
(b
)
The number of credits and schedule for release shall be
88
determined by the department or water management district based
89
upon the performance criteria for the mitigation bank and the
90
success criteria for each mitigation activity. The release
91
schedule for a specific mitigation bank or phase thereof shall
92
be related to the actions required to implement the bank, such
93
as site protection, site preparation, earthwork, removal of
94
wastes, planting, removal or control of nuisance and exotic
95
species, installation of structures, and annual monitoring and
96
management requirements for success. In determining the specific
97
release schedule for a bank, the department or water management
98
district shall consider, at a minimum, the following factors:
99
1. Whether the mitigation consists solely of preservation
100
or includes other types of mitigation.
101
2. The length of time anticipated to be required before a
102
determination of success can be achieved.
103
3. The ecological value to be gained from each action
104
required to implement the bank.
105
4. The financial expenditure required for each action to
106
implement the bank
.
107
(d)
(c)
Notwithstanding
the provisions of
this subsection,
a
108
mitigation
no
credit
may not
shall
be released for freshwater
109 wetland creation until the success criteria
established
included
110 in the mitigation bank permit
for initial construction
111
activities
are met.
112
(e)
(d)
The withdrawal of mitigation credits from a
113 mitigation bank shall be accomplished as a minor modification of
114 the mitigation bank permit. A processing fee
is not
shall not be
115 required by the department or water management district for this
116 minor modification.
117 (6) MITIGATION SERVICE AREA.—The department or water
118 management district shall establish a mitigation service area
119 for each mitigation bank permit. The department or water
120 management district shall notify and consider comments received
121 on the proposed mitigation service area from each local
122 government within the proposed mitigation service area. Except
123 as provided
in this section
herein
, mitigation credits may be
124 withdrawn and used only to offset adverse impacts in the
125 mitigation service area. The boundaries of the mitigation
126 service area shall depend upon the geographic area where the
127 mitigation bank could reasonably be expected to offset adverse
128 impacts. Mitigation service areas may overlap, and mitigation
129 service areas for two or more mitigation banks may be approved
130 for a regional watershed.
131 (a) In determining the boundaries of the mitigation service
132 area, the department or the water management district shall
133 consider the characteristics, size, and location of the
134 mitigation bank and, at a minimum, the extent to which the
135 mitigation bank:
136 1. Contributes to a regional integrated ecological network;
137 2. Will significantly enhance the water quality or
138 restoration of an offsite receiving water body that is
139 designated as an Outstanding Florida Water, a Wild and Scenic
140 River, an aquatic preserve, a water body designated in a plan
141 approved pursuant to the Surface Water Improvement and
142 Management Act, or a nationally designated estuarine preserve;
143 3. Will provide for the long-term viability of endangered
144 or threatened species or species of special concern;
145 4. Is consistent with the objectives of a regional
146 management plan adopted or endorsed by the department or water
147 management districts; and
148 5. Can reasonably be expected to offset specific types of
149 wetland impacts within a specific geographic area. A mitigation
150 bank need not be able to offset all expected impacts within its
151 service area.
152 (b) The department and water management districts shall use
153 regional watersheds to guide the establishment of mitigation
154 service areas. Drainage basins established pursuant to s.
155 373.414(8) may be used as regional watersheds when they are
156 established based on the hydrological or ecological
157 characteristics of the basin. A mitigation service area may
158 extend beyond the regional watershed in which the bank is
159 located into all or part of other regional watersheds when the
160 mitigation bank has the ability to offset adverse impacts
161 outside that regional watershed. Similarly, a mitigation service
162 area may be smaller than the regional watershed in which the
163 mitigation bank is located when adverse impacts throughout the
164 regional watershed cannot reasonably be expected to be offset by
165 the mitigation bank because of local ecological or hydrological
166 conditions.
167 (c) Once a mitigation bank service area has been
168 established by the department or a water management district for
169 a mitigation bank,
such mitigation bank shall be deemed to
170
implement a plan that provides regional ecological value;
such
171 service area shall be accepted by all water management
172 districts, local governments, and the department
; and the use of
173
credits from such mitigation bank to offset impacts within that
174
bank’s service area shall be considered to have met the
175
cumulative impact requirements of s. 373.414(8)(a)
.
176 (d) If the
provisions of
requirements in
s. 373.414(1)(b)
177 and (8) are met
and an insufficient number or type of credits
178
from banks whose permitted service area overlays in whole or in
179
part the regional watershed in which the impacts occur, the
180
permit applicant is entitled to a one-time use of credits
181
released from a mitigation bank outside the mitigation bank
182
service area to offset impacts pursuant to s. 373.414(1)(b), as
183
established by the procedure in paragraph (f). The
department or
184
water management district must have determined that the
185
mitigation service area lacked the appropriate credit type.
186
Priority must be given to mitigation banks whose permitted
187
service area fully includes the impacted site. If the number of
188
released credits within a mitigation service area only partially
189
offsets the impacts associated with a proposed project in the
190
mitigation service area, the permit applicant may only use out
191
of-service-area credits to account for the difference between
192
the released credits available in the mitigation bank service
193
area and the credits required to offset the impacts associated
194
with the proposed project. In implementing this subsection, the
195
department and water management districts shall apply a
196
proximity factor to determine adequate compensatory mitigation
197
as follows:
198
1. A 1.0 multiplier shall be applied for use of in-kind
199
credits within the service area.
200
2. A 1.0 multiplier shall be applied for use of in-kind and
201
out-of-service-area credits when the service area overlays part
202
of the same regional watershed as the proposed impacts only
203
after credit-deficiency has been established by the procedure
204
set forth in paragraph (f).
205
3. A 1.2 multiplier shall be applied for use of in-kind and
206
out-of-service-area credits located within a regional watershed
207
immediately adjacent to the regional watershed overlain by a
208
bank service area in which proposed impacts are located
only
209
after credit-deficiency has been established by the procedure
210
set forth in paragraph (f).
211
4. When in-kind credits are not available to offset impacts
212
in the regional watershed immediately adjacent to the regional
213
watershed overlain by a mitigation bank service area in which
214
the proposed impacts are located, an additional 0.25 multiplier
215
shall be applied for each additional regional watershed boundary
216
crossed only after credit-deficiency has been established by the
217
procedure set forth in paragraph (f).
218
5. An additional 0.50 multiplier shall be applied after any
219
multipliers required in subparagraphs 1.-4., if the mitigation
220
used to offset impacts entails out-of-kind replacement.
221
(e)
Use of the multipliers in subparagraphs (d)2., 3., 4.,
222
and 5. meets the requirements of s. 373.414(8)(a) for addressing
223
cumulative impacts.
224
(f)
Once
the amount of mitigation required to offset
225
impacts has been determined, and the department or water
226
management district determines
that out
-of-service-area or out
227
of-kind mitigation is necessary, the department or water
228
management district shall contact all mitigation banks with a
229
mitigation service area encompassing the location of the
230
proposed impacts within 7 business days after receipt of the
231
request from the permit applicant and request an accounting of
232
available credits, including out-of-kind credits. The accounting
233
may not include credits reserved for other permit applicants.
234
The mitigation banks contacted by the department or water
235
management district shall be allowed 15 business days after
236
receipt of the request by the department or water management
237
district to reply to such request. If one or more mitigation
238
banks replying to the request notifies the department or the
239
water management district that out-of-kind credits are available
240
to offset the proposed impact and the department or a water
241
management district determines that such out-of-kind credits are
242
appropriate to offset all or part of the proposed impact, the
243
department or the water management district shall notify the
244
permit applicant that sufficient credits are available within
245
that bank’s service area to offset the proposed impacts and the
246
use of credits from another mitigation bank outside of that
247
other mitigation bank’s service area may not occur until use of
248
all of the out-of-kind credits occurs as allowed by the
249
department or water management district
. If
a
mitigation
bank
250
does not reply within the 15 business day timeframe, it is
251
presumed credits
from that bank
are not available. Upon receipt
252
of the accounting from the mitigation banks, the department or
253
water management district shall determine if sufficient credits
254
are available to offset impacts associated with the proposed
255
project and notify the permit applicant of such determination
256
within 15 business days. The permit applicant, and no other
257
entity, may rely on the determination from the department or
258
water management district for a period of
6 months
beginning on
259
the date the department or water management district notifies
260
the permit applicant of such determination, but only for
261
purposes relating to the pending application producing such
262
determination and not any extensions, nor renewals, nor
263
modifications of any permit issued pursuant to that pending
264
application, nor for any other permit application.
265
(g) Beginning July 1, 2026, and each July 1 thereafter,
266
each mitigation bank in this state shall submit to the
267
department or water management district an accounting of the
268
number and type of credits the mitigation bank has available for
269
sale. The accounting may not include names of parties for which
270
credits have been reserved or the contract price paid for the
271
credits. The department or water management district shall
272
compile the information to provide an assessment of this state’s
273
mitigation banking system and submit a report to the President
274
of the Senate and the Speaker of the House of Representatives on
275
October 1, 2026, and each October 1 thereafter
,
the following
276
projects or activities regulated under this part shall be
277
eligible to use
a mitigation bank, regardless of whether they
278
are located within the mitigation service area
:
279
1. Projects with adverse impacts partially located within
280
the mitigation service area.
281
2. Linear projects, such as roadways, transmission lines,
282
distribution lines, pipelines, railways, or seaports listed in
283
s. 311.09(1).
284
3. Projects with total adverse impacts of less than 1 acre
285
in size
.
286 Section 2. This act shall take effect July 1, 2025.